RESOLUTION APPROVING M2 MILESTONE PAYMENT
FOR GENERATION INTERCONNECTION AGREEMENT WITH MISO
FOR THE AMES MUNICIPAL ENERGY CENTER
FOR THE CITY OF AMES, IOWA
WHEREAS, Electric Services is undertaking a project to design and construct a
new electric generating facility, referred to as the Ames Municipal Energy Center (AMEC).
The City has retained Sargent & Lundy to provide the standard design services, along
with support in obtaining all permits and regulatory permissions required to construct the
facility; and,
WHEREAS, one of the permissions needed is a Generation Interconnection
Agreement (GIA) from the Mid-Continent Independent System Operator (MISO); and,
WHEREAS, the operator studies the impact of new generation on the electric grid
and determines whether the proposed new generating assets will require system
upgrades to support generation-to-load requirements. These studies include a steady
state, short circuit analysis, and stability studies. The completed studies will identify
overloads or limitations on the electric grid which must be corrected before the new
generation can be connected; and,
WHEREAS, payment of the non-refundable application fee and the study deposits
were previously approved by the City Council on May 12, 2026; and,
WHEREAS, the initial study has been performed and the City has received
preliminary approval from MISO to proceed. A milestone (M2) payment is now required.
This payment is intended to disincentivize a developer from submitting a possible new
generation project and subsequently failing to build the project after receiving an
approved Generator Interconnection Agreement. Based on the size of Ames' proposed
generation, the M2 milestone amount is $435,200; and,
WHEREAS, the M2 payment is held by MISO while it determines whether Ames
must pay for a share of system upgrades as a result of bringing the AMEC online. The
cost to Ames of such upgrades could vary depending on whether other planned projects
proceed or withdraw from interconnection. It is possible that the AMEC project
necessitates additional payments for upgrades in excess of the M2 payment amount. If
no system upgrades are required, or if Ames' cost share for system upgrades is less than
the M2 payment amount, then Ames may receive a refund of the unused M2 amount once
AMEC enters into commercial operation.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames,
Iowa, that the cash M2 payment to Mid-Continent Independent System Operator (MISO)
in the amount of $435,200 for a Generation Interconnection Agreement application is
hereby approved.
ADOPTED THIS 28th day of August, 2026.
_______________________________ _________________________________
Renee Hall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Junck, Gartin, Rollins
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 28th day of August, 2026.