HomeMy WebLinkAboutA027 - Resolution approving preliminary plans and specifications for the Resource Recovery & Recycling Campus (R3C)ITEM #:30
DATE:01-27-26
DEPT:P/W
SUBJECT:RESOURCE RECOVERY & RECYCLING CAMPUS
PRELIMINARY PLANS AND SPECIFICATIONS
COUNCIL ACTION FORM
BACKGROUND:
Since 1975, the City's Resource Recovery Plant has received municipal solid waste (MSW)
from throughout Story County, processed it to remove recyclable metals, and converted a
substantial portion of the MSW into a supplemental fuel for use in the City's Power Plant
boilers. Although this system was successful in reducing the volume of MSW that needed to
be landfilled, in recent years this arrangement has resulted in technical, economic, and
regulatory challenges.
In response to these issues, the City is pursuing the development of a new Resource
Recovery & Recycling Campus (R3C). Property has been secured on Freel Drive to site this
new operation. At the facility, MSW will be received from haulers and customers, recyclable
metals will be recovered, and the waste will be loaded into semi trailers to be hauled to the
Carroll County Landfill.
At the June 24, 2025 City Council meeting, the City Council received the conceptual design
and financial analysis report for the Resource Recovery and Recycling Campus (R3C). The
conceptual design and financial analysis were developed by HDR Engineering, Inc. of Omaha,
NE, following a competitive request for proposal (RFP) process.
On September 3, 2025, the City Council approved an amendment to the agreement with HDR
for the detailed design work necessary to bid and construct the new facility. The agreement
also included bid assistance and construction engineering support throughout the project. The
fees for these services total an amount not-to-exceed $965,715.
In September 2025, the City retained Story Construction of Ames, IA to serve as a
Construction Manager as Advisor for this project. Story's role in the project is to : 1) represent
the City during the project, 2) identify opportunities during the design phase for cost-savings or
improved constructability, 3) assist with bidding, and 4) coordinate schedules and workflow for
the various contractors during construction.
The plans and specifications have been completed and are now ready to be issued for bids.
Through the Construction Manager approach, HDR has prepared 11 separate bid packages.
Story will coordinate the work of each individual contractor that receives a contract for the
work.
Project Highlights:
The project contains a main transfer building, a scalehouse, yard waste storage, customer
convenience area, and paved maneuvering and parking areas for equipment. The total site is
approximately 9.5 acres. The attached document contains drawings of the site layout, office
1
and processing areas, and renderings of the building exterior and interior education room. The
key areas of the project are described in more detail below:
The main transfer building will be a pre-engineered metal building structure with footprint of
33,275 sq. ft. The structure will house both the tipping floor (26,100 sq. ft.) and a two-story
office (7,175 sq. ft.). The first floor of the office includes a lobby, reception desk, maintenance
and mechanical rooms, a locker room with separate shower/toilet rooms, and an employee
break room. The second floor includes staff offices, restrooms, an operations room, and an
education room.
The education and operations rooms are designed to provide visibility into other parts of the
facility. From the education room, visitors can observe the scale entry/exit, tipping floor, and
processing area operations. The facility will include an elevator to provide access to the
second floor, in addition to a public-facing internal stairwell and a staff-oriented stairwell near
the tipping floor.
The tipping floor area allows commercial haulers to enter, turn, tip their loads, and exit. Staff
will operate a wheel loader on the floor, using it to load MSW into a shredder. The shredder is
designed to open garbage bags and packaging. The waste will then be passed under a drum
magnet to remove ferrous metals. The remaining waste will pass through two eddy current
separators (ECS) placed in series, which will remove non-ferrous metals. The MSW will then
be returned to the tipping floor where it will be loaded into transfer trailers for transportation to
the landfill. Operators can bypass the processing equipment and load directly into the trailers if
the processing equipment is down or if the MSW does not contain any recyclable metals (e.g.,
food or industrial processing waste).
The scalehouse will consist of a pre-fabricated structure and two scales, serving both inbound
and outbound traffic. This area will be staffed or operated remotely using video and audio
equipment. While commercial customers will enter the tipping floor, residential customers will
be diverted towards a customer convenience area. The customer convenience area contains
roll-off boxes for small quantities of household waste, separated recyclables, and a shack for
household hazardous waste.
Yard waste will be collected on the east side of the site, where it will be stored until it can be
hauled off for disposal. The northern portion of the site will be a storage yard for trucks,
trailers, and other equipment. A fueling area will be situated here, containing double-walled
aboveground storage tanks of both B100 biodiesel and standard diesel fuel. This area will be
accessible for all diesel-powered equipment in the City's vehicle fleet.
Stormwater management will be facilitated through the construction of four large,
interconnected basins around the perimeter of the site. Site development will be coordinated
with the paving of Freel Drive adjacent to the site, which will be taking place in the 2026
construction season.
Public Outreach:
The design details of the project have been shared with the haulers, participating Resource
Recovery System (RRS) members, and Resource Recovery operations staff at several steps
during the design process. These have included an open house for haulers and RRS
Members on October 16, a meeting with partnering RRS members on November 19, a plan
2
Project Revenues Project Expenses
Revenue Abated G.O. Bonds $22,365,486 Land Acquisition (220, 306,
312, 318, 400 Freel Drive)$1,077,500
Electric Utility Fund 2,340,000 Due Diligence prior to closing 15,465
G.O. Bonds 975,000 Conceptual Design and
Financial Modeling 50,000
review with haulers on November 19, and plan reviews with Resource Recovery operations
staff at the 60% and 90% design stages. In addition, City staff, elected officials,
representatives from partner RRS members, and haulers have received project updates
through recurring issues of the R3Cycled Report, an e-newsletter published by City staff.
Bid Packages:
Through the Construction Manager as Advisor delivery method, Story Construction will be
coordinating the work of several individual prime contractors responsible for specific aspects
of the project. HDR and Story have worked to divide the project into 11 separate bid packages
for the work. The packages are:
1. General Construction Work
2. Concrete and Steel Work
3. Gypsum Board Assembly Work
4. Elevator Lift Work
5. Fire Suppression Systems Work
6. Plumbing and HVAC Work
7. Electrical, Communications, Electrical Safety and Security Work
8. Site Demolition and Earth Work
9. Paving and Sidewalk Work
10. Site Utility Work
11. Millwright Process Integration Work
Two add-alternates have been prepared for the project. One add-alternate is for the
installation of a recycling canopy over the customer convenience area. This canopy would
provide some cover from rain and snow for the roll-off boxes that are used to collect
recyclables. However, the canopy would not extend over the drive lane due to fire code and
the need to hoist the roll-offs, meaning the benefit for customers is not significant. Therefore,
staff would like to evaluate the cost for this option against the potential benefits and determine
whether it should be included. The second add-alternate is for the procurement and
installation of a recycling baler. This equipment would allow bulky recyclable materials, such
as cardboard, to be baled into dense cubes for more efficient transportation to their
destination. This is expected to provide a benefit by reducing operating costs.
Budget:
The project budget, including the Freel Drive paving and the procurement of mobile equipment
(both of which will be bid and financed separately from the R3C facility construction project) is
outlined in the table below. It should be noted that a portion of the expenses related to the
fueling area will be charged to Fleet Services rather than the project, although that cost is not
broken out in the table:
3
Final Design 965,715
Final Design Contingency 124,785
Permitting (est.)50,000
Opinion of Probable
Construction Costs for R3C
Facility
16,821,527
Construction Contingency 1,435,020
Construction Inspection (est.)450,950
Construction Manager Fee
(est.)926,524
Construction Manager General
Conditions Costs (est.) 448,000
R3C Construction Subtotal 22,365,486
Mobile Equipment (transfer
trucks and trailers)2,340,000
Freel Drive Paving 975,000
Total Revenues $25,680,486 Project Total $25,680,486
ALTERNATIVES:
1. Approve preliminary plans and specifications for the Resource Recovery & Recycling
Campus (R3C), setting March 3, 2026, as the bid due date and March 10, 2026, as the
date of Public Hearing.
2. Direct staff to make modifications to the project.
CITY MANAGER'S RECOMMENDED ACTION:
This project is essential to ensure the responsible and cost-effective handling and
disposal of Ames and Story County's municipal solid waste and recyclables. The
proposed Resource Recovery and Recycling Campus (R3C) is sized to handle the
anticipated waste of the community over the next 20 years, and includes equipment
that will assist in processing solid waste and removing recyclable metals before being
transported to the landfill for disposal. In addition, the R3C will accommodate the
community's waste diversion and recycling public outreach efforts. The facility will
welcome classrooms, community groups, and other visitors through an education
room and other features that offer a glimpse into waste disposal and recycling for the
community.
4
It is critical that this facility is constructed and operational by July 1, 2027. Delays will
have a substantial impact on solid waste disposal costs, electric rates, or both.
Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative
No. 1, as described above.
ATTACHMENT(S):
R3C Selected Images.docx
5