HomeMy WebLinkAbout~Master - Resolution approving Change Order No. 4 for the Resource Recovery and Recycling Campus with Jensen Builders, LTD., of Des Moines, IA, for Bid Package 3-1 - Concrete & Steel WorkRESOLUTION NO. 26-637
RESOLUTION APPROVING CHANGE ORDER NO. 4
ON CONTRACT WITH JENSEN BUILDERS, LTD., OF DES MOINES, IA,
FOR BID PACKAGE 3-1 – CONCRETE & STEEL WORK
FOR THE RESOURCE RECOVERY AND RECYCLING CAMPUS
FOR THE CITY OF AMES, IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper
on the above Contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames,
Iowa, that Change Order No. 4 in the amount of $75,764.25 on contract with Jensen
Builders, LTD., of Des Moines, IA, for Bid Package 3-1 – Concrete & Steel Work for the
Resource Recovery and Recycling Campus be approved and adopted as attached hereto
and made a part hereof by this reference.
ADOPTED THIS 13th day of October, 2026.
_______________________________ _________________________________
Renee Hall, City Clerk John A. Haila, Mayor
Introduced by: Gartin
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Gartin, Junck, Rollins
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 13th day of October, 2026.