PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month.
Additionally, staff, along with representatives from Story Construction and RDG
Planning and Design, will provide an in-person update once per quarter (January,
April, July, & October). If anything occurs during the project that requires Council
action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Update (Attachment A).
There are several items that City Council needs to be updated on regarding the
project.
Precast Concrete Panels
Staff continues to work with Story and RDG regarding the precast concrete
panels. A Notice to Cure letter has been sent to the Bid Package Contractor
which included the need to respond by February 23. Three stain colors have
been selected to be applied to the mockup panel and will be done soon. Staff,
along with RDG and Story Construction representatives, will provide an update to
City Council in March.
Polished Concrete Floors
The concrete floors in the lobby and the hallway to the locker rooms were
specified to be a polished Class B finish which is best described as a "salt &
pepper" look. Staff is not happy with the inconsistencies, imperfections, and the
overall appearance of these areas. Thus, staff has directed the contractor to go
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
to a Class C finish which will look similar to a terrazzo floor.
A Construction Change Directive (CCD) was issued to keep the project moving
forward. The work began on February 9 and is expected to be completed by
February 23. The cost estimate to do this work is $34,210. Staff has had
conversations with Story and the contractor regarding who is to pay for this
change. Through these discussions, it has been agreed that the City will pay
$20,000, the contractor $12,210, and Story $2,000. All parties feel this is a fair
resolution and a change order has been processed administratively.
Substantial Completion Dates
The revised substantial completion dates are as follows:
February 27 - Non-natatorium spaces
February 27 - Natatorium spaces
Please note that the glazing for the southeast portion of the natatorium has a 10-
week lead time and will need to be installed in early April. Efforts to expedite the
procurement of the glazing have been unsuccessful. Story has informed the Pool
Bid Package Contractor that they are responsible for paying for the purchase and
installation of temporary tempered glass in this area.
State Inspection
The state inspection is scheduled for March 3 and will encompass all
components related to the operation of the aquatic areas. In preparation for this,
Story, RDG, and City staff are reviewing the inspection checklist to ensure the
facility is ready to go.
Soil and Ground Water Contamination
It should be noted there have been no contaminated soils or groundwater found
to date.
CHANGE ORDER SUMMARY:
There were five change orders since the last report, and the changes thus far on
the project are shown on the change order log (Attachment B).
Roller Shade in Aquatic Manager Office - $1,103. Staff requested the contractor
add a roller shade on the door of the office to provide privacy when needed.
AV Media Touch Pads, Antenna, and Mic - $1,212. Staff directed these to be
installed as they are needed for aqua classes that will be offered in the lap pool
and wellness pool.
Aquatic Storage Rooms HVAC - $6,626. Staff asked for fans to be installed and
changes be made to the HVAC system to provide increased air flow in these
rooms to dry wet equipment between uses.
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Aquatic Storage Rooms Piping Insulation - $1,141. The Building Commissioning
agent recommended insulating the piping in these rooms and staff agreed.
Redo Conduit in Thickened Slab in Maintenance Area - $483. Staff requested a
thicker slab in the maintenance area and because of this, conduit had to be
installed deeper than what was originally done.
To date, construction change orders for the project total $406,732, or
19.37% of the contingency budget. The contingency for this project is $2.1
million with a current balance of $1,693,268. There is also $1 million set
aside for mitigation of contamination issues, which has not been used at
this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2026-2.pdf
Attachment B - Change Order Log - 2-24-26.pdf
Parks and Recreation 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
3
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
February 2026
*Natatorium: Wellness, Recreation and Lap Pools
*Non-Natatorium: All supporting rooms outside of the Natatorium including Mechanical, Loading,
Locker Rooms, Offices, Main Lobby & Check-In, and the Alternate Walk Path
PROGRESS THIS PAST MONTH:
1. All pool painting and tiling was completed.
2. Pool accessories (volleyball nets, ladders, etc.) were installed.
3. Pool deck caulking and sealing was completed.
4. Pool fill started.
5. Natatorium painting and lighting was completed.
6. Polished concrete floor was completed per design change from the city.
7. Check-In desk in the Lobby will be installed.
8. Interior storefront framing and glazing continued.
9. Low voltage wiring for fire alarm, cameras and audio/visual continued.
10. HVAC Controls wiring continued.
11. Exterior curtain wall framing was installed at Natatorium southwest.
12. Exterior roof edge metals were installed.
13. Job trailers were removed from the parking lot.
14. Parking lot striping and signage was installed.
15. Final mechanical, electrical and plumbing installations continued in the Aquatic and Electrical
Mechanical Rooms.
16. Final cleaning started.
17. Owner Trainings started.
18. Coordination meetings continued for mechanical equipment startup with the affected Bid
Package Contractors. Various mechanical equipment was started up.
19. Building Envelope Consult inspections continued for curtain wall glazing and precast
penetrations.
20. Design team site visits and field observations continued.
21. Requests for Information continued to be processed between the Bid Package Contractors,
Story Construction, and RDG Planning & Design.
Page 1 of 8 4
WORK PLANNED FOR UPCOMING MONTH:
1. Final mechanical equipment will be started up.
2. HVAC Commissioning will begin.
3. All storefront and curtain wall glazing will be completed except for the southwest exterior
glazing which will be installed early April.
4. Exterior metal soffit panels will be installed.
5. Final cleaning will be completed.
6. Punch List will be recorded and distributed to contractors.
7. Pool filling will be complete and State Pool Inspection will be completed.
8. Final Fire and Life Safety Inspections will be completed for Temporary Certificate of Occupancy,
allowing building turnover to the city. The southwest quadrant of the site will be temporarily
fenced off through Spring 2026 to allow safe install of the bioretention cell as soon as the
ground thaws. The Final Certificate of Occupancy will be granted once this work is completed.
9. Owner Trainings will continue.
10. Building Envelope Consult inspections will be completed for curtain wall glazing and sealing
exterior wall penetrations.
SCHEDULE SUMMARY:
Construction Substantial Completion Date:
Non-Natatorium: February 27, 2026
Natatorium: February 27, 2026
PROJECT PHOTOS: [Next page]
Page 2 of 8 5
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
02/04/2026 at 01:24 pm
Upload Date
02/04/2026 at 01:24 pm
Uploaded By
Deb Thurmond
Name
IMG_2026_02_04_13_24…
Progress
Description
Taken Date
02/04/2026 at 01:25 pm
Upload Date
02/04/2026 at 01:25 pm
Uploaded By
Deb Thurmond
Name
IMG_2026_02_04_13_25…
LIGHTING AND FINAL
CLEANING - VIEW TO NORTH
FINAL CLEANING OF
DUCTWORK IN PROGRESS
Page 3 of 8 6
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
02/17/2026 at 12:11 pm
Upload Date
02/17/2026 at 12:11 pm
Uploaded By
Deb Thurmond
Name
IMG_2026_02_17_12_11…
Aerial Photos
Description
Taken Date
02/16/2026 at 01:09 pm
Upload Date
02/16/2026 at 01:19 pm
Uploaded By
Mitch Anderson
Name
D1BD701E-E34C-43F3-B…
WELLNESS POOL READY
TO FILL & STOREFRONT
FRAMING IN PROGRESS
WATER SLIDE STAIRS AND
RUNOUT TUB
Page 4 of 8 7
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Aerial Photos
Description
Taken Date
02/16/2026 at 01:08 pm
Upload Date
02/16/2026 at 01:18 pm
Uploaded By
Mitch Anderson
Name
7E34FC69-0026-4E3A-8…
Aerial Photos
Description
Taken Date
02/16/2026 at 12:52 pm
Upload Date
02/16/2026 at 01:21 pm
Uploaded By
Mitch Anderson
Name
C1F2DD47-5F85-47C9-A…
REC POOL READY FOR
PLAY STRUCTURE
ROOF STRUCTURE
FOLLOWING CLEANING
Page 5 of 8 8
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Aerial Photos
Description
Taken Date
02/16/2026 at 12:51 pm
Upload Date
02/16/2026 at 01:21 pm
Uploaded By
Mitch Anderson
Name
EBC2887C-6006-4169-9…
Progress
Description
Taken Date
02/17/2026 at 12:07 pm
Upload Date
02/17/2026 at 12:07 pm
Uploaded By
Deb Thurmond
Name
IMG_2026_02_17_12_07…
LAP POOL ACCESSORIES
INSTALLED & READY TO FILL
CHILLER EQUIPMENT READY
TO BRING ONLINE DURING
POOL FILL
Page 6 of 8 9
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
02/17/2026 at 12:07 pm
Upload Date
02/17/2026 at 12:07 pm
Uploaded By
Deb Thurmond
Name
IMG_2026_02_17_12_07…
Aerial Photos
Description
Taken Date
02/16/2026 at 12:43 pm
Upload Date
02/16/2026 at 01:22 pm
Uploaded By
Mitch Anderson
Name
EFAEC96B-54CD-48B0-B…
WATER SERVICE ENTRY WITH
PIPE INSULATION & LABELING
EXTERIOR BUILDING NORTH
ELEVATION SHOWING
PARKING LOT STRIPING
Page 7 of 8 10
Story Construction Co.
Printed on Tue Feb 17, 2026 at 11:46 am CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Aerial Photos
Description
Taken Date
02/16/2026 at 12:42 pm
Upload Date
02/16/2026 at 01:22 pm
Uploaded By
Mitch Anderson
Name
0E01EDD2-A398-4650-8…
EXTERIOR SOUTH
ELEVATION SHOWING
GLAZING & WATER SLIDE
Page 8 of 8 11
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
All Star Concrete 2 Increase Concrete Thickness in Maintenance Area $ 7,029 $ 2,082,961
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,060,896
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,056,917
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,059,869
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,061,072
Core Construction 5 Channel Support $ 3,739 $ 2,057,333
Core Construction 6 Hoist Beam End Stop $ 1,356 $ 2,055,977
Forrest & Associates 1 Channel Support $ 1,163 $ 2,054,814
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,012,685
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,009,827
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,006,806
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 2,002,811
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 2,001,172
Lansink Construction 6 Wood Blocking $ 752 $ 2,000,420
Lansink Construction 7 Waterproof Exterior - Aquatic Mechanical $ 1,167 $ 1,999,253
Lansink Construction 8 Converting Room 108 Shower to a Roll In Shower $ 2,653 $ 1,996,600
Lansink Construction 9 Donor Wall $ 33,224 $ 1,963,376
Lansink Construction 10 Additional Changing Room Tile $ 2,597 $ 1,960,779
Lansink Construction 11 Roller Shade Add in Aquatic Manager Office $ 1,103 $ 1,959,676
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 1,958,029
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 1,952,913
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 1,956,736
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 1,954,993
Orning Glass Company 3 Auto Door Operators $ 9,757 $ 1,945,236
Orning Glass Company 4 Entry Way Column Metal Wrap $ 438 $ 1,944,798
Hilsabek Schacht 1 Wet Room Door Change $ - $ 1,944,798
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 1,944,798
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 1,941,241
Hilsabek Schacht 4 Site Signage $ (350) $ 1,941,591
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,938,993
Hilsabek Schacht 6 Omit Painting - Mechanical Rooms $ (3,280) $ 1,942,273
Hilsabek Schacht 7 Close Off Top Of South Wellness Precast $ 3,808 $ 1,938,465
Hilsabek Schacht 8 Wellness Precast Vertical Joints & Frame Top of Masonry $ 3,656 $ 1,934,809
Hilsabek Schacht 9 Curtain Wall 12 & Metal Panels $ 599 $ 1,934,210
Hilsabek Schacht 10 AV Media Player Touch Pads Antenna & Mic $ 1,212 $ 1,932,998
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,931,628
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,928,936
Sande Construction 3 Sump Pump Rail System and Backwash Pit Grate $ 4,744 $ 1,924,192
Midwest Fire Sprinkler 1 Omit Sprinkler Heads at Main Entry Exterior $ (700) $ 1,924,892
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,927,212
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,888,510
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,876,477
Brockway Mechanical 4 Pool Trench Drain Float Alarm $ 2,318 $ 1,874,159
Brockway Mechanical 5 Converting Room 108 Shower to a Roll In Shower $ 7,180 $ 1,866,979
Brockway Mechanical 6 Aquatic Storage Rooms HVAC $ 6,626 $ 1,860,353
Brockway Mechanical 7 Aquatic Storage Rooms Piping Insulation $ 1,141 $ 1,859,212
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,837,259
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,823,022
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,818,343
Van Maanen Electric 4 Exterior Signage Lighting Controls $ 1,007 $ 1,817,336
Van Maanen Electric 5 Pool Trench Drain Float Alarm $ 1,356 $ 1,815,980
Van Maanen Electric 6 Wiring Auto Door Operators in Corridor 108 $ 959 $ 1,815,021
Van Maanen Electric 7 ICN Connection $ 9,040 $ 1,805,981
Van Maanen Electric 8 New Light Fixture for Vestibule & Exterior $ 2,411 $ 1,803,570
Van Maanen Electric 9 Change TV Mounting Heights $ 1,049 $ 1,802,521
Van Maanen Electric 10 Redo Conduit in Thickened Slab in Maintenance Area $ 483 $ 1,802,038
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,794,291
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,748,872
Con-Struct 3 Planting Revisions $ (737) $ 1,749,609
Con-Struct 4 Curb Strip Restoration $ 9,702 $ 1,739,907
Con-Struct 5 Southeast Planting Revisions & Dormant Seed Matting $ 2,575 $ 1,737,332
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,722,814
Lakeside 1 Site Signage $ 2,120 $ 1,720,694
Lakeside 2 CyRide Concrete Pad $ 296 $ 1,720,398
Lakeside 3 Replace Curb & Gutter on Oak Avenue $ 27,130 $ 1,693,268
Totals / Current Balance $ 406,732 $ 1,693,268
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 2/24/26)
Highlighted Rows Indicate New Change Orders Since the Last Update