HomeMy WebLinkAbout~Master - Resolution accepting completion of the contract for bid package 31-1 (Demolition & Earthwork) with Con-Struct, Inc., of Ames, IA, for the Fitch Family Indoor Aquatic CenterRESOLUTION NO. 26-510
RESOLUTION ACCEPTING COMPLETION OF THE CONTRACT
FOR BID PACKAGE 31-1 (DEMOLITION & EARTHWORK)
FOR THE FITCH FAMILY INDOOR AQUATIC CENTER
FOR THE CITY OF AMES, IOWA
WHEREAS, the Parks and Recreation Department has filed a certificate of
completion for the bid package 31-1 (Demolition & Earthwork) for the Fitch Family Indoor
Aquatic Center for the City of Ames, IA, in accordance with a contract dated 21st day of
March, 2024, by and between the City of Ames, IA, and Con-Struct, Inc., of Ames, IA.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City
of Ames, Iowa, as follows:
Section 1. The total contract for the bid package 31-1 (Demolition & Earthwork)
for the Fitch Family Indoor Aquatic Center has been fully completed by the
Contractor in accordance with the terms of the contract and is hereby accepted
and approved.
Section 2. The total cost of the contract is $597,039.
Section 3. The amount due to Con-Struct, Inc., of Ames, IA, is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are
hereby repealed to the extent of such conflict.
ADOPTED THIS 11th day of August, 2026.
_______________________________ _________________________________
Renee Hall, City Clerk John A. Haila, Mayor
Introduced by: Corrieri
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Corrieri, Junck, Gartin, Rollins
Voting nay: None Absent: None