HomeMy WebLinkAbout~Master - August 2026 Monthly Project HighlightsContact the City Manager's Office at 515-239-5101
515 Clark Avenue, Ames, IA 50010
Report compiled by
Allie Warrenburg, Principal Clerk
City Manager's Office
AUGUST 2026
MONTHLY PROJECTHIGHLIGHTS
LIBRARY
Summer Wraps Up: Another exciting summer has come to a close at Ames Public
Library. The Summer Reading Challenge had almost 3,400 participants who read over 5
MILLION minutes! SUN Meals at Ames Public Library, in partnership with the United
States Food and Nutrition Service, was as busy as ever, with over 4,000 lunches served.
Local teens provided over 1,700 hours of volunteer power to assist with SUN Meals,
special projects, events, and more through the Library's summer APL-Youth Volunteer
program.
Supporting Local Creators: This fall, the Library will host several events to support
local authors and filmmakers. The Octagon Center for the Arts' inaugural Ames
Documentary Film Festival will be held at the Library Sunday, September 27, from 10
a.m. until 4 p.m. Details are at https://amesdocfilmfest.com. The Library is also gearing
up for the annual Author Fair, which will be held Saturday, November 7. Local Iowa
authors can apply to participate by October 10 at www.AmesPL.org/AuthorFair. Be sure
to check the calendar for upcoming author events with Ryan T. Pozzi and Great Reads
from Great Places authors Jill Esbaum and Denise Williams.
Welcome Cyclones!: Ames Public Library has begun
its annual outreach efforts to connect Iowa State
University students with resources. During Cyclone
Welcome Weekend, 285 people dropped in to the
welcome event and 162 signed up for a library card!
Ames Public Library also participates in several
welcome events on campus in addition to offering
special activities and giveaways at the weekly
Bookmobile stop near Kildee Hall. These are great
opportunities to invite students to events like Speed Friending (September 13), That's
Fun (2nd Monday of each month), International Community Meetup (3rd Tuesday of each
month), and many more in addition to raising awareness about the Library's services and
resources.
What's With the Dots?: Ames Public Library is partnering
with several organizations to protect birds in our area with
new window treatments. A pattern of dots on the outside of
the windows helps birds recognize the windows as a barrier
and not something to fly through. The treatment is being
added to windows around the Library’s atrium and courtyard,
as well as the corner in the Youth Services area. Thank you
to CoolVu of Des Moines, Feather Friendly Bird Collision
Deterrent Markers, Wild Birds Unlimited of Ames, and Big
Bluestem Audubon Society for making this project possible.
2
PARKS AND RECREATION
Aquatics: The final session of summer swimming lessons at Fitch Indoor Aquatic Center
ended on July 30 with a total of 211 participants.
Daley Park Splash Pad Project: Staff resubmitted information to the State of Iowa in
early August for the Daley Park Splash Pad in order to be approved for construction. Staff
expects to receive approval for construction in the near future. Once approved, the
contractor will have until May 15, 2027, to complete the project. Staff is currently in the
process of completing the mechanical building, which will house the pumps, controllers,
filters, and other necessary mechanical equipment.
Duck Derby: The Fourth Annual Scholarship
Duck Derby was held at Furman Aquatic Center
on August 12, bringing the community together for
an exciting fundraiser benefiting the Ames Parks
& Recreation’s Scholarship Fund.
A record 1,267 ducks raced through the lazy river
as spectators cheered them on. The event raised
more than $8,000, making it the most successful
Duck Derby to date.
Prizes included a $500 cash prize sponsored by
The Mucky Duck Pub, a kayak from CrawDaddy
Outdoors, a mountain bike from Bike World, and more.
Funds raised help provide financial assistance to
individuals and families so they can participate in Ames
Parks & Recreation programs.
The event was made possible through strong community
participation and support from sponsors, including
presenting sponsor The Mucky Duck Pub, as well as
CrawDaddy Outdoors, Duck Worth Wearing Ames, Bike
World, and First National Bank 247.
3
The Duck Derby continues to grow as a community tradition while raising funds to make
recreation more accessible to local families.
Homewood Golf Course: As of August 24, 2026, Homewood Golf Course has had
17,839 round of golf played. During the same time frame last year, there were 18,795
rounds played. Homewood opened on March 28 in 2025 and on March 30 in 2026.
Below is information related to the HomeWood Clubhouse Rentals:
July 1, 2025 –
August 24, 2025
July 1, 2026 –
August 24, 2026
Paid Event Hours 18 17.75
Revenue from Paid Events $1,890.00 $1,863.75
Non-Paid Event Hours 23 14
Homewood hosted a Youth Day on August 2 where youth played free with a paying
customer. A total of 18 youth took advantage of the free golf.
Several Golf Leagues ended recently including the Men’s League (Jake Veenstra and
Ricardo Castrodad) and the Sixty Forward League (Paul Hinderaker and Rick Ertz).
4
Homewood Golf Course Hole Nine Crossing Project: Con Struct, of Ames, Iowa, will
be completing the final portions of the Hole Nine Crossing project in early November. The
last items to be done include pouring the concrete path over the crossing and completing
final grading and seeding once the course closes.
Homewood Golf Course Parking Project: As a result of the Hole Nine Crossing
project, the golf course driveway has sustained considerable damage to the asphalt
surface. This project will replace the asphalt drive with concrete, increase the number of
parking spaces from 55 to 81, and manage stormwater. Staff is working with Public Works
to develop plans and specifications which will be distributed for bid in the near future. The
goal is to start the project later this year in preparation for the 2027 season.
Fall Youth Soccer Prep: The fall Youth Soccer Program has been moved from North
River Valley Park (NRV) to Brookside Park to allow staff to conduct needed turf
maintenance at NRV. Turf maintenance, including broadleaf weed spraying, core
aeration, and overseeding, will be completed to allow the NRV fields to rest in order to
provide improved playing conditions for future seasons.
Forestry: Multiple storms in July and early August caused downed branches and trees
in park spaces and the right of way resulting in cleanup efforts that continued through
mid-August.
Staff completed 15 tree removals and 25 SeeClickFix requests. Staff also partnered with
Public Works to remove downed trees and limbs from several creek locations across
Ames.
Steven L. Schainker Plaza Project: At the end of the day on August 31, the Steven L.
Schainker Plaza, including the spray pad, restrooms, etc., will close for the season to
allow Henkel Construction, of Ames, Iowa, to remove and replace the ice-skating ribbon
beginning September 1. The ice ribbon is planned to be completed by November 15 so it
can open to the public for the winter season. Ice skate rentals will be offered at various
times throughout the week; however, individuals can use their own ice skates as well.
5
WATER & POLLUTION CONTROL
Capital Improvements Plan Implementation: Numerous Capital Improvement Plan
projects for the Department are moving into the construction phase. A Notice to Bidders
has been issued to implement a “split treatment modification” to the Water Plant. Bids for
a major HVAC renovation of the Technical Services Complex (home to the Water Meter
and Laboratory Services Divisions) will be solicited in September. A transition from
powdered fluoride to liquid fluoride is also moving forward. Staff has submitted a grant
application to Delta Dental that will hopefully defray a significant portion of the cost of that
change. A new variable frequency drive is being added to a pump at the Water Plant. A
new arc flash evaluation is being performed for the Water Plant and remote pump
stations. A preventative maintenance project at the Old High Service Pump Station will
address corrosion on pipe fittings as well as recoating portions of the piping.
Cyber Security in the News: In August, headlines around the nation told stories of
coordinated cyber-attacks on water infrastructure. Staff participated in numerous briefings
from state and federal agencies to learn the details of these incidents. All of the
recommended countermeasures in those briefings were things that both the Water Plant
and Water Pollution Control Facility had already implemented. Water & Pollution Control
(W&PC) staff continues to stay coordinated with Story County Emergency Management
and has offered technical resources to other water utilities in the county.
Focus on Values and Mission: In August, the entire W&PC Department spent time
together talking about the City’s Excellence Through People Values and how those values
look and sound in the context of the departmental mission. There was also time set aside
to talk specifically about the “trust agreement” City staff has with its customers,
“excellence,” “positive attitude,” “leadership,” and “honesty and integrity.” Part of the
excellence conversation included a competition where teams raced to build the tallest
free-standing water
tower capable of
holding eight ounces
of water for at least
30 seconds, using
random supplies like
straws, paper clips,
bandages, and push
pins. The height of
the winning water
tower was 34.75”.
6
NPDES Permit Renewal Application Submitted: Discharge permits for wastewater
facilities cannot be for longer than five years under federal law. The current permit for the
Water Pollution Control Facility was issued on February 28, 2022, and will expire early
next year. Staff has completed a permit renewal application and submitted it to the Iowa
Department of Natural Resources for approval.
Nutrient Reduction Modification Progress: Work on phase 1 of the nutrient
modifications at the Water Pollution Control Facility slowed slightly during July and August
due to the frequent heavy rains. Despite that, the contractor’s work remains well ahead
of the contract deadlines. Start-up of the new activated sludge process is anticipated by
the end of the calendar year. In the past month, work has required multiple complete
shutdowns of the plant. This requires water to be backed up in the 66” diameter
interceptor sewer. It is a nerve-wracking experience for the plant staff, especially on those
days when the entire electrical system is powered down to allow new switchgear to be
installed.