HomeMy WebLinkAboutA033 - August 25, 2026, Regular Meeting of the Ames City CouncilITEM #:35
DATE:08-25-26
DEPT:FIN
SUBJECT:RESOLUTION FIXING DATE FOR A MEETING ON THE AUTHORIZATION
OF A LOAN AND DISBURSEMENT AGREEMENT AND THE ISSUANCE OF
NTE $53,930,000 ELECTRIC REVENUE BONDS FOR SEPTEMBER 8, 2026
COUNCIL ACTION FORM
BACKGROUND:
The City is moving forward with the financing of the new thermal generation project for the
Ames Municipal Electric Utility. The project includes the purchase and installation of new
reciprocating internal combustion engine (RICE) generation units, along with the associated
site, electrical, mechanical, and other construction improvements necessary to place the new
generation resources into service.
The financing currently proposed represents the first phase of a larger financing plan for the
project. Since the project was initially presented to the City Council in April, the proposed
financing strategy has been revised as additional information regarding final equipment costs,
contractual payment requirements, and the overall construction schedule has become
available.
On April 21, 2026, PFM Financial Advisors LLC presented a financial analysis of the proposed
RICE generation project to the City Council. The presentation reviewed the changing regional
electric utility environment, the City's evolving power supply portfolio, anticipated operating
savings from the project, projected electric rate requirements, and a preliminary financing
strategy.
The preliminary financing strategy developed earlier in the project relied heavily on short-term
construction financing during the construction period, followed by one large long-term Electric
Revenue Bond issue. Under the original plan, the City anticipated the following:
A draw-down construction loan beginning in 2027
A single, approximately $190 million Electric Revenue Bond issuance in 2029 to repay
the construction loans and finance the remaining project costs.
The purpose of the original structure was to use draw-down construction financing during the
early stages of the project so the City would borrow funds only as they were needed and could
gradually transition into the full annual debt-service requirement.
The April analysis also assumed approximately 2.5% annual electric rate increases from FY
2026/27 through FY 2044/45, followed by approximately 1.5% annual increases thereafter.
To accomodate the borrowing needs of the project, Electric Services staff has now developed
a more complete monthly construction schedule through October 2030. That schedule
currently identifies approximately $192,663,000 in total project construction costs, with
1
significant expenditures occurring before the construction financing contemplated in the
original plan would have been available.
The estimated expenditures by fiscal year are:
Fiscal Year Construction Costs
FY 2025/26 $ 424,000
FY 2026/27 43,457,000
FY 2027/28 16,176,000
FY 2028/29 88,317,000
FY 2029/30 41,174,000
FY 2030/31 3,115,000
Total $192,663,000
These earlier and more clearly defined payment requirements caused staff and PFM to
reconsider the original financing structure. Under the new recommended plan, the City would
finance the project through a combination of Electric Revenue Bonds and a construction draw-
down loan issued as the project progresses:
Financing Timing Project Funding
Electric Revenue Bonds October 2026 $50,533,000
Electric Revenue Bonds March 2028 $71,550,000
Construction Draw-Down Loan April 2029 $70,580,000
Electric Revenue Bonds to repay 2029
construction loan October 2030 $70,580,000
The primary difference from the original financing strategy is that the City would now
issue long-term Electric Revenue Bonds earlier in the construction process rather than
relying primarily on construction loans until a single, large 2029 bond issue.
This revised approach better matches the City's borrowing with the actual contractual payment
schedule and known construction cash flows. PFM estimates the total all-in financing cost of
the new recommended plan at approximately $341.2 million, including principal, interest,
underwriting discount, and costs of issuance.
PFM also evaluated an alternative plan that more closely aligned with the original financing
strategy. Based on revised schedule, the plan would have relied more heavily on construction
loans in 2026 and 2029 before refinancing those loans with Electric Revenue Bonds. The
estimated all-in financing cost of that alternative is approximately $392 million.
PFM therefore recommends the new phased Electric Revenue Bond approach because:
It is estimated to reduce total financing costs by approximately $50.75 million compared
with the construction-loan alternative
Maximum annual debt service increases by only approximately $200,000
The financing can still be accomplished within the 2.5% annual electric rate increases
previously modeled for the project.
2
The action staff is requesting is only in relation to the first financing phase of the project, as
noted above. This phase is intended to provide approximately $50,533,000 of project funding,
primarily for the RICE engines and other project construction costs anticipated through
approximately February 2028. It should be noted that the issuance also includes $827,000 in
issuance costs, for a total of $51,360,000.
Although the current preliminary bond amount is approximately $51,360,000, the proposed
public hearing authorization establishes a principal amount not to exceed $53,930,000. The
not-to-exceed amount provides flexibility for changes in market conditions, final bond sizing,
required reserves, issuance costs, and other financing adjustments before the bonds are sold.
If approved, the bonds would be expected to close on October 29, 2026, with a 30-year
amortization schedule.
Current estimated annual debt service is approximately:
$1.51 million in FY 2026/27
$2.57 million in FY 2027/28
Approximately $3.44 million to $3.45 million annually thereafter
Principal payments are currently expected to begin in 2029, with final maturity in 2056. The
Series 2026D Bonds would be Electric Revenue Bonds payable from the net revenues of the
City's Electric Utility. They would not be General Obligation Bonds and would not be
supported by the City's property tax levy.
The City's approximately $9.5 million of outstanding Electric Revenue Bonds issued in
2015 are currently rated Aa2 by Moody's Ratings. PFM does not expect the City to
finance the entire $192 million thermal generation project without some pressure on the
Electric Utility's revenue bond rating.
Susanne Gerlach of PFM Financial Advisors is expected to be in attendance at the meeting on
Tuesday evening to review the revised financing plan with the City Council. She will also
discuss the Moody's rating process, the rating scorecard, factors that could affect the electric
revenue bond rating, and the potential financial impact of the various rating outcomes.
Following a review of the financial plan, and if approved by the City Council, staff will
request the City Council approve a resolution establishing September 8, 2026 as the
date for the public hearing on the proposal to enter into an Electric Revenue Loan
Agreement and borrow money thereunder in a principal amount not to exceed
$53,930,000, and would authorize publication of the required notice.
No bonds will be sold as a result of the August 25 action. The action establishes the public
hearing and allows staff, PFM, and bond counsel to continue preparing for the proposed
Series 2026D financing.
3
ALTERNATIVES:
1. Adopt a resolution fixing September 8, 2026 as the date for a public hearing on a
proposal to enter into an Electric Revenue Loan Agreement and to borrow money
thereunder in a principal amount not to exceed $53,930,000.
2. Do not adopt the resolution and direct staff to modify or delay the proposed financing
schedule.
CITY MANAGER'S RECOMMENDED ACTION:
Since PFM's initial presentation to the City Council on April 21, 2026, the City has received
final RICE engine pricing and a detailed construction and progress-payment schedule. This
additional information demonstrated that the timing of project expenditures occurs significantly
earlier than contemplated in the original financing plan.
PFM has recommended replacing the original construction loan-based financing
strategy with a phased financing plan that begins with Electric Revenue Bonds in 2026
and 2028, uses a construction draw-down loan for the final phase of construction in
2029, and converts that loan to long-term Electric Revenue Bonds following completion
of construction.
PFM estimates that this revised approach will reduce total financing costs by
approximately $50.8 million compared with the alternative revised financing structure,
while increasing maximum annual debt service by only approximately $200,000 over a
shorter duration. The revised plan also remains within the 2.5% annual electric rate
increases previously modeled for the project.
Setting the public hearing at this time will allow the City to proceed with the first phase
of the revised financing plan and maintain the anticipated October 29, 2026
closing. Therefore, it is the recommendation of the City Manager that the City Council adopt
Alternative No. 1, as described above.
ATTACHMENT(S):
PFM Recommendation.pdf
4
August 18, 2026
Memorandum
To: City of Ames, Iowa (the “City”)
From: Susanne Gerlach, PFM Financial Advisors LLC (“PFM”)
Re: PFM’s Recommended Changes to Plan of Finance for Electric New Thermal
Generation Project
SUMMARY
PFM recommends that the City revise the plan of finance for the New Thermal Generation Project
to Option 1 described below. Option 1 reduces total financing costs by approximately
$50,750,000 relative to Option 2, increases maximum annual debt service by only approximately
$200,000, and can be accomplished within the 2.5% annual rate increases previously presented.
The revision is driven by the final RICE engine cost of $72,407,000 and a progress payment
schedule that begins in July 2026, well ahead of the original financing timeline.
ORIGINAL PLAN OF FINANCE
Earlier this year, PFM’s Public Power group provided a detailed cashflow analysis for the Electric
Enterprise New Thermal Generation Project. This analysis included a proposed plan of finance
as well as the projected rate increases necessary to cashflow operations and the debt for the
project.
The original plan of finance included:
A draw-down construction loan to fund incremental construction beginning in June 2027
One large issuance of $190,000,000 Electric Revenue Bond issued in 2029 to repay the
draw-down construction loan and finance the balance of the project.
o 30-year maturity schedule
o Note: The City traditionally issues 20-year bonds. However, 30-year bonds are
the industry standard for larger electric revenue bonds.
The goal of this original plan of finance was to utilize construction loans early in the construction
period allowing for slower ramp-up to maximum annual debt service of $13,030,000 beginning
in FY 2030-31.
WHAT HAS CHANGED
Bids have been received and contracts approved for the purchase of the RICE engines. The
purchase agreement requires significant progress payments not contemplated in the original
analysis.
5
Revised Electric Plan of Finance
August 18, 2026
Page 2
RICE Engine progress payments require $72,007,000 to be paid within the first 8 months. The full
progress payment schedule is as follows:
Payment Date Amount Payment Date Amount
July 2026 $18,002,000 May 2029 $3,600,000
November 2026 $7,201,000 November 2029 $3,600,000
March 2027 $10,801,000 February 2030 $1,800,000
March 2029 $18,002,000 October 2030 $1,800,000
April 2029 $7,201,000 TOTAL $72,007,000
In addition, engineers have now provided the full construction schedule with anticipated monthly
construction costs through October 2030, summarized in the chart below (including the RICE
Engine progress payments).
Fiscal Year Construction Costs
FY 2026 $424,000
FY 2027 $43,457,000
FY 2028 $16,176,000
FY 2029 $88,317,000
FY 2030 $41,174,000
FY 2031 $3,115,000
Total $192,663,000
PFM ANALYSIS FOR A REVISED PLAN OF FINANCE
PFM analyzed two potential plans of finance:
1. OPTION 1: Electric Revenue Bonds issued in 2026 and 2028, a draw-down construction
loan in 2029 to fund the final phase of construction, and Electric Revenue Bonds issued
in 2030 after completion to repay the construction loan.
a. Plan of finance detailed project funding:
i. $50,533,000 financed by Electric Revenue Bonds issued October 2026
ii. $71,550,000 financed by Electric Revenue Bonds issued March 2028
iii. $70,580,000 Construction Draw-down loan issued April 2029
iv. $70,580,000 to repay 2029 construction loan with Electric Revenue Bonds
issued October 2030
b. Total all-in cost of Option 1 plan of finance: $341,218,331
i. All-in cost includes principal, interest, underwriter’s discount and all costs of
issuance
2. OPTION 2: Draw-down construction loans issued in 2026 and 2029, with Electric
Revenue Bonds issued in 2028 and 2030 to repay the construction loans.
a. Plan of finance detailed project funding:
i. $88,498,000 Construction Draw-down loan issued November 2026
ii. $88,498,000 to repay construction loan 1 financed by Electric Revenue
Bonds issued November 2028
iii. $104,165,000 Construction Draw-down loan issued January 2029
iv. $104,165,000 to repay construction loan 2 financed by Electric Revenue
Bonds issued October 2030
b. Total all-in cost of Option 2 plan of finance: $391,969,300
i. All-in cost includes principal, interest, underwriter’s discount and all costs of
issuance.
6
Revised Electric Plan of Finance
August 18, 2026
Page 3
MOODY’S ELECTRIC ENTERPRISE RATING CONSIDERATIONS
The City’s outstanding $9,500,000 Electric Revenue Bonds issued in 2015 are currently rated
‘Aa2’ by Moody’s Ratings.
It is unlikely the City will issue Electric Revenue Bonds to fund the $192,663,000 project cost
without a rating downgrade.
The final rating outcome will be based on a number of factors:
The customer base, billing history, kWh generated and sold, solid electric fund cash
reserves, and the institutional presence of Iowa State University all support a strong AA
level rating outcome.
Leverage and debt ratios, together with long-term projected debt service coverage, are
the factors that pressure the rating into the A category.
The Bonds will be issued over a four-year timeframe (2026 – 2030). The normal rating
outlook timeframe is two years.
o Should the rating analyst include just the electric revenue bond to be issued within
the two-year outlook period, a more favorable rating outcome is likely.
o Should the rating analyst include ALL of the electric revenue bond to be issued for
the project, a lower rating outcome is likely.
To help quantify the cost of a potential rating downgrade, PFM has prepared the following table
illustrating the estimated pricing spreads to the Aaa BVAL scale, the incremental cost for each
rating outcome and the estimated present value increase to total debt service. For this analysis,
PFM is using the proposed $51,360,000 Electric Revenue Bonds. The present value of 1 basis
point for the proposed 2026D Bonds is $59,706.25.
Rating
Estimated Pricing
Spread to Aaa BVAL
in Basis Point (Bps)
Increase from
Current Aa2 Rating
In Basis Points (Bps)
Projected Cost for
the 2026 Electric
Revenue Bonds
Aa2 +35 - 40 bps
Aa3 +40 - 45 bps +5 bps +$298,531.25
A1 +45 - 50 bps +10 bps +$597,062.50
A2 +50 - 55 bps +15 bps +$895,593.75
A3 +55 - 60 bps +20 bps +$1,194,125.00
Projected costs of a rating downgrade would be amortized over the 30-year term of the Bonds.
PFM considers a rating of ‘A3’ to be the worst-case outlook, with ‘A1’ or ‘A2’ the likely rating
outcome. The rating outcome is largely dependent upon how the assigned rating analyst applies
the total project cost to be financed in the scorecard.
PFM is optimistic that the first series of Bonds could be issued without the worst-case rating
outcome, particularly because not all of the proposed bonds will be issued within the two-year
rating outlook timeframe. However, Moody’s may still include the full cost of the project in its
scorecard analysis. That is at the sole discretion of the rating analyst and the rating committee.
PFM RECOMMENDATION
PFM recommends changing the plan of finance to Option 1.
The total cost of financing for Option 1 is $50,750,969 less than Option 2, while increasing
maximum annual debt service by approximately $200,000.
Option 1 can be accomplished within the 2.5% annual rate increases as originally
presented in the original plan of finance.
PFM would be pleased to review this analysis with City staff and the City Council in greater detail
at your convenience.
7