HomeMy WebLinkAboutA001 - Council Action Form dated March 10, 2026ITEM #:21
DATE:03-10-26
DEPT:PW
SUBJECT:FREEL DRIVE PAVING PROJECT
COUNCIL ACTION FORM
BACKGROUND:
The Freel Drive Paving project involves paving the remaining gravel-surfaced portion of Freel
Drive to SE 5th Street. The current gravel street is unable to withstand the increase in traffic
and the weight of the trucks required to operate the Resource Recovery and Recycling
Campus (R3C). Planning and Zoning requirements also trigger the improvements to the street
in conjunction with the construction of the R3C.
The paving will take place concurrently with the construction of the Resource Recovery and
Recycling Campus. Construction for this project will be staged between the entrances of the
R3C to allow the R3C site construction to occur without interruption.
Freel Drive is currently 23 to 24 feet wide with shallow ditches, whereas the proposed section
will be a 31-foot section with curb and gutter. The existing ditches are planned to be filled and
a storm intake system installed. Due to the very small elevation change along the length of
Freel Drive, the ability to make water drain quickly is very limited. As a result, a percolation
system is planned to be constructed using the intakes to allow water to enter the soil. A tile
system will also be constructed to provide a system overflow.
The base bid will include paving Freel Drive from the end of the current paved section, 765
feet south of Lincoln Way, to SE 5th Street. An alternate will also be included with the
base bid to replace the existing paved section from Lincoln Way, 750' to the south, with
a new 31' section of PCC pavement. This existing pavement is in the early stages of
pavement distress. If funding is available, replacement of the existing pavement will be
considered with the project. The sidewalk along the east side of Freel Drive from
Lincoln Way to SE 5th Street will also be included with the alternate bid, except for the
portion of the sidewalk adjacent to the R3C property which is included in the R3C
construction base bid.
PUBLIC OUTREACH:
Owners and residents along Freel Drive were mailed letters informing them of the R3C project
as well as the Freel Drive paving project. Those impacted by the paving project were then
reached out to directly to inform them of the planned changes to the street width and the
possibility of a sidewalk along the east side of Freel. Feedback was also received to help
develop the staging of the project for businesses that need to maintain access.
The feedback indicated that there was no opposition to the paving project, but property owners
did not want to have to pay for any portion of the improvements.
1
A summary of revenues and projected expenses is shown below:
Description Revenue Expenses
Freel Drive Paving (G.O. Bonds)$ 975,000
Unobligated G.O. Bonds 225,000
Water Utility Funds 40,000
Construction Base Bid Estimate $1,150,000
Engineering/Administration 90,000
TOTAL $1,240,000 $1,240,000
Alternate 1 is estimated to cost $550,000. Additional Unobligated GO bonds could be
considered for if favorable bids for this Alternate are received.
CONSIDERATION OF SPECIAL ASSESSMENT:
Because the existing portion of Freel Drive is unpaved and as such does not meet the current
design standards, Iowa Code Chapter 384 allows for a city to assess certain costs of the
public improvement to abutting private property owners. In order to determine the value that
can be assessed, it is typical to follow an establish formula known as the "Flint Formula" for
calculating the benefits gained by each abutting property. The Flint Formula considers the
frontage of a lot and how many feet abut the public improvement. Additionally, factors such as
lot depth can be used to identify the special benefit gained by the abutting property. The
maximum assessment is capped at 25% of the assessed value of each lot that abuts the
public improvement.
There are 19 lots that abut the unpaved portion of Freel Drive. Of those 19 lots there are
seven distinct owners, of which one is the City of Ames. Staff has preliminarily estimated
that if the City Council desires to pursue a special assessment of the paving costs,
roughly $268,000 of the project costs could be assessed property owners other than
the City of Ames. Assessments could range between $16,000 to $30,000 per lot,
depending on the lot size.
If City Council wishes to pursue the special assessment approach, there is a very detailed
process in Iowa Code Chapter 384 that lays out steps necessary to begin the assessment
process. The first step in this process is to direct staff to formally produce an assessment
schedule for the project, with each lot and proposed assessment indicated. Following
preparation of the assessment schedule, a resolution of necessity and public hearing is held
before approving plans and specifications and setting a bid date. Should this be the
decision of Council it is important that Alternative 3 is chosen so as to follow the
proper steps detailed in the Iowa Code.
ALTERNATIVES:
1. Approve plans and specifications for the Freel Drive Paving project and establish April 8,
2026, as the date of letting and April 14, 2026, as the date of Public Hearing for report of
bids.
2. Direct staff to make changes to this project.
2
3. Direct staff to pursue a special assessment approach and prepare an assessment
schedule for City Council consideration.
CITY MANAGER'S RECOMMENDED ACTION:
Approval of the plans and specifications will keep this project on the April 8, 2026, letting
schedule to allow for construction in 2026. This project will provide an improved street surface
to the new Resource Recovery and Recycling Campus.
Funding for the improvements along Freel Drive are included in the City's budget.
Although the abutting property owners will benefit from the paving of the road, a
special assessment is not currently recommended since the need to upgrade the road
is primarily the result of the operational impact of the new R3C facility on Freel Drive.
Additionally, the requirement to improve the portion of the road fronting the R3C (most
of the necessary improvements) is a condition of the R3C site plan approval. Therefore,
it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as
described above.
ATTACHMENT(S):
Freel Dr Location Map with Alternate.pdf
3
4