HomeMy WebLinkAboutA029 - Ames Animal Services UpdateITEM #:33
DEPT:POLICE
May 12, 2026
Staff Report
AMES ANIMAL SERVICES UPDATE
BACKGROUND:
The City's Animal Shelter, located at 325 Billy Sunday Road, is in need of replacement. The
existing facility is undersized and experiences challenges related to weatherization,
mechanical equipment, and other aging systems. City staff has been working through the
planning stages to develop a new animal shelter facility for the past several years.
In November 2024, staff became aware that the property at 2715 Dayton Ave, which recently
housed Eagle’s Loft daycare, was for sale. The City Council obtained an option to purchase
the property following an assessment of the potential to renovate it into a new animal shelter.
On December 26, 2024, the City Council approved an agreement not to exceed $66,360 with
INVISION Architecture LTD (INVISION), Des Moines, Iowa, to analyze the existing conditions
and needs and identify future requirements for a modern animal shelter facility. Following that
evaluation, INVISION was to provide the City with a conceptual design and a preliminary cost
estimate that would be approved as a change order.
After receiving the conceptual design report, on February 18, 2025, City Council approved the
purchase of 2715 Dayton Avenue in the amount of $1.1 million. At that same meeting, staff
notified City Council that an anonymous lead donation of $3 million had been obtained.
On September 2, 2025 City Council approved a change order to the INVISION design contract
for the completion of schematic design, design development, and construction documents,
bidding phase, and construction administration. The contract incorporates references to best
practices outlined by the American Society of Veterinarians (ASV) Guidelines for Sheltering,
and the need to meet the requirements for Animal Welfare of the Iowa Department of
Agriculture and Land Stewardship (IDALS). In addition, the contract outlines the City's interest
in reducing greenhouse gas emissions.
SERVICES AND FACILITY DESCRIPTION:
Through discussions with the design team and animal care experts during the design process,
staff learned that the terms "control" and "shelter" were outdated and being less frequently
used to describe facilities like the one being pursued. Based on the new building and the
variety of animal services provided, "Ames Animal Control" will be changing to "Ames Animal
Services." The new facility will also reflect this change.
1
DESIGN DEVELOPMENT:
INVISION and its sub-consultants have worked with City staff and fundraisers to complete a
schematic design and design development of the facility. The design is broken into three
spaces: 1) cat spaces, 2) dog spaces, and 3) human spaces. This design features an
approximately 1,700 square-foot addition that will be utilized as dog spaces and will have a flat
roof to accommodate mechanical equipment. An addition was determined to be the best
financial option for dog spaces due to the needed sound attenuation, plumbing, and durability
required in dog holding areas. This addition will also connect to the outside dog run areas. The
attached presentation shows the schematic design and outside and inside renderings based
on the design development phase.
Sustainability
As part of the design contract, INVISION was to identify options to reduce greenhouse gas
emissions. These options could include geothermal heating and cooling, ensuring that the
building is ready to install future solar panels, LED lighting, variable frequency drives for
pumps, and a heat recovery system.
Due to the cost estimate, it does not appear that geothermal heating and cooling is financially
feasible. While there is the possibility of a Federal tax incentive for 30% of the costs
associated with geothermal, it is estimated that adding geothermal could cost 50% to 100%
more than the current estimated HVAC costs. Therefore, it was determined that air-source
heat pumps and heat recovery are the best sustainable options within the current
funding available.
The roof is planned for replacement and will be designed to hold future solar panels. The
electrical equipment will also be designed for the addition of future solar. There is also the
possibility on this site to use ground-mounted solar panels on the west end of the property.
FINANCIAL AND DESIGN DEVELOPMENT ESTIMATE:
The following table shows the current funding and estimated costs for the project. The Design
Development construction estimate was completed by Stecker-Harmsen, a sub-consultant to
INVISION. The design development estimate received based on the information provided
exceeded the established construction budget. Therefore, staff and the design team worked to
value-engineer to a reduced project cost, including making sure the Furniture, Fixtures and
Equipment (FF&E) budget was accurate. This process involved removing items deemed not
necessary due to cost, refining the FF&E budget number with accurate estimates, and
identifying possible alternatives should funding be available. This process resulted in the
revised project being within the identified funding.
The table below shows the breakdown of expenses and revenues for the project. It should be
noted that the design development estimate includes a 5% design contingency for items that
were potentially not in the estimate during the development of construction documents.
2
EXPENSES FUNDING SOURCES
Previous Site Investigation $ 4,075
2715 Dayton Purchase Option 5,000
Site Acquisition 1,100,000
Conceptual Design 66,360
Change Order No. 1 (Detailed
Design/Construction Specs)588,000
Construction/Renovation 4,870,976
FF&E/Permits 450,000
Construction Contingency 250,000
3rd Party Testing/Geotechnical 40,000
Stormwater
Quality CIP
Funding
$ 30,000
FY 2023/24
General Fund
Savings
100,000
Council Priorities
Capital Fund 2,855,000
Lead Donation 3,000,000
Donation
Campaign 1,500,000
TOTALS $ 7,374,411 $7,485,000
3
Bid Alternates
Based on the value engineering discussion and decisions, some items were marked as add-
alternates for construction if the budget allows, based on favorable bids. The first add-
alternate is for a screen wall on the catio area on the south side of the building. This would
allow for more shade, visual interest, and the opportunity for signage in front of the catios. The
second alternative is for additional parking to the west of the current parking lot. Other items
may be designated as alternatives during the construction document phase and will be
identified when the project goes to bid.
Fundraising
As of this date, volunteer fundraising has met the goal with a lead donation of $3,000,000 for
this project and another $1,500,000 through small donations and gifts to specific project items.
The design team has worked with the fundraising group to make sure the spaces are
appropriate for the donation request.
Additional Scope
Near the end of design development, staff, volunteers, and donors discussed the proposed
schematic design of the dog holding areas and determined that the route to take dogs from
those areas to the outside yards was not ideal. Instead, the ideal scenario is to allow access
from the dog holding areas directly to the yards with a door available in each area. Due to
ADA requirements, this would require expanding the proposed addition and changes to the
yards and egress from the building.
Since modifying the design at this point would require design rework, it was determined that
any changes would require additional design services in addition to the added construction
costs from the increased scope. INVISION provided an estimate of the additional design and
construction costs to accomplish these changes. Additional design costs are be $24,440, and
the additional construction costs are estimated at $154,416 (including a proportionate increase
in contingency) for the expansion of the proposed addition, for a total of $178,856.
The City has received a commitment from the fundraising team to cover the total
$178,856 for the improvements to the dog area. The work related to the redesign will
impact the schedule. The schedule shown below reflects the revised timing. The costs are not
shown in the table above, but will be reflected in future project budgets presented to the City
Council. Staff will prepare and approve the change order for INVISION's contract following this
Council meeting. No further substantial changes to the design are anticipated.
NEXT STEPS
The next steps are to complete the construction documents and bid the project. The estimated
schedule is shown below:
Construction Documentation
Now – June 2026
Cost Estimate by Stecker-Harmsen @ 75% construction documentation
4
Bidding
July 2026 – August 2026
Construction
Summer 2026 – Spring 2027
The contract will be awarded to a prime general contractor. The City will hire a third-party
testing company and will manage the construction with the assistance of the architect and sub-
consultants.
STAFF COMMENTS:
Once the City Council can receives this report, work will proceed with preparation of
construction documents. The revised dog area will be designed and its costs will be covered
by additional donor funding in excess of the $4,500,000 goal.
ATTACHMENT(S):
Ames Animal Services Project - City Council Presentation Update 2026.05.12.pdf
5
City of Ames
May 12, 2026
Ames Animal Services
6
Agenda
Tuesday 05.12.2026 Introduction
Design
•Floor Plan
•Exterior Material Palette
•Exterior Design Concepts
•Exterior Renderings
•Interior Material Palette
•Interior Renderings
Schedule
•Review CD and Bidding Schedule
Budget
•Review Budget & DD Cost Opinion
7
Plan Update
Current Floor Plan
8
Materiality
Stain existing brick. Warm wood-toned elements. Building graphics
>
AM
E
S
9
Design Concepts
Street Presence – The Billboard – Entry Experience – Catios & Animals on Display
KELLER WILLIAMS REALTY – NEUMANN MONSON SAN ANTONIO ANIMAL SHELTER – LAKE|FLATO
COFFEE CATS CAFE
10
Existing - NE
N
11
Proposed - NE
N
12
Design Concepts
Entry Experience – Human Scale
•Human scale entry element.
•Dark stained brick
contrasted with warm wood
tone material
•Cat Bay Windows & Bun
Run at Entry
•Playful graphic elements
N
13
Proposed – NW
N
14
Design Concepts
Building Addition
•Rooftop mechanical louver
with playful graphics
•High windows for natural
light into dog spaces
•Dark exterior finish to match
existing building brick stain
•Exterior dog runs with
artificial turf grass
N
15
Existing - SE
N
16
Proposed - SE
N
BASE BID
17
Design Concepts
Street Presence – Catios on Display
•Catio spaces viewable
from Dayton Road
N
BASE BID
18
Design Concepts
Street Presence – The Billboard
•Large building signage/graphic
element visible from cars driving
by @ 55 MPH
•Catio Screenwall will be an Add
Alternate.
N
ADD ALTERNATE
19
Design Concepts
Street Presence – Catio Display
20
Design Concepts
Entry Experience
21
Design Concepts
Entry Experience
22
Design Concepts
Entry Experience
23
Wayfinding and Graphics
NOT TO SCALE
24
LOBBY PHOTO WALL + WAYFINDING
WALL PAINT HOLLOW METAL FRAMESWALL PAINT SOLID SURFACE LAMINATE TILE FLOORS + COVE BASE
25
LOBBY RETAIL WALL + WAYFINDING
WALL PAINT HOLLOW METAL FRAMESWALL PAINT SOLID SURFACE LAMINATE TILE FLOORS + COVE BASE
26
EXOTICS CORRIDOR
WALL PAINT VINYL WALLCOVERINGWALL PAINT EPOXY FLOORINGHOLLOW METAL FRAMESWALL PAINT 27
Schedule
•Construction Documentation
•Current – June 2026
•Cost Estimate by Stecker-Harmsen @ 75% CDs
•Bidding
•July 2026 – August 2026
•Construction
•Summer 2026 – Spring 2027
28
Budget
29
Thank you
+
30