HomeMy WebLinkAboutA001 - Council Action Form dated October 27, 2026ITEM #:22
DATE:10-27-26
DEPT:FLEET
SUBJECT:AMES ANIMAL SERVICES FACILITY - AWARD OF CONTRACT AND
CHANGE ORDER NO. 1
COUNCIL ACTION FORM
BACKGROUND:
The City has purchased the former Eagle's Loft Daycare property at 2715 Dayton Avenue in a
project to renovate and expand it into a new Ames Animal Services Facility. The City retained
INVISION Architecture LTD (INVISION), Des Moines, Iowa, to design the facility using best
practices outlined by the American Society of Veterinarians (ASV) Guidelines for Sheltering,
and meeting the requirements for Animal Welfare of the Iowa Department of Agriculture and
Land Stewardship (IDALS).
INVISION and its sub-consultants have worked with City staff and fundraisers to complete a
design of the facility, which is broken into three spaces: 1) cat spaces, 2) dog spaces, and 3)
human spaces. This design features an approximately 1,700 square-foot addition that will be
utilized as dog space and will have a flat roof to accommodate mechanical equipment.
BIDS:
The invitation to bid was issued on August 25, 2026. It contained eight add-alternates:
1. Dog run shade structures
2. Replace resilient corridor flooring with epoxy
3. Catio screens
4. Parking lot addition
5. Exterior building signage
6. Building automation
7. Wood-look metal entry trellis
8. Catio on south elevation
On September 30, 2026, bids were received as follows:
Bidders Base Bid
Add
Alternate
#1 - Dog
Run
Shade
Structures
Add
Alternate
#2 -
Epoxy
Flooring
Add
Alternate
#3 -
Wood
Look
Metal
Louvers
at Catio
Add
Alternate
#4 -
Parking
Lot
Addition
Add
Alternate
#5 -
Exterior
Building
Signage
Add
Alternate
#6 -
Building
Automation
Add
Alternate
#7 -
Wood
Look
Metal
Louver
at Entry
Add
Alternate
#8 - Catio
Enclosure
HPC, LLC,
Ames, IA $5,500,000 163,000 (11,000)45,000 66,000 71,000 53,000 45,000 120,000
1
Big Lake
Construction,
LLC, Des
Moines, IA
$5,698,000 199,000 (5,400)76,000 84,000 37,500 24,600 87,800 98,300
Munro
Construction
Co,
Johnston, IA
$5,733,000 99,000 (6,000)90,750 79,000 54,500 106,500 98,500 206,000
Ball Team,
LLC,
Urbandale,
IA
$5,786,530 146,690 - 132,376 75,955 68,048 48,278 112,403 161,409
Greiner
Construction,
Des Moines,
IA
$5,925,000 140,100 (16,800)137,400 83,400 68,700 103,500 115,900 192,100
Keystone
Construction
Services,
Waukee, IA
$6,200,000 88,000 (10,000)130,000 67,000 52,000 51,000 10,000 152,000
Kingland
Construction
Services,
Forest City,
IA
$6,600,000 330,000 160,000 137,000 76,000 58,000 25,000 115,000 95,000
The base bid received from HPC, the low bidder, is $5,500,000. The estimated construction
cost with no contingency was $5,441,081, leaving a shortfall of $58,919 if the base bid was to
be awarded. On October 13, 2027 City Council directed staff to evaluate the bids, project
budget, and evaluate Alternatives 1, 2, 3, 4, 5, 7 and 8 for inclusion in the project.
Following the bid opening, staff and the design team met with HPC to identify value
engineering items that could reduce the base bid without affecting the overall function of the
spaces. HPC has sent value engineering items to staff and the design team for review and
a p p rov a l. At this time, staff and the design team have agreed that changes to light
fixtures, construction methods, HVAC changes, and siding are acceptable and will not
change the usefulness of the building (see attachment for detailed information about
agreed changes, rejected changes, and pending changes).
The changes supported by the architect and staff to date reduce the base contract total
by $113,900. A change order to deduct this amount from the contract has been signed
by HPC and returned to staff. The City Council is being asked to award the contract and
approve Change Order #1 at this same meeting.
Several other value engineering items are still under review. Any changes resulting from this
review will be packaged into one or more subsequent changes for approval at a later date by
staff or City Council, as appropriate. Staff estimates the total savings from the changes,
inclusive of the items in Change Order #1, to be $150,000. Staff will attempt to finalize
these other items by the time the contract and bond are approved by Council.
Assuming the deducts total the anticipated $150,000 in savings, the construction cost would
be as follows:
2
ITEM AMOUNT
Base Bid $ 5,500,000
Estimated Base Bid Deducts (150,000)
Alternate 1 (Dog run shade structures)163,000
Alternate 2 (Epoxy flooring)(11,000)
Alternate 3 (Wood look metal louvers at catio)45,000
Alternate 4 (Parking lot addition)66,000
Alternate 5 (Exterior Building Signage)71,000
Alternate 7 (Wood look metal louver at Entry)45,000
Alternate 8 (Catio enclosure)120,000
Estimated Construction Contract Total $ 5,849,000
Construction contingency 250,000
Estimated total construction expenses 6,099,000
Shortfall from $5,441,081 construction budget ($657,919)
Staff has reviewed the funding available to address the shortfall. The private donations
received to date for the project have earned interest totaling $95,354. This amount can
be applied to the project as additional funding. City staff would recommend that the
remaining shortfall of $562,565 be financed from the Council Priorities Capital Fund.
This fund currently has a balance of $6,232,856.
At the conclusion of the project, any further interest earned on the deposited donation funds
will be applied to the project, and the balance of expenses up to the $562,565 amount will be
financed from the Council Priorities Capital Fund. Any funds remaining at the end of the
project will be returned to the Council Priorities Capital Fund.
The overall budget for this project, inclusive of design, site acquisition, and site investigation,
is shown below:
EXPENSES FUNDING SOURCES
Previous Site Investigation $
4,075
2715 Dayton Purchase Option 5,000
Site Acquisition 1,100,000
Conceptual Design 66,360
Design Change Order No. 1
(Detailed Design/Construction
Specs)
588,000
Design Change Order No. 2
(additional scope for Dog Run
access)
24,440
3
Construction/Renovation Base
Bid 5,500,000
Construction Bid Alternates 1,
2, 3, 4, 5, 7, & 8 499,000
Change Order #1 (113,900)
Anticipated Change Order #2 (36,100)
Contingency 250,000
FF&E/Permits 450,000
3rd Party Testing/Geotechnical 40,000
Stormwater Quality CIP
Funding $ 30,000
Sanitary Sewer Utility Fund 29,000
Shared Use Path
Maintenance Program
available balance (LOST)
16,500
FY 2023/24 General Fund
Savings 100,000
Council Priorities Capital
Fund 2,855,000
Donations 4,534,040
Supplemental Donation for
Dog Area Doors 154,416
Interest Earned on
Donations 95,354
Additional Funding from
Council Priorities Capital
Fund
562,565
TOTALS $
8,376,875 $ 8,376,875
ALTERNATIVES:
1. Approve final plans and specifications and award a contract to HPC, LLC of Ames, Iowa
in the amount of $5,500,000 for the base bid and Alternates 1, 2, 3, 4, 5, 7 & 8 for a total
of $5,999,000.
a. Approve Change Order #1, a deduct in the amount of $113,900.
b. Allocate $562,565 to the project from the Council Priorities Capital Fund. Any
unused funds will be returned to the Council Priorities Capital Fund.
c. Direct staff to further refine the potential cost savings and prepare change orders
4
as necessary to implement them.
2. Approve final plans and specifications and award a contract to HPC, LLC of Ames, Iowa
in the amount of $5,500,000.
a. Approve Change Order #1, a deduct in the amount of $113,900.
b. Approve a different combination of Alternates for award.
c. Allocate funding from the Council Priorities Capital Fund in the amount necessary
to finance the shortfall in funding and provide a $250,000 contingency.
3. Reject all bids, and direct staff to work with the design team to modify the project for
another invitation to bid.
CITY MANAGER'S RECOMMENDED ACTION:
The bids received for the Animal Services Facility project exceed the estimate and the
available funding for the project. Staff has had conversations with the design team and
the low bidder and a change order has been signed by the contractor that will reduce
the contract cost by $113,900. These changes are not expected to impact the function
of the building.
Further reductions are believed to be achievable, which should result in a total deduct
amount of approximately $150,000. In addition, Staff will continue to discuss these
issues with the contractor and will process further change orders as appropriate once
savings have been finalized.
In order to proceed with the alternates as directed by City Council on October 13, the
City Council will need to authorize the use of up to an additional $562,565 from the
Council Priorities Capital Fund. Any unused funding will be returned to that account at
the conclusion of construction.
Therefore, it is the recommendation of the City Manager that the City Council approve
Alternative #1a-c, as described above.
ATTACHMENT(S):
Animal Shelter Base Bid Deducts.pdf
5
Item Amount Status
1. Building Permit – Have the City waive the cost of
the permit $ 30,000.00 Rejected
2. Delete Section 099723 Concrete & Masonry
Coatings $ 24,000.00 Rejected
3. Delete insulation & vapor barrier above ceiling at
wall type W03 & W06 on sheet IN3.2 $ 32,000.00 Accepted
4. Change wall and soffit metal panels to 22 ga. In
lieu of 20ga. $ 29,000.00 Accepted
5. Electrical service entrance change from copper
to aluminum - $8,500 $ 8,500.00 Accepted
6. Electrical change light fixtures A2 & A2e to a flat
panel, and change exit signs & exterior lights to a
different brand
$ 19,500.00 Accepted
7. Alternate Mech louver options $ - In Review
8. Treated Dim Lumber instead of prebuck parapet
cap blocking @ addition $ 2,500.00 Accepted
9. Adjustments to door hardware quality or type. $ - In Review
10. Adjustments to door and frame quality or type. $ - In Review
11. Alternate roof systems. $ - In Review
13. Alternate rooftop mech equip? $ 22,400.00 Accepted
6