HomeMy WebLinkAboutA001 - Council Action Form dated July 14, 2026ITEM #:55 DATE:07-14-26 DEPT:PW SUBJECT:2026/27 AIRPORT AIRSIDE IMPROVEMENTS PROJECT (RECONSTRUCTION OF RUNWAY 01/19) COUNCIL ACTION FORM BACKGROUND: The Capital Improvements Plan (CIP) includes the Airport Airside Improvements program, which provides for the reconstruction of Runway 01/19 and associated airfield improvements at the James Herman Banning Ames Municipal Airport. The project includes full reconstruction of Runway 01/19 and associated airfield improvements, including portions of taxiways, lighting, drainage, grading, signage, and pavement markings necessary to maintain FAA design standards and long-term operational functionality. The base bid is for the Runway 01/19 reconstruction and associated airfield improvements. Bid Alternate A involves the reconstruction of the navigational aid building that is located at the south end of Runway 01/19. Bids were received on June 30, 2026. Seven bids were received, and all bidders were determined to be responsive. The bid results are summarized below: Bidder Base Bid Bid Alternate A (Reconstruct Nav. Aid Bldg) Total Engineer’s Estimate $24,178,537.50 $232,500.00 $24,411,037.50 Flynn Company, Inc. (Dubuque, IA)$18,993,597.00 $125,194.00 $19,118,791.00 Elder Corporation (Des Moines, IA)$19,026,017.30 $132,200.00 $19,158,217.30 Manatts, Inc. (Brooklyn, IA)$19,378,607.00 $125,194.00 $19,503,801.00 Reilly Construction Co., Inc. (Ossian, IA)$20,149,349.50 $115,585.00 $20,264,934.50 Concrete Technologies Inc. (Grimes, IA)$20,360,415.80 $117,326.15 $20,477,741.95 Boomerang Corporation (Anamosa, IA)$23,001,215.00 $115,585.00 $23,116,800.00 Hawkins Construction Company (Omaha, NE)$26,035,271.50 $131,850.00 $26,167,121.50 Flynn Company, Inc., of Dubuque, Iowa, submitted the apparent low responsive, responsible 1 bid for the Base Bid and Bid Alternate A, in the amount of $19,118,791. Bolton & Menk, Inc. has reviewed the submitted bid documents, checked references for the bidder, and is recommending award to Flynn Company, Inc. Because this project is anticipated to be funded primarily through FAA Airport Improvement Program (AIP) grants, award of the contract should be conditioned upon FAA concurrence and receipt of the federal grant funding necessary to finance the project. The City intends to submit a grant application for the full construction cost of the project, including both the Base Bid and Bid Alternate A, in an effort to maximize the amount of federal funding that may be awarded in 2026. As previously reported to City Council, the FAA is expected to fund the project through two separate grant awards. Any eligible project costs not funded through the initial grant, anticipated in fall 2026, are expected to be included in a second grant award in early 2027. The Table 1 below demonstrates the overall project budget that was presented to City Council on June 9, 2026 during the approval of the plans and specifications. This budget table represents the project budget before bidding results were received. Table 1 Fiscal Year Available Revenues Pre Bid Amount Anticipated Expenses Pre Bid Amount Design Phase Design Phase 2024/25 Federal Grant - Design (95/5)$1,140,095 PSA Design $1,196,000 2024/25 Airport Improvements Fund $130,000 Design Independent Fee Evaluation (IFE)$3,500 Construction Phase Construction Phase 2025/26 Federal Grant - Construction (95/5) (estimated) $10,450,000 Construction Independent Fee Evaluation (IFE)$7,000 2026/27 Federal Grant - Construction (90/10) (estimated) $15,282,000 PSA Amendment 1: AGIS Design Survey $120,000 2024/25 Airport Improvements Fund (Reprogrammed) $25,000 PSA Amendment 2: Construction Admin $2,500,000 2025/26 G.O. Bonds $531,750 PSA Amendment 3: Glide Slope Coordination $150,000 2026/27 G.O. Bonds $623,250 Construction: Base Bid (estimated)$24,182,500 2026/27 G.O. Bonds (previously issued)$975,000 Construction: Bid Alternate A (estimated)$232,500 2026/27 Airport Improvements Fund $42,500 Work By FAA on Navaids 2 Glide Slope - Watts Antenna - Refurbishment Kits, Assistance and Setup $320,000 FAA RA - End Fire Glide Slope Design Review $100,000 FAA RA - End Fire Glide Slope Construction Observation and Support $200,000 FAA Flight Check for Visual Navaids $50,000 FAA Flight Check for Electronic Navaids - End Fire Glideslope, Localizer, MALSR $120,000 Total Revenue Pre Bid $29,199,595 Total Expense Pre Bid $29,179,500 The Table 2 below has been revised to reflect the results of receiving bids for the project. The table conservatively allocates anticipated grant revenues between fiscal years in 2025/26 and 2026/27 based on the anticipated timing of those grant awards while recognizing that the actual distribution of grant funding between fiscal years will be determined by the FAA. Table 2 Fiscal Year Revised Available Revenues Post Bid Amount Revised Anticipated Expenses Post Bid Amount Design Phase Design Phase 2024/25 Federal Grant - Design (95/5)$1,140,095 PSA Design $1,196,000 2024/25 Airport Improvements Fund $130,000 Design Independent Fee Evaluation (IFE)$3,500 Construction Phase Construction Phase 2025/26 Federal Grant - Construction (95/5) (estimated) $10,450,000 Construction Independent Fee Evaluation (IFE)$7,000 2026/27 Federal Grant - Construction (90/10) (estimated) $10,517,212 PSA Amendment 1: AGIS Design Survey $120,000 2024/25 Airport Improvements Fund (Reprogrammed) $25,000 PSA Amendment 2: Construction Admin $2,500,000 2025/26 G.O. Bonds $531,750 PSA Amendment 3: Glide Slope Coordination $150,000 3 2026/27 G.O. Bonds $623,250 Construction: Base Bid (This Council Action)$18,993,597 2026/27 G.O. Bonds (previously issued)$975,000 Construction: Bid Alternate A (This Council Action)$125,194 2026/27 Airport Improvements Fund $42,500 Work By FAA on Navaids Glide Slope - Watts Antenna - Refurbishment Kits, Assistance and Setup $320,000 FAA RA - End Fire Glide Slope Design Review $100,000 FAA RA - End Fire Glide Slope Construction Observation and Support $200,000 FAA Flight Check for Visual Navaids $50,000 FAA Flight Check for Electronic Navaids - End Fire Glideslope, Localizer, MALSR $120,000 Revised Total Revenue Post Bid $24,434,807 Revised Total Expense Post Bid $23,885,291 The inclusion of the Pre Bid and Post Bid budget tables is to highlighted that while the bid results reflect a project savings of $5,292,246.50 for the combination of the base bid and bid alternate A, the majority of the project savings will be experienced by the FAA due to the federal grant funding. Ninety percent (90%) of the savings from the bid results will be realized by the FAA in their grant award to the City of Ames. The local match of the grant (10%) or $529,224.65, is the savings that the City of Ames will realize in G.O. Bonds based off the bid results. ALTERNATIVES: 1. The City Council may: a. Approve final plans and specifications for the 2026/27 Airport Airside Improvements Project (Reconstruction of Runway 01/19). b. Award the 2026/27 Airport Airside Improvements Project (Reconstruction of Runway 01/19) to Flynn Company, Inc., of Dubuque, Iowa, in the amount of $19,118,791, contingent upon FAA concurrence and receipt of the necessary Airport Improvement Program (AIP) grant funding. c. Approve submission of the Federal Aviation Administration (FAA) Airport Improvement Program (AIP) grant application requesting federal funding for the full 2026/27 Airport Airside Improvements Project (Reconstruction of Runway 01/19), 4 including the Base Bid and Bid Alternate A. 2. Reject the bids and direct staff to modify the project and rebid at a future date. CITY MANAGER'S RECOMMENDED ACTION: The reconstruction of Runway 01/19 is necessary to maintain the long-term safety, operational reliability, and functionality of the Ames Municipal Airport. The project will replace deteriorated pavement infrastructure, improve associated airfield systems, and maintain compliance with applicable Federal Aviation Administration (FAA) design standards while positioning the Airport to continue serving existing and future aviation needs. Flynn Company, Inc., submitted the apparent low responsive, responsible bid, and Bolton & Menk, Inc., recommends award of the contract contingent upon FAA concurrence and receipt of the Airport Improvement Program (AIP) grant funding necessary to finance the project. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as noted above. In anticipation of construction impacts to the John Deere lease area, the City's Legal Department has prepared a Memorandum of Understanding (MOU) establishing a framework for coordination between the City and Deere regarding temporary use of leased property during construction. The MOU is intended to be executed administratively and provides for a future lease amendment once the contractor has established a detailed construction schedule and defined the specific areas of the lease required for staging, access, or construction a c ti v i ti e s . At that time, Public Works staff will return to the City Council with a construction-related lease amendment for approval. Following the award of contract, staff will work with the contractor, design consultant, fixed- base operator, and Airport users to coordinate the schedule of construction activities and ensure the project impacts are appropriately communicated to all affected parties. ATTACHMENT(S): Engineers Letter of Recommendation Overview Map 5 Ames-Runway 01-19 Reconstruction-Engineers Letter of Recommendation.docx July 1, 2026 Mr. Damion Pregitzer, P.E. PTOE Traffic Engineer City of Ames 515 Clark Avenue Ames, IA 50010-6135 RE: Recommendation of Award Reconstruct Runway 01/19 (5,701 ft. by 100 ft.) and Portions of Associated Taxiways & Runway 13/31 (within Runway 01/19 Safety Area) FAA AIP Project No.: 3-19-0004-036-2026-AIP BMI Project No.: 24X.136121.000 Dear Mr. Pregitzer, At 2:00 p.m. local time on June 30, 2026, bids were received for the Reconstruct Runway 01/19 (5,701 ft. by 100 ft.) and Portions of Associated Taxiways and Runway 13/31 (within Runway 01/19 Safety Area) project. The Engineer’s Opinion of Probable Cost for the Base Bid of the project was $24,178,537.50 and Bid Alternate ‘A’ was $232,500.00 for a total of estimated cost of $24,411,037.50. Seven (7) bids were received, all bidders were responsive, and bids are summarized as follows: Bidder City Base Bid Bid Alternate ‘A’ Total (Base Plus Alternate) Flynn Company, Inc. Dubuque, IA $18,993,957.00 $125,194.00 $19,118,791.00 Elder Corporation Des Moines, IA $19,026,017.30 $132,200.00 $19,158,217.30 Manatts, Inc. Brooklyn, IA $19,378,607.00 $125,194.00 $19,503,801.00 Reilly Construction Co., Inc. Ossian, IA $20,149,349.50 $115,585.00 $20,264,934.50 Concrete Technologies Inc. Grimes, IA $20,360,415.80 $117,326.15 $20,477,741.95 Boomerang Corporation Anamosa, IA $23,001,215.00 $115,585.00 $23,116,800.00 Hawkins Construction Company Omaha, NE $26,035,271.50 $131,850.00 $26,167,121.50 The bid received from Flynn Company, Inc. for the base bid plus bid alternate A was 21.6% below the Engineer’s Opinion of Probable Cost for the project and was determined to be the lowest responsive, responsible bidder. Bolton & Menk, Inc. has reviewed the bid documents submitted and checked references for this bidder and was satisfied with responses given. 1519 Baltimore Dr Ames, IA 50010 Ph: (515) 233-6100 Bolton-Menk.com 6 H:\AMES\24X136121000\6_Plans-Specs\C_Bids Received\After Bid Documents\Ames-Runway 01-19 Reconstruction-Engineers Letter of Recommendation.docx Mr. Damion Pregitzer, P.E., PTOE Page Two July 1, 2026 Therefore, Bolton & Menk, Inc. recommends award of the Reconstruct Runway 01/19 (5,701 ft. by 100 ft.) and Portions of Associated Taxiways and Runway 13/31 (within Runway 01/19 Safety Area) Project to Flynn Cmpany, Inc., of Dubuque, Iowa, for the total amount of $19,118,791.00 (Nineteen Million, One Hundred Eighteen Thousand, Seven Hundred Ninety- one and 00/100 Dollars), which includes for the Base Bid and Bid Alternate ’A’, based on FAA concurrence and receipt of available FAA funding. The bid tabulation is attached for your use. Feel free to contact me should there be any questions related to this project. Sincerely, Joseph R. Roenfeldt, P.E. Aviation Project Manager Attachment: Bid Tabulation 7 > > > > POTENTIAL BATCH PLANT/ STAGING AREA DETENTION POND DETENTION POND WETLAND AREA RO F Z ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ RO F Z ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZ ROFZRS A RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RS A RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RO F A RO F A ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA RO F A RO F A RO F A ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROFA ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF A ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z ROF Z RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA LO C C R LOC CR LOC CR LOC CR LOC CR LOC CR LOC CR LOC CR LO C C R LOC CR LOC CR LOC CR LOC CR LOC CR LOC CR PO F Z PO F Z PO F Z POFZ PO F Z PO F Z PO F Z IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IA O F Z IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IAOFZ IA O F Z GS CR GS CR GS CR GS CR GS CR GS CR GS CR GS CR GS CR GS CR GS C R TW A 1 TW A 2 TW A 4 TW B RUN W A Y 1 3 / 3 1 RUNWA Y 1 / 1 9 TW B 3 TW A TW A TW A TW B TW B TW B 2 TW B 1 WEST A P R O N SO U T H AP R O N TAXIL A N E C TW A 3 S RIVERSIDE DRIVE TW A XXXXX X X X X X X X X X X X X X X X X X X X X X X X X XXXXXXXXX X X X X XXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XXXX X X XXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X XXXXXXXXXXXXXXXX X X X X X X X X X X X X X X X X X PR O P PROPPROP PR O P PR O P PR O P PROP PRO P PR O P PR O P PR O P PR O P PROPPROPPROPPROP PR O P PR O P PR O P PR O P PR O P PR O P PR O P PROP PROP PROP PROP PROP PR O P PROP PR O P PROP PR O P PR O P PROP PROP PROP PROP PROP PROP PROP PROP PR O P PR O P PROP PROP PR O P PROPPROPPROP PR O P PROPPROPPROPPROP PROPPROPPROP PR O P X X X X X X XXX X X X X X X X X X X EXISTING DRAINAGE SWALE SHOWN FOR REFERENCE TEMPORARY CULVERT LIKELY NEEDED FOR ACCESS ROUTE ACROSS FEILD. AI R P O R T R O A D EXTRA STAGING/STORAGE AREA SHEET B o l t o n & M e n k , I n c . 20 2 6 , A l l R i g h t s R e s e r v e d c H: \ A M E S \ 2 4 X 1 3 6 1 2 1 0 0 0 \ C A D \ C 3 D \ 1 3 6 1 2 1 J 0 1 . d w g 6/ 4 / 2 0 2 6 1 1 : 3 3 : 4 9 A M DESIGNED DRAWN CHECKED CLIENT PROJ. NO. ISSUED FOR DATENO.AMES MUNICIPAL AIRPORT RECONSTRUCT RUNWAY 1/19 0T5.136121 1519 BALTIMORE DRIVE AMES, IA 50010 Phone: (515) 233-6100 Email: Ames@bolton-menk.com www.bolton-menk.comR CDW CDW JPR KEY MAP J.00 CONSTRUCTION SAFETY & PHASING PLAN - BOTH DIVISIONSFEETSCALE 0 300 600 HORZ. OVERALL PHASING PLAN - BOTH DIVISIONS R WIDEN EXISTING FIELD ACCESS TO 50' OR WHAT EVER IS NEEDED FOR CONSTRUCTION REMOVE AND REPLACE FENCE AS NEEDED. NO CULVERT NEEDED. LOCATION OF EXISTING CONCRETE FIELD ACCESS. DO NOT DISTURB. 12" WATER MAIN AND FIRE HYDRANT AVAILABLE CONTRACTOR SHALL COORDINATE WITH UTILITY AND IS RESPONSIBLE FOR ALL COSTS ASSOCIATED WITH THE CONNECTION, METERING AND USE OF ANY WATER APPROXIMATE LOCATION OF POWER POLE SINGLE-PHASE OR THREE-PHASE POWER IS AVAILABLE CONTRACTOR SHALL COORDINATE WITH UTILITY AND IS RESPONSIBLE FOR ALL COSTS ASSOCIATED WITH THE CONNECTION, METERING AND ELECTRICITY USED FOR UTILITY ACCOMMODATIONS AND COORDINATION CONTACT MARK IMHOFF (CITY OF AMES ELECTRIC) AT 515-239-5175 WATER CONTRACTOR: AMES UTILITY SERVICES AT 515-239-5120 OR PUBLIC WORKS 515-239-5160  LEGEND AIRPORT PROPERTY LINE AIRPORT PERIMETER FENCE CONTRACTORS ACCESS ROUTE - CURRENT PHASE CONSTRUCTION STAGING/STORAGE/STOCKPILE LOCATION RUNWAY CLOSURE MARKER TAXIWAY CLOSURE MARKER LOW-PROFILE BARRICADES PHASE 1 PREPARATION WORK - OCCURRING IN 2026 PHASE 1 WORK AREA PHASE 2 WORK AREA PHASE 3 WORK AREA PROP PROP PROP PROP PROP XXXXXXXXXXXX X INSTALL 18" MIN CULVERT AND PROVIDE A NEW CONSTRUCTION ACCESS FIELD ENTRANCE. REMOVE AND REPLACE FIELD FENCE AS NEEDED. NOTE: CONTRACTOR MAY USE MILLINGS FOR ACCESS OR HAUL ROUTES BUT MUST REMOVE AND DISPOSE OF ON DEDICATED WASTE AREAS. 40' ACCESS GATE 40' ACCESS GATE ACCESS IMPROVEMENTS TO AIRPORT ROAD/FIELD ENTRANCE 8