HomeMy WebLinkAboutA001 - Council Action Form dated May 26, 2026ITEM #:34 DATE:05-26-26 DEPT:PW SUBJECT:2024/25 CDBG INFRASTRUCTURE PROGRAM (S RIVERSIDE DRIVE - S 4TH STREET TO LINCOLN WAY) COUNCIL ACTION FORM BACKGROUND: This project included new water main infrastructure that improved water quality, reduced the number of lead services in the water distribution system, increased firefighting service capacity in this area, and benefited a HUD-identified Low- and Moderate-Income (LMI) population (Census Tract 10). This project was located along S Riverside Drive from S 4th Street to Lincoln Way. On October 21 , 2025, City Council awarded a contract to Iowa Water & Waste System of Boone, Iowa, in the amount of $559,321.30. Three change orders were approved by as part of the project. Change Order No. 1 was approved in the amount of $22,835 for water main 4" repair, hydrant relocation, and water main abandonment. Change Order No. 2 was approved by city council in the amount of $81,792.08. Change Order No. 3 (balancing), administratively approved by staff, was an increase in the amount of $7,224.93 to reflect actual measured quantities completed during construction. Construction was completed in the amount of $671,173.31. Revenue and expenses associated with the project are estimated as follows: Description Available Revenue Estimated Expenses CDBG Funding $ 700,000 Construction (this council action) $ 671,173.31 Engineering/Administration $ 20,000.00 TOTAL $ 700,000 $ 691,173.31 ALTERNATIVES: 1. Accept the 2024/25 CDBG Infrastructure Program (S Riverside Drive - S 4th Street to Lincoln Way) project as completed by Iowa Water & Waste System, LLC of Boone, IA in the amount of $671,173.31. 2. Direct staff to pursue changes to the project. 1 CITY MANAGER'S RECOMMENDED ACTION: This project has been completed in accordance with the approved plans and specifications and improved water quality and firefighting capacity in a LMI census tract area. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as described above. ATTACHMENT(S): Project Map.pdf Certification Letter 2024-25 CDBG Infrastructure Program (S Riverside Dr).pdf 2 2024/25 CDBG Infrastructure Program S. Riverside Dr - Lincoln Way to S. 4th St N 2ND ST LINCOLN WAY 6TH ST N 3RD ST N H A Z E L A V E N 4TH S T N R I V E R S I D E D R N R U S S E L L A V E N M A P L E A V E N O A K A V E 5TH ST N 4TH S T Ames I O W A Location Map N 3RD ST N 2ND ST N 4TH S T N H A Z E L A V E N R I V E R S I D E D R N M A P L E A V E LINCOLN WAY S 2ND ST S 3RD ST S O A K A V E S M A P L E A V E S H A Z E L A V E UN I V E R S I T Y B L V D S R U S S E L L A V E CENTER DR CY T O W N L N N O A K A V E Work Area 16TH ST DU F F A V E 17TH ST DO U G L A S A V E LINCOLN WAY S 2ND ST S H A Z E L A V E S 3RD ST S R U S S E L L A V E LINCOLN WAY S 2ND ST S 3RD ST S 4TH ST S M A P L E A V E S H A Z E L A V E UN I V E R S I T Y B L V D S R U S S E L L A V E CENTER DR 3 Smart Choice Public Works Department 515.239.5160 main 515 Clark Ave. P.O. Box 811 515.239.5404 fax Ames, IA 50010 www.CityofAmes.org May 21, 2026 Honorable Mayor and Council Members City of Ames Ames, Iowa 50010 Dear Mayor and Council Members: I hereby certify the 2024/25 CDBG Infrastructure Program (S. Riverside Drive – S. 4th Street to Lincoln Way) project was completed in an acceptable manner by Iowa Water & Waste System, LLC, of Boone, Iowa, in the amount of $671,173.31 and was inspected by the Public Works Department of the City of Ames, Iowa. Sincerely, Justin A. Clausen, PE, CPWP-M Public Works Director JAC/lbc cc: City Clerk, Finance, Contractor, Administrative Services, Project File 4