SUBJECT:AMES ANIMAL SERVICES FACILITY - CONSTRUCTION CONTRACT BIDS
COUNCIL ACTION FORM
BACKGROUND:
The City has purchased the former Eagle's Loft Daycare property at 2715 Dayton Avenue in a
project to renovate and expand it into a new Ames Animal Services Facility. The City retained
INVISION Architecture LTD (INVISION), Des Moines, Iowa, to design the facility using best
practices outlined by the American Society of Veterinarians (ASV) Guidelines for Sheltering,
and meeting the requirements for Animal Welfare of the Iowa Department of Agriculture and
Land Stewardship (IDALS).
INVISION and its sub-consultants have worked with City staff and fundraisers to complete a
design of the facility, which is broken into three spaces: 1) cat spaces, 2) dog spaces, and 3)
human spaces. This design features an approximately 1,700 square-foot addition that will be
utilized as dog space and will have a flat roof to accommodate mechanical equipment.
BIDS:
The invitation to bid was issued on August 25, 2026. It contained eight add-alternates:
1. Dog run shade structures
2. Replace resilient corridor flooring with epoxy
3. Catio screens
4. Parking lot addition
5. Exterior building signage
6. Building automation
7. Wood-look metal entry trellis
8. Catio on south elevation
On September 30, 2026, bids were received as follows:
Bidders Base Bid
Add
Alternate
#1 - Dog
Run
Shade
Structures
Add
Alternate
#2 -
Epoxy
Flooring
Add
Alternate
#3 -
Wood
Look
Metal
Louvers
at Catio
Add
Alternate
#4 -
Parking
Lot
Addition
Add
Alternate
#5 -
Exterior
Building
Signage
Add
Alternate
#6 -
Building
Automation
Add
Alternate
#7 -
Wood
Look
Metal
Louver
at Entry
Add
Alternate
#8 - Catio
Enclosure
HPC, LLC,
Ames, IA $5,500,000 163,000 (11,000)45,000 66,000 71,000 53,000 45,000 120,000
1
Big Lake
Construction,
LLC, Des
Moines, IA
$5,698,000 199,000 (5,400)76,000 84,000 37,500 24,600 87,800 98,300
Munro
Construction
Co,
Johnston, IA
$5,733,000 99,000 (6,000)90,750 79,000 54,500 106,500 98,500 206,000
Ball Team,
LLC,
Urbandale,
IA
$5,786,530 146,690 - 132,376 75,955 68,048 48,278 112,403 161,409
Greiner
Construction,
Des Moines,
IA
$5,925,000 140,100 (16,800)137,400 83,400 68,700 103,500 115,900 192,100
Keystone
Construction
Services,
Waukee, IA
$6,200,000 88,000 (10,000)130,000 67,000 52,000 51,000 10,000 152,000
Kingland
Construction
Services,
Forest City,
IA
$6,600,000 330,000 160,000 137,000 76,000 58,000 25,000 115,000 95,000
The base bid received from HPC is $5,500,000. The estimated construction cost with no
contingency was $5,441,081, leaving a shortfall of $58,919 if the base bid was to be awarded.
Following the bid opening, staff and the design team met with HPC to identify value
engineering items that could reduce the base bid without affecting the overall function of the
s p a c e s . In this preliminary discussion, it was believed that the base bid could be
reduced by $100,000 to $200,000 through these efforts. Staff would like a minimum
contingency balance of $250,000, so more savings or additional funding will be needed
to provide such a balance.
In addition, a decision will need to be reached regarding inclusion of any of the add-
alternates that were offered outside of the base bid. A discussion regarding these add-
alternates, the bid amount for them from HPC, and staff's preliminary thoughts
regarding each of them, is below:
1. Dog run shade structures ($163,000) - Among the add-alternates, staff believes this
one has the most direct impact on animal and volunteer well-being. At the City Council
discussion on August 11, individual Council Members made comments supporting the
inclusion of this alternate. Staff has asked HPC to confirm the pricing on this alternate
since it was higher than estimated and higher than some of the other bidders. Further
discussions need to occur to determine if there is a less costly manner in which to
provide shade to the dog areas.
2. Epoxy flooring (-$11,000) - Given the deduct offered, staff believes this epoxy flooring
alternative should be included in the bid award.
3. Wood look catio louvers ($45,000) - This is a primarily cosmetic component to the
2
project. Staff believes the bid amount for this add-alternate is competitive. However, it is
also a component that does not significantly affect animal care. Additionally, it may be
possible to add a similar feature at a later date.
4. Parking lot addition ($66,000) - The base bid specifications add two parking spaces
compared to the existing facility on Billy Sunday Road. This add-alternate provides
another 12 parking spaces. At the City Council discussion on August 11, individual
Council Members made comments supporting the inclusion of this alternate. Staff
believes the bid amount for this add-alternate is competitive. However, it is also a
component that does not affect animal care and could be added in a future project.
5. Exterior building signage ($71,000) - This is a cosmetic component to the project,
which does not affect animal care. Staff can look to identify alternative ways in which to
incorporate signage into the project.
6. Building automation ($53,000) - This alternate provides a system that coordinates the
various mechanical systems throughout the building. Although the bid amount for this
alternate is approximately 1/3 of the estimated amount, Staff does not believe this
alternate adds enough value to the project to make its inclusion worthwhile. Excluding
this system will also avoid some future operating costs to maintain this system.
7. Wood look metal entry ($45,000) - This is a cosmetic component to the project. Staff
believes the bid amount for this add-alternate is competitive. However, it is also a
component that does not affect animal care.
8. Catio enclosure ($120,000) - Staff has asked HPC to confirm the pricing on this
alternate since it was higher than some of the other bidders. This alternate would be
difficult to add to the building at a later date due to the manner in which it is integrated
into the building. It also provides some additional space for cats to inhabit, which has an
impact on animal care.
To summarize, staff believes it would be worth having further discussions with HPC and the
design team, with a goal to incorporate add-alternates 1, 2, 4, and 8. Preliminary
discussions regarding the value engineering were positive, so staff would like time to
discuss with HPC reducing the base bid before coming back to City Council with a
deduct change order and information on any alternates. Further Council direction
regarding these add-alternates would allow staff to focus its discussions with the
contractor and design team.
If it is assumed there are no changes to the pricing of these add-alternate components, then
the construction cost would be as follows:
ITEM AMOUNT
Base Bid $ 5,500,000
Estimated Base Bid Deducts (150,000)
Alternate 1 (Dog run shade structures)163,000
Alternate 2 (Epoxy flooring)(11,000)
Alternate 4 (Parking lot addition)66,000
Alternate 8 (Catio enclosure)120,000
3
Estimated Construction Contract Total $ 5,688,000
Construction contingency 250,000
Estimated total construction expenses 5,938,000
Shortfall from $5,441,081 construction budget ($496,919)
The overall budget for this project, inclusive of design, site acquisition, and site investigation,
is shown below:
EXPENSES FUNDING SOURCES
Previous Site Investigation $ 4,075
2715 Dayton Purchase Option 5,000
Site Acquisition 1,100,000
Conceptual Design 66,360
Change Order No. 1 (Detailed
Design/Construction Specs)588,000
Change Order No. 2 (additional scope
for Dog Run access)24,440
Construction/Renovation 5,441,081
FF&E/Permits 450,000
3rd Party Testing/Geotechnical 40,000
Stormwater
Quality CIP
Funding
$ 30,000
Sanitary Sewer
Utility Fund 29,000
Shared Use Path
Maintenance
Program available
balance (LOST)
16,500
FY 2023/24
General Fund
Savings
100,000
Council Priorities
Capital Fund 2,855,000
Donations 4,534,040
Supplemental
Donation for Dog
Area Doors
154,416
TOTALS $ 7,718,956 $ 7,718,956
4
ALTERNATIVES:
1. Accept the report of bids and delay the award to provide staff additional time to evaluate
the bids and project budget.
City staff is also requesting that the Council provide guidance regarding the
combination of alternates, if any, that staff should further discuss with the
apparent low bidder and the design team.
2. Accept the report of bids and award a contract.
3. Accept the report of bids, reject all bids, and direct staff to work with the design team to
modify the project for another invitation to bid.
CITY MANAGER'S RECOMMENDED ACTION:
The bids received for the Animal Services Facility project exceed the estimate and the
available funding. Staff believes that through conversations between the low bidder
changes can be made to lower the base bid without impacting the function of the
building. However, more time is necessary to complete these discussions and prepare
for award, including any alternates that the Council would want to consider. Therefore, it
is the recommendation of the City Manager that the City Council approve Alternative #1, as
described above.