HomeMy WebLinkAboutA011 - Motion accepting the Fitch Family Indoor Aquatic Center Monthly ReportTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:March 24, 2026
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 13
MEMO
PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month.
Additionally, staff, along with representatives from Story Construction and RDG
Planning and Design, will provide an in-person update once per quarter (January,
April, July, & October). If anything occurs during the project that requires Council
action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Update (Attachment A).
There are several updated for City Council regarding the project.
Precast Concrete Panels
Three stain colors have been selected and applied to the mockup panel. Details
regarding this item are being presented in a separate Council Action Form on the
March 24 City Council Agenda.
Polished Concrete Floors
The work to grind the lobby and hallway floors to a Class C finish has been
completed. The finished product in most of the areas look good but some
inconsistencies remain. Staff is not recommending any additional work to these
floors.
Heated Sidewalk
Staff was notified on March 18 that the heated sidewalk in front of the main
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
entrance is not working. Story Construction is working with contractors to
determine a fix which may include removing the concrete and redoing this work.
The heated sidewalk was included due the north facing entrance and the
potential of snow/ice buildup during the winter months.
Substantial Completion Dates
The building has been substantially completed and contractors are working on
addressing punch list items. A temporary Certificate of Occupancy has been
issued, and staff is moving in equipment and supplies to get the facility ready for
opening. Staff training is also occurring at this time.
Please note that the glazing for the southeast portion of the natatorium has a
long lead time and will need to be installed in early to mid April. Efforts to
expedite the procurement of the glazing were unsuccessful. Temporary tempered
glass was installed in this area at no cost to the City. The temporary glass will be
replaced when the correct glass panels arrive.
State Inspection
The state inspection regarding all components related to the operation of the
aquatic areas occurred on March 3 with a follow-up inspection done on March 6.
There are a couple of items that are still outstanding; however, the City did
receive licenses for each basin, and they are eligible to be opened for use.
Soil and Ground Water Contamination
No contaminated soils or groundwater has been found to date.
CHANGE ORDER SUMMARY:
There were 13 change orders since the last report, and the changes thus far on
the project are shown on the change order log (Attachment B). The attachment
includes a 14th change order for Lansink Construction, which is detailed in a
separate Council Action Form since it requires City Council approval.
Polished Concrete Floors - $22,000. Staff directed the contractor to grind the
polished concrete floors to a Class C finish. Of the total approximate cost of
$34,000, the City will pay $20,000 as Story Construction is providing the City a
$2,000 credit, and the contractor is responsible for the remaining cost.
Mechanical Equipment Relocation in Maintenance Area - $7,885. This is for
concrete associated work related to the relocation of equipment within the
Maintenance area.
Folding Seats and Sanitary Dispensers - $3,329. Staff desired different seats and
dispensers in the locker rooms and restrooms.
Stainless Steel Railing at the Water Slide - $10,732. The railing was installed per
City Inspections.
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Temporary Glazing - $3,870. The temporary enclosure was removed so the
contractor could install framing for the glass. Since there is a ten-week lead time,
temporary glass was installed. The contractor responsible for the delay that
caused this issue is providing a credit to the City to offset this cost. Additionally,
Story Construction is paying $3,870 to the contractor as the total cost of this
glazing was $7,740.
Emergency Stops Added - $269. Staff asked for two additional emergency stops
for the play structure and the current channel to be added in the lifeguard room.
Temporary Glazing Credit & SS Railing at Water Slide - ($3,685). This reflects
the credit for the aforementioned glazing and some work for the stainless-steel
railing at the water slide.
Mechanical Equipment Relocation in Maintenance Area - $44,749. This change
order was approved by City Council at its March 10, 2026 meeting.
Boiler E-Stop and Carbon Monoxide Detectors - $404. These items were added
per City Inspections.
AV Media Player Touch Pads Antenna & Mic - $15,144. Staff added this
equipment to enhance programming in the natatorium.
Aquatic Storage HVAC & Boiler Breaker Voltage - $8,348. Changes were made
as staff had concerns regarding air flow in the aquatic storage rooms.
Distributed Antenna System (DAS) Credit and Combo Starter NEMA 4 -
($2,142). City IT staff indicated the DAS is not needed due to other systems in
place and a credit was issued.
Microwave Circuit and Flood Prevention Valve Alert - $1,524. These were added
per staff direction.
Maintenance Area, Water Slide Railing, Boiler E-Stops, Misc. - $7,233. These are
electrical portions of previously described change orders.
To date, construction change orders for the project total $526,122, or
25.05% of the contingency budget. The contingency for this project is $2.1
million with a current balance of $1,573,878. There is also $1 million set
aside for mitigation of contamination issues, which has not been used at
this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2026-3.pdf
Attachment B - Change Order Log - 3-24-26.pdf
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
3
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
March 2026
*Natatorium: Wellness, Recreation and Lap Pools
*Non-Natatorium: All supporting rooms outside of the Natatorium including Mechanical, Loading,
Locker Rooms, Offices, Main Lobby & Check-In, and the Alternate Walk Path
PROJECT PROGRESS:
1. The State Pool Inspection was held at the beginning of March. The inspector complimented the
facility design and construction and provided feedback on a handful of action items for the
project team. Those items included two variances: one for the wall inlet layout for the Lap Pool,
of which two inlets deviate slightly from specified layout - the other for a floor inlet in the Rec
Pool, of which one of ten inlets is missing. The inspector believes the pools’ optimal circulation
and turnover rates should still be acceptable. For record verification, Water’s Edge Aquatic
Design will produce a water flow modeling report and file this information via a waiver request
form with the state. The pool registration was granted to the City on March 6, 2026.
2. The City of Ames Inspection Division held inspections at the beginning of March. A temporary
Certificate of Occupancy was granted for the facility. Exceptions to this certificate include the
completion of the southwest bioretention cell which is currently fenced off and will be installed
as soon as weather allows. The temporary tempered glass in the southwest corner of the
Natatorium will be replaced with the final “fritted design” glass to match the southeast corner of
the building.
3. Parks & Recreation started lifeguard certification training in the facility.
4. Punch lists were completed for the building. Contractors are actively engaged in their punch list
items and continue to work on various in-progress change orders.
5. The Sitework punch list is outstanding until the southwest biocell is completed. The project
team recently revisited an item on the site demolition drawing sheet for an existing monitoring
well. The drawings included a note to “protect” the monitoring well. The design intent was to
protect and, in addition, maintain and keep the monitoring well for future monitoring use. The
well has since been covered by the parking lot grading and paving and is inaccessible.
6. The low voltage wiring contractor continues their work on the Security Management System
and Audio-Visual scopes and anticipates hosting Owner training at the end of this month.
7. Owner Trainings will continue as Parks & Recreation begins using the facility.
8. The Lobby desk and the City’s furniture was installed.
9. The HVAC Commissioning meeting and reporting continues.
10. Exterior architectural metals were completed.
Page 1 of 5 4
11. All mechanical equipment was started up except for one condensing unit which is warm
weather dependent.
12. Building Envelope Consult inspection reporting will be resolved over the next month.
13. Story Construction will continue to facilitate the closeout documentation process with the City.
PROJECT PHOTOS: [Next page]
Page 2 of 5 5
Progress
Description
Taken Date
03/16/2026 at 02:45 pm
Upload Date
03/17/2026 at 11:23 am
Uploaded By
Deb Thurmond
Name
20260316_144535.jpg
Progress
Description
Taken Date
03/16/2026 at 02:44 pm
Upload Date
03/17/2026 at 11:23 am
Uploaded By
Deb Thurmond
Name
20260316_144458.jpg
Story Construction Co.
Printed on Tue Mar 17, 2026 at 11:24 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
DONOR WALL INSTALL IN
PROGRESS
PORTION OF WALK
TRACK WITH OWNER
FURNITURE
Page 3 of 5 6
Aerial Photos
Description
Taken Date
03/16/2026 at 02:12 pm
Upload Date
03/16/2026 at 02:41 pm
Uploaded By
Mitch Anderson
Name
DJI_0887.JPG
Aerial Photos
Description
Taken Date
03/16/2026 at 02:12 pm
Upload Date
03/16/2026 at 02:41 pm
Uploaded By
Mitch Anderson
Name
DJI_0886.JPG
Story Construction Co.
Printed on Tue Mar 17, 2026 at 11:16 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
LAP POOL AND NORTH
WALL ELEVATION
LAP, REC POOL AND
REC POOL PLAY
STRUCTURE
Page 4 of 5 7
Aerial Photos
Description
Taken Date
03/16/2026 at 02:15 pm
Upload Date
03/16/2026 at 02:41 pm
Uploaded By
Mitch Anderson
Name
DJI_0893.JPG
Story Construction Co.
Printed on Tue Mar 17, 2026 at 11:16 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
LAP POOL VIEW TO
SOUTHEAST
Page 5 of 5 8
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
All Star Concrete 2 Increase Concrete Thickness in Maintenance Area $ 7,029 $ 2,082,961
All Star Concrete 3 Polished Concrete Floors $ 22,000 $ 2,060,961
All Star Concrete 4 Mechanical Equipment Relocation in Maintenance Area $ 7,885 $ 2,053,076
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,031,011
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,027,032
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,029,984
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,031,187
Core Construction 5 Channel Support $ 3,739 $ 2,027,448
Core Construction 6 Hoist Beam End Stop $ 1,356 $ 2,026,092
Forrest & Associates 1 Channel Support $ 1,163 $ 2,024,929
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 1,982,800
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 1,979,942
Lansink Construction 3 Interior Finishes $ 3,021 $ 1,976,921
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 1,972,926
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 1,971,287
Lansink Construction 6 Wood Blocking $ 752 $ 1,970,535
Lansink Construction 7 Waterproof Exterior - Aquatic Mechanical $ 1,167 $ 1,969,368
Lansink Construction 8 Converting Room 108 Shower to a Roll In Shower $ 2,653 $ 1,966,715
Lansink Construction 9 Donor Wall $ 33,224 $ 1,933,491
Lansink Construction 10 Additional Changing Room Tile $ 2,597 $ 1,930,894
Lansink Construction 11 Roller Shade Add in Aquatic Manager Office $ 1,103 $ 1,929,791
Lansink Construction 12 Folding Seats & Sanitary Dispensers $ 3,329 $ 1,926,462
Lansink Construction 13 Stainless Steel Railing at the Water Slide $ 10,732 $ 1,915,730
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 1,914,083
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 1,908,967
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 1,912,790
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 1,911,047
Orning Glass Company 3 Auto Door Operators $ 9,757 $ 1,901,290
Orning Glass Company 4 Entry Way Column Metal Wrap $ 438 $ 1,900,852
Orning Glass Company 5 Temporary Glazing $ 3,870 $ 1,896,982
Hilsabek Schacht 1 Wet Room Door Change $ - $ 1,896,982
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 1,896,982
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 1,893,425
Hilsabek Schacht 4 Site Signage $ (350) $ 1,893,775
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,891,177
Hilsabek Schacht 6 Omit Painting - Mechanical Rooms $ (3,280) $ 1,894,457
Hilsabek Schacht 7 Close Off Top Of South Wellness Precast $ 3,808 $ 1,890,649
Hilsabek Schacht 8 Wellness Precast Vertical Joints & Frame Top of Masonry $ 3,656 $ 1,886,993
Hilsabek Schacht 9 Curtain Wall 12 & Metal Panels $ 599 $ 1,886,394
Hilsabek Schacht 10 AV Media Player Touch Pads Antenna & Mic $ 1,212 $ 1,885,182
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,883,812
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,881,120
Sande Construction 3 Sump Pump Rail System and Backwash Pit Grate $ 4,744 $ 1,876,376
Sande Construction 4 Emergency Stops Added $ 269 $ 1,876,107
Sande Construction 5 Temporary Glazing Credit & SS Railing at Water Slide $ (3,685) $ 1,879,792
Midwest Fire Sprinkler 1 Omit Sprinkler Heads at Main Entry Exterior $ (700) $ 1,880,492
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,882,812
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,844,110
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,832,077
Brockway Mechanical 4 Pool Trench Drain Float Alarm $ 2,318 $ 1,829,759
Brockway Mechanical 5 Converting Room 108 Shower to a Roll In Shower $ 7,180 $ 1,822,579
Brockway Mechanical 6 Aquatic Storage Rooms HVAC $ 6,626 $ 1,815,953
Brockway Mechanical 7 Aquatic Storage Rooms Piping Insulation $ 1,141 $ 1,814,812
Brockway Mechanical 8 Mechanical Equipment Relocation in Maintenance Area $ 44,749 $ 1,770,063
Brockway Mechanical 9 Boiler E-Stop & Carbon Monoxide Detectors $ 404 $ 1,769,659
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,747,706
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,733,469
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,728,790
Van Maanen Electric 4 Exterior Signage Lighting Controls $ 1,007 $ 1,727,783
Van Maanen Electric 5 Pool Trench Drain Float Alarm $ 1,356 $ 1,726,427
Van Maanen Electric 6 Wiring Auto Door Operators in Corridor 108 $ 959 $ 1,725,468
Van Maanen Electric 7 ICN Connection $ 9,040 $ 1,716,428
Van Maanen Electric 8 New Light Fixture for Vestibule & Exterior $ 2,411 $ 1,714,017
Van Maanen Electric 9 Change TV Mounting Heights $ 1,049 $ 1,712,968
Van Maanen Electric 10 Redo Conduit in Thickened Slab in Maintenance Area $ 483 $ 1,712,485
Van Maanen Electric 11 AV Media Player Touch Pads Antenna & Mic $ 15,144 $ 1,697,341
Van Maanen Electric 12 Aquatic Storage HVAC & Boiler Breaker Voltage $ 8,348 $ 1,688,993
Van Maanen Electric 13 Distributed Antenna System Credit and Combo Starter NEMA 4 $ (2,412) $ 1,691,405
Van Maanen Electric 14 Microwave Circuit & Flood Prevention Valve Alert $ 1,524 $ 1,689,881
Van Maanen Electric 15 Maintenance Area, Water Slide Railing, Boiler E-Stops, Misc. $ 7,233 $ 1,682,648
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,674,901
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,629,482
Con-Struct 3 Planting Revisions $ (737) $ 1,630,219
Con-Struct 4 Curb Strip Restoration $ 9,702 $ 1,620,517
Con-Struct 5 Southeast Planting Revisions & Dormant Seed Matting $ 2,575 $ 1,617,942
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,603,424
Lakeside 1 Site Signage $ 2,120 $ 1,601,304
Lakeside 2 CyRide Concrete Pad $ 296 $ 1,601,008
Lakeside 3 Replace Curb & Gutter on Oak Avenue $ 27,130 $ 1,573,878
Totals / Current Balance $ 526,122 $ 1,573,878
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 2/24/26)
Highlighted Rows Indicate New Change Orders Since the Last Update
9