PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month.
Additionally, staff, along with representatives from Story Construction and RDG
Planning and Design, will provide an in-person update once per quarter (January,
April, July, & October). If anything occurs during the project that requires Council
action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Update (Attachment A).
There are several updates for City Council regarding the project.
Precast Concrete Panels
Conversations regarding the 25-year warranty for the stain are ongoing as staff
believes the warranty should cover labor as well as materials. The contractor has
agreed to stain a 100' wide by 8' high mock up on the north side of the
natatorium, although there is no timeline for when the work will be completed.
Once the mock up is done, staff will present its findings at a future Council
meeting.
Heated Sidewalk
Contractors removed the concrete that included the wire to heat the sidewalk.
New wire was placed and new concrete was poured. The work was completed
April 15-16 at no cost to the City.
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
Southwest Glazing
The temporary tempered glass has been removed, and the permanent glazing
has been installed. This was also completed at no cost to the City.
State Inspection
Although the State did issue the City a license for each basin, two waivers
needed to be submitted regarding water inlets in the lap pool and Recreation
pool. State Code requires wall inlets in the lap pool to be no further than 5' from
the corners. The southwest corner has one inlet at 5'9" from the corner and the
other inlet is 7' from the corner. In the recreation pool, a floor inlet was not
installed. Waters Edge has submitted these waivers and provided modeling
showing that the water in both pools circulates sufficiently, which was the concern
from the State.
Building Commissioning
The City hired a Commissioning Agent (CA) to ensure all equipment is working
as expected. There are several items that the CA is working with the contractors
to correct. Most notably, there are two items related to the imbalance of
pressures and potential moisture between the natatorium and non-natatorium
space.
Soil and Ground Water Contamination
No contaminated soils or groundwater has been found to date.
CHANGE ORDER SUMMARY:
There were two change orders since the last report, and the changes thus far on
the project are shown on the change order log (Attachment B).
Folding Seat Revisions - $2,507. Staff directed the contractor to install different
folding seats in the locker rooms which included drywall repair and painting.
Electrical Work Associated with Water Slide Railing, Boiler E-Stops, and
Miscellaneous Items - $17,430. These items were completed per staff direction.
To date, construction change orders for the project total $546,059, or 26.0%
of the contingency budget. The contingency for this project is $2.1 million
with a current balance of $1,553,941. There is also $1 million set aside for
mitigation of contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2026-4.pdf
Attachment B - Change Order Log - 4-28-26.pdf
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
April 2026
PROJECT PROGRESS:
1. The State Pool Inspection: Water’s Edge submitted the waiver requests to the State for record
and the team anticipates the forms will satisfy the State’s requirements.
2. The final glazing (glass) was installed on the southwest elevation of the Natatorium.
3. The sitework punch list was completed by the civil design team.
4. The low voltage wiring contractor continues their work on the integration of the Audio-Visual
system with the needs of the facility.
5. The excavation for the southwest biocell started and the last of the utility structures are
installed. Final grading and plantings will be complete by mid-May.
6. Owner Trainings will continue as Parks & Recreation begins using the facility.
7. Parks & Recreation held lifeguard certification training.
8. The City held a Donor Wall dedication event.
9. The HVAC Commissioning testing will begin early May. All mechanical equipment is online,
including warm weather units.
10. Building Envelope Consult inspections are complete.
11. Contractors are over 90% complete with their punch list activities.
12. Story Construction will continue to facilitate the closeout documentation process with the
design team and the City.
PROJECT PHOTOS: [Next page]
Page 1 of 2 3
Progress
Description
Taken Date
04/16/2026 at 08:49 am
Upload Date
04/16/2026 at 08:50 am
Uploaded By
Deb Thurmond
Progress
Description
Taken Date
04/16/2026 at 08:46 am
Upload Date
04/16/2026 at 08:46 am
Uploaded By
Deb Thurmond
Story Construction Co.
Printed on Tue Apr 21, 2026 at 08:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 2 of 2
DONOR WALL - FITCH
HISTORY PANEL IN
PROGRESS
SOUTHWEST PERMANENT
GLAZING INSTALLED
4
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
All Star Concrete 2 Increase Concrete Thickness in Maintenance Area $ 7,029 $ 2,082,961
All Star Concrete 3 Polished Concrete Floors $ 22,000 $ 2,060,961
All Star Concrete 4 Mechanical Equipment Relocation in Maintenance Area $ 7,885 $ 2,053,076
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,031,011
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,027,032
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,029,984
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,031,187
Core Construction 5 Channel Support $ 3,739 $ 2,027,448
Core Construction 6 Hoist Beam End Stop $ 1,356 $ 2,026,092
Forrest & Associates 1 Channel Support $ 1,163 $ 2,024,929
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 1,982,800
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 1,979,942
Lansink Construction 3 Interior Finishes $ 3,021 $ 1,976,921
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 1,972,926
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 1,971,287
Lansink Construction 6 Wood Blocking $ 752 $ 1,970,535
Lansink Construction 7 Waterproof Exterior - Aquatic Mechanical $ 1,167 $ 1,969,368
Lansink Construction 8 Converting Room 108 Shower to a Roll In Shower $ 2,653 $ 1,966,715
Lansink Construction 9 Donor Wall $ 33,224 $ 1,933,491
Lansink Construction 10 Additional Changing Room Tile $ 2,597 $ 1,930,894
Lansink Construction 11 Roller Shade Add in Aquatic Manager Office $ 1,103 $ 1,929,791
Lansink Construction 12 Folding Seats & Sanitary Dispensers $ 3,329 $ 1,926,462
Lansink Construction 13 Stainless Steel Railing at the Water Slide $ 10,732 $ 1,915,730
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 1,914,083
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 1,908,967
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 1,912,790
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 1,911,047
Orning Glass Company 3 Auto Door Operators $ 9,757 $ 1,901,290
Orning Glass Company 4 Entry Way Column Metal Wrap $ 438 $ 1,900,852
Orning Glass Company 5 Temporary Glazing $ 3,870 $ 1,896,982
Hilsabek Schacht 1 Wet Room Door Change $ - $ 1,896,982
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 1,896,982
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 1,893,425
Hilsabek Schacht 4 Site Signage $ (350) $ 1,893,775
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,891,177
Hilsabek Schacht 6 Omit Painting - Mechanical Rooms $ (3,280) $ 1,894,457
Hilsabek Schacht 7 Close Off Top Of South Wellness Precast $ 3,808 $ 1,890,649
Hilsabek Schacht 8 Wellness Precast Vertical Joints & Frame Top of Masonry $ 3,656 $ 1,886,993
Hilsabek Schacht 9 Curtain Wall 12 & Metal Panels $ 599 $ 1,886,394
Hilsabek Schacht 10 AV Media Player Touch Pads Antenna & Mic $ 1,212 $ 1,885,182
Hilsabek Schacht 11 Folding Seat Revisions $ 2,507 $ 1,882,675
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 4/28/26)
Highlighted Rows Indicate New Change Orders Since the Last Update
5
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,881,305
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,878,613
Sande Construction 3 Sump Pump Rail System and Backwash Pit Grate $ 4,744 $ 1,873,869
Sande Construction 4 Emergency Stops Added $ 269 $ 1,873,600
Sande Construction 5 Temporary Glazing Credit & SS Railing at Water Slide $ (3,685) $ 1,877,285
Midwest Fire Sprinkler 1 Omit Sprinkler Heads at Main Entry Exterior $ (700) $ 1,877,985
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,880,305
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,841,603
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,829,570
Brockway Mechanical 4 Pool Trench Drain Float Alarm $ 2,318 $ 1,827,252
Brockway Mechanical 5 Converting Room 108 Shower to a Roll In Shower $ 7,180 $ 1,820,072
Brockway Mechanical 6 Aquatic Storage Rooms HVAC $ 6,626 $ 1,813,446
Brockway Mechanical 7 Aquatic Storage Rooms Piping Insulation $ 1,141 $ 1,812,305
Brockway Mechanical 8 Mechanical Equipment Relocation in Maintenance Area $ 44,749 $ 1,767,556
Brockway Mechanical 9 Boiler E-Stop & Carbon Monoxide Detectors $ 404 $ 1,767,152
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,745,199
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,730,962
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,726,283
Van Maanen Electric 4 Exterior Signage Lighting Controls $ 1,007 $ 1,725,276
Van Maanen Electric 5 Pool Trench Drain Float Alarm $ 1,356 $ 1,723,920
Van Maanen Electric 6 Wiring Auto Door Operators in Corridor 108 $ 959 $ 1,722,961
Van Maanen Electric 7 ICN Connection $ 9,040 $ 1,713,921
Van Maanen Electric 8 New Light Fixture for Vestibule & Exterior $ 2,411 $ 1,711,510
Van Maanen Electric 9 Change TV Mounting Heights $ 1,049 $ 1,710,461
Van Maanen Electric 10 Redo Conduit in Thickened Slab in Maintenance Area $ 483 $ 1,709,978
Van Maanen Electric 11 AV Media Player Touch Pads Antenna & Mic $ 15,144 $ 1,694,834
Van Maanen Electric 12 Aquatic Storage HVAC & Boiler Breaker Voltage $ 8,348 $ 1,686,486
Van Maanen Electric 13 Distributed Antenna System Credit and Combo Starter NEMA 4 $ (2,412) $ 1,688,898
Van Maanen Electric 14 Microwave Circuit & Flood Prevention Valve Alert $ 1,524 $ 1,687,374
Van Maanen Electric 15 Emergency Stops Added and AV Webcast Changes $ 7,233 $ 1,680,141
Van Maanen Electric 16 Maintenance Area, Water Slide Railing, Boiler E-Stops, Misc. $ 17,430 $ 1,662,711
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,654,964
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,609,545
Con-Struct 3 Planting Revisions $ (737) $ 1,610,282
Con-Struct 4 Curb Strip Restoration $ 9,702 $ 1,600,580
Con-Struct 5 Southeast Planting Revisions & Dormant Seed Matting $ 2,575 $ 1,598,005
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,583,487
Lakeside 1 Site Signage $ 2,120 $ 1,581,367
Lakeside 2 CyRide Concrete Pad $ 296 $ 1,581,071
Lakeside 3 Replace Curb & Gutter on Oak Avenue $ 27,130 $ 1,553,941
Totals / Current Balance $ 546,059 $ 1,553,941