Meeting Minutes
December 15, 2011
The Ames Public Library (APL) Board of Trustees met in regular session on Thursday,
November 17, 2011, in the Council Chambers of City Hall, 515 Clark Avenue, with Bradley,
Budd, Campbell, Manus, Meier, Rawlins, Schill, and Stow in attendance. Manus arrived late.
Luckett was excused. Library Director Art Weeks and Assistant Director Lynne Carey were also
present.
Call to Order: Board Vice President Stow called the meeting to order at 7:00 p.m.
Adoption of Agenda: Moved by Campbell, seconded by Rawlins, to approve the agenda.
Vote on Motion: 6-0. Motion approved unanimously.
Approval of Minutes: Moved by Bradley, seconded by Schill, to approve the minutes of
the meeting of November 17, 2011.
Vote on Motion: 6-0. Motion approved unanimously.
Public Forum: None
Manus arrived at 7:03 p.m.
Consent Agenda: Meier moved and Rawlins seconded adoption of a resolution approving
the consent agenda:
1) Claims Report 11/1/11 – 11/30/11
2) Financial Reports
Vote on Resolution: 7-0. Resolution adopted unanimously.
Administrative Staff Report: Library Director Weeks summarized his written report, noting
that funding from Story County is expected to be flat this year. The library’s Teen Advisory
Group (TAG) and former library trustee Chuck Jons and his wife were all recently honored by
the Story County Alliance for Philanthropy. Weeks said that the operating budget was reviewed
with the Finance Department early in the month.
Ames Public Library Friends Foundation Report: Stow reported that the fall fundraising
campaign is currently in progress. A small book sale of special items brought in $1,100 and
TAG also held a bake sale. Stow said that the youth have raised $1,100 for the library in the first
six months of the year. The two TAG co-chairs, Divya Navi and Tripti Upreti, have now been
hired to work in the circulation department, so new co-chairs are being sought.
Library Building Project Update: Weeks said that fundraising is on track and the
philanthropic group is discussing the timeline for the rest of the campaign. Grant writing, which
was dependent on the outcome of the election, will begin now and work with individuals,
corporations, and groups continues.
Policy Review:
Exam Proctoring Policy
Moved by Campbell, seconded by Budd, to adopt a resolution approving the Exam
Proctoring Policy as presented/amended.
Weeks affirmed that staff was not recommending any changes at this time.
Vote on resolution as presented: 7-0. Resolution adopted unanimously.
New Business:
Contract for Library Service for Story County for Fiscal Year 2012/13
Weeks explained that the annual contract requires the board to review the policy prior to
February 1 of each year; however, no action is required. The eleven libraries in the county are
all parties to the contract, which states that the libraries will serve the unincorporated areas of
the county. The payment to each library is dependent on each one’s level of circulation.
Stow asked if there was much fluctuation in the level of funding. Weeks said that the payment
received is dependent on circulation, so it goes up and down, but is relatively flat. Last year APL
received about $128,000.
Construction Delivery Method for Library Renewal Project
Trustee Manus said the committee had met to discuss some of the information it received from
staff. The second session she attended was with Dean McCormick, the Director of Design and
Construction Services for Facilities Planning and Management at Iowa State University. Manus
said the committee determined the primary decision points and discussed them, but did not
reach a conclusion about whether it would be preferable to hire a construction management
agent or a general contractor. The committee members f elt it was important to have more input
and collectively reflect on the matter.
Trustee Meier added that she feels it is important to take the time to make the right decision and
feel comfortable about it. There are a lot of decisions to be made and research to be done.
Trustee Budd agreed, noting that there are plusses and minuses on both sides and he feels it
might be something the entire board may want to weigh in on.
Meier said the subcommittee would probably meet again between Christmas and New Years.
Weeks said he had taken the liberty of inviting someone who is an advocate for General
Contractor (GC) to make a presentation at an upcoming committee meeting. He added that two
representatives from Cost, Planning & Management International, Inc. (CPMI), the cost
estimating firm the library’s architect has been using for APL’s project, were present in the
audience and had expressed willingness to field questions.
For the sake of clarification, Weeks explained that under the GC model, one contractor would
be selected by a bidding process. That contractor then becomes responsible for the entire
project. If that turns out to be the chosen model, Weeks said it had been recommended that the
library also engage an owner’s representative to work with staff and provide expertise. The
Construction Management Agent (CMa) is someone brought in to manage the project and the
other contractors that are brought in to do the work. The CMa can be selected in the same way
an architect or other professional consultant would be. He or she then manages the construction
contracts, with the contractors selected by lowest responsible bid. Every contractor has to
provide his own performance bond and the CMa manages their work.
Stow thanked the committee for its work thus far and invited the trustees to ask questions of
Larry Gleason and Joe Gerleman from CPMI. Manus said it was her understanding that with a
general contractor, the mark-up would be built into the bid, but she wondered about costs if the
construction manager model were used during design and also during construction. She asked
if it would be possible for CPMI to work with the architect to present a budget comparing the
overall cost both ways. She also wondered if he could provide any information on how the
methods compared on past projects. Meier added that the committee was familiar with
accepting bids from a general contractor and knowing the cost in advance; they were not
comfortable with the cost structure when a construction manager is used.
Gleason stated that the cost management involves several things, and different delivery
methods will affect how that cost management benefits the project. One of the benefits of the
construction management approach is that there is a construction professional on the team with
the architect during design to work on issues that might skew the cost at the time of bid. It
allows for managing costs of alternates and anticipating problems prior to the bidding phase.
Under Iowa law, the entire project has to be competitively bid, whether it is bid by one single
prime contractor or through several contracts.
Gleason said that if bids made by one single prime do not fit into the proposed budget, there are
a number of dilemmas related to redesign and re-scheduling. The construction management
approach does help control that problem up front. He said that Manus was correct in stating that
a single prime contractor takes into account the administration of the subcontracts and his own
risks in his bid. He emphasized that the documents have to be very clear and concise before the
bid is let. If documents are not good, the single prime contract will be very difficult to manage.
With construction management approach, the fee is built in for administering the subcontracts.
There is a professional fee for the amount of hours the agent works (because he is serving as
ad hoc staff). Gleason suggested that an appropriate approach to bidding could be to allow a
single prime contractor to bid, and compare that to a combination of multiple prime contracts.
He said CPMI has done this in the past. Sometimes the total cost of the construction
management fee plus the bids of the combined multiple prime contractors is not lower than the
single prime package bid. He cited a project done for the Linn-Mar School System where that
was the case. Linn-Mar opted to use the single prime contractor, so the construction manager
cut his fee because he was no longer administering the project. The construction management
approach offers the opportunity to find out what the lowest possible bid was under either of the
scenarios.
Gleason commented on change orders that come along, once bids are in place and the project
is on its way. He said change orders may be the result of unknown site conditions (such as old
wiring or something hidden behind a wall), coordination issues (documents not clear or what
bidders were expecting), or owner’s discretionary changes (things added later or revised as the
project progresses). Gleason cautioned that with a single prime bid, every change will be
marked up by the general contractor. In contrast, under the CMa approach, there would be no
mark-up on the changes. The only time the CMa fee goes up is if project gets extended for
reasons for which the CMa was not responsible – and the fee would increase because the job
would then require more hours.
When asked if the Construction Manager’s fee was a percentage of the cost of the total project,
Gleason stated that CPMI never bases the fee on the cost of project. Typically, pre-construction
and construction fees are based on the hours the manager is anticipated to work and a
maximum fee would be determined. He said sometimes it could be converted to a lump sum
fee, but Gleason said he would not recommend using a percentage of construction cost
because then there is no incentive for the construction manager to keep costs low.
Manus inquired if it would be feasible to change construction managers, if the project were
started with one that the library ended up not liking. Gleason said that CPMI had not had that
experience. More frequently, he sees projects that have started with the one single prime
approach with a general contractor and then switched to CMa because of problems with bids.
Gleason added that a professional services contract of this type would typically have a
“termination for convenience,” which is for the owner. However, the owner has to be in default
for the CMa to walk away.
Trustee Schill asked what sort of communication should be practiced between the CMa, the
owner, and the architect. Gleason replied that in the pre-construction period, the design team
works with owner and the CMa tries not to get in the way; rather, he stays in the loop so that he
is aware of any design changes or cost changes. The CMa should be doing the estimating
because he will have to manage the costs later. Once the contractors are involved, the CMa
takes the lead and conversations should go through the CMa. Any changes in the project will
happen with owner approval. Gleason added that the CMa should provide monthly status
reports, field reports, photos, and keep basic communication in a project database which is
accessible to the committee, the architects, and the owners. At a minimum, the owner should
expect monthly reporting on financial status, schedule status, and contract status. The database
also includes warranties and other information for the owner’s records, and it gets turned over to
the owner at the end.
Asked how often the architects should be expected to be on site, Gleason said once a week, at
minimum. The architects should attend construction meetings and put together a field report of
how their observations match up with the drawings. The construction manager takes over some
of the responsibilities so that the architect will be freed up to spend more time on quality control,
submittal review, and making sure the work is being done properly. The construction manager is
on site every day and has a feeling for how much progress has been made on construction and
what should be paid on a monthly basis.
Trustee Meier asked about reimbursable expenses and controlling them. Gleason said that
reimbursables are a tricky thing. Most contractors consider reimbursables to be: field
superintendents, field engineers, the jobsite trailer and equipment that does not stay with the job
when it’s complete. Typically, in a CM Agent role, the reimbursables are the office and things
that they need to perform their job on site. All of the labor should be included in the base fee.
Gleason cautioned that when the board selected a CMa, it would want to make sure to clarify
what was considered reimbursables versus labor on the project. He said that contractors who
do CMa work will sometimes include field staff in with their reimbursables because that’s what
they do as a general contractor.
Manus asked Gleason how much contingency should be included on a project such as this. He
stated that the Construction Manager functions as ad hoc staff and serves as “your insurance
policy,” whereas a GC picks up the risk and you are paying him for that. Gleason said he would
say three to five percent (3-5%) minimum on a remodeling project. He said he did not do the
estimating on the APL project, but he guessed the library would be at the low end of the range
because the addition is fairly new and there have not been many projects in the interim.
Stow stated that the subcommittee would meet again and asked staff to look at scheduling a
special meeting of the full board the first week of January so that the project does not get
delayed.
Appointment of Director Evaluation Committee
Stow said that he, President Luckett, and Sherry Bradley would be serving on the committee.
Trustee Comments:
Schill thanked Ames voters for giving the library bond question a 76% approval.
Manus acknowledged Art and Lynne for spending time with the construction delivery committee
and providing so much information. She also congratulated the Teen Advisory Group for their
honor.
Meiers said there is a lot to learn and much work ahead, but she is certain the library will come
out with a great project.
Adjournment: The meeting was adjourned by consent at 7:41 p.m.