HomeMy WebLinkAboutA015 - October 28, 2025, Regular Meeting of the Ames City CouncilTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:October 28, 2025
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 18
MEMO
PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month.
Additionally, staff, along with representatives from Story Construction and RDG
Planning and Design, will provide an in-person update once per quarter (January,
April, July, & October). If anything occurs during the project that requires Council
action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Report (Attachment A). Story
Construction and RDG Planning and Design are 97% complete with reviewing
shop drawings and submittals. This activity will continue until 100% complete.
It should be noted there have been no contaminated soils or groundwater found
to date.
CHANGE ORDER SUMMARY:
There were nine change orders recently approved, and the changes thus far on
the project are shown on the change order log (Attachment B). Staff directed
contractors to implement the nine change orders which are detailed below:
1) Additional changing room tile - $2,597. Staff reviewed what was tiled and it did
not convey a sense of completeness. Therefore, staff asked to have additional
areas and headers tiled.
2) Wellness precast vertical joint and frame top of masonry - $3,656. The vertical
joints between some precast panels were specified to be caulked. Staff did not
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
like the appearance, so the joints now have a metal covering. There is a masonry
wall in the maintenance area that did not go to the ceiling. Staff directed the
contractor to frame and drywall the open area so it is closed.
3) Curtain wall and metal panels at southeast corner of building - $599. This was
a unique situation where a joist landed on tube steel header. The tube steel
needed to be foamed and wrapped in plywood to provide a thermal barrier
between the steel and the exterior metal panel. Staff directed this work to be
done.
4) Sump pump rail system and backwash pit grate - $4,744. For the safety of
staff performing maintenance, staff directed the contractor to add a rail system so
the sump pump can be brought to the surface to work on. The backwash pit grate
is not required by code; however, staff felt it is necessary to have to provide a
safe work area and thus directed the contractor to install one.
5) Omit sprinkler heads at main entry exterior - ($700). These are not required on
the exterior so staff approved omitting them.
6) Wiring auto door operators in changing room corridor - $959. Staff directed
two additional operators be added (previous change order) and this is the cost of
wiring them.
7) Planting revisions - ($737). Staff requested changes to the planting plan which
resulted in a deduct.
8) Curb strip restoration - $9,702. Parks and Recreation staff is planting the grass
throughout the site. Since Con-Struct was doing the earthwork, staff requested
they prepare the right of way strips which was not included in the original
contract.
9) Replace curb & gutter on Oak Avenue - $27,130. The curb and gutter along
Oak was in poor shape, so staff directed the contractor to remove and replace.
To date, change orders for the project total $379,298, or 18.06% of the
contingency budget. The contingency for this project is $2.1 million with a
current balance of $1,720,702. There is also $1 million set aside for
mitigation of contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2025-10.pdf
Attachment B - Change Order Log - 10-28-25.pdf
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
October 2025
*Natatorium: Wellness, Recreation and Lap Pools
*Non-Natatorium: All supporting rooms outside of the Natatorium including Mechanical, Loading,
Locker Rooms, Offices, Main Lobby & Check-In, and the Alternate Walk Path
PROGRESS THIS PAST MONTH:
1. Rec Pool concrete footings and walls (shallow end) were completed.
2. Rec Pool excavation of the deep end started.
3. Concrete pool deck pours started and pool deck under slab preparation continues.
4. Drywall hanging and finishing was completed in the non-Natatorium, not including the large,
suspended ceiling in the Lobby.
5. Shower tile was completed throughout.
6. Painting started in the non-Natatorium.
7. Interior storefront framing and glazing started.
8. Exterior signage was installed at the south elevation of the Natatorium.
9. Exterior curtain wall framing continued for the non-Natatorium and started on the Natatorium.
10. Mechanical, electrical and plumbing installations continued in the Aquatic and Electrical
Mechanical Rooms.
11. Owner-furnished CO2 tank was delivered.
12. Perimeter sidewalk demolition, prep and installation continued.
13. Final grading for sitework was completed and landscape plantings started.
14. Subgrade preparation for parking lot pavers started.
15. Exterior precast panels were power washed.
16. Alliant Energy installed the gas service piping to the meter set.
17. Design review meetings were held for Mechanical Commissioning with the Commissioning
Agent and affected Bid Package Contractors.
18. Owner Operations Introductory meetings were held for audio-visual and paging systems.
19. Building Envelope Consult inspections continued for vapor barrier, pool water stop and curtain
wall glazing.
20. Special inspections and testing of concrete and sitework continued.
21. Design team site visits and field observations continued.
22. Submittals and Requests for Information continued to be processed between the Bid Package
Contractors, Story Construction, and RDG Planning & Design.
Page 1 of 15 3
WORK PLANNED FOR NEXT MONTH:
1. Rec Pool concrete will be completed.
2. Pool deck concrete (Phase 1 of 2) will be completed.
3. Pool sandblasting will be completed, in preparation for pool coatings.
4. Painting will continue in the non-Natatorium.
5. Interior storefront framing and glazing will continue throughout.
6. Ceiling grid will be installed.
7. Resinous flooring and polished concrete will be installed.
8. Structural steel supports for lockers and countertops will be installed.
9. Doors and toilet partition installations will start.
10. Mechanical, Plumbing and Electrical will continue in the Aquatic and Electrical Mechanical
Rooms.
11. Exterior curtain wall framing and glazing will be completed at the main entrance.
12. Exterior architectural metal panel installation will start.
13. Perimeter sidewalk demolition, prep and installation will continue.
14. Parking lot pavers will be installed.
15. Owner Operations Introductory meetings will continue.
16. Building Envelope Consult inspections will continue for vapor barrier, pool water stop and
curtain wall glazing.
17. Special inspections and testing of concrete and sitework will continue.
SCHEDULE SUMMARY:
Construction Substantial Completion Date: January 20, 2026
PROJECT PHOTOS: [Next page]
Page 2 of 15 4
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 3 of 15
Aerial Photos
Description
Taken Date
10/20/2025 at 01:30 pm
Upload Date
10/20/2025 at 03:10 pm
Uploaded By
Mitch Anderson
Name
DJI_0712.JPG
Aerial Photos
Description
Taken Date
10/20/2025 at 01:28 pm
Upload Date
10/20/2025 at 03:10 pm
Uploaded By
Mitch Anderson
Name
DJI_0708.JPG
Exterior Natatorium
South Elevation
Signage and Plantings
Exterior Parking Lot
Plantings and Paver
Prep
5
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 4 of 15
Aerial Photos
Description
Taken Date
10/20/2025 at 01:29 pm
Upload Date
10/20/2025 at 03:10 pm
Uploaded By
Mitch Anderson
Name
DJI_0711.JPG
Aerial Photos
Description
Taken Date
10/20/2025 at 01:36 pm
Upload Date
10/20/2025 at 03:10 pm
Uploaded By
Mitch Anderson
Name
DJI_0723.JPG
Exterior Natatorium East
Elevation Final Sitework
Grading
Pool Deck, Rec Pool
Shallow End and Deep
End Excavation Progress
6
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 5 of 15
Progress
Description
Taken Date
09/29/2025 at 10:30 am
Upload Date
10/03/2025 at 09:07 pm
Uploaded By
Eli Rochleau
Name
35BD2E9E-A5EF-41F8-8…
Progress
Description
Taken Date
10/07/2025 at 02:56 pm
Upload Date
10/10/2025 at 05:06 pm
Uploaded By
Eli Rochleau
Name
F705C937-9DB2-4B89-A…
Wellness Pool Bench
Concrete in progress
Wellness Pool West
Deck with Trench Drain
and Signage
7
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 6 of 15
Progress
Description
Taken Date
09/26/2025 at 12:53 pm
Upload Date
09/29/2025 at 08:39 am
Uploaded By
Eli Rochleau
Name
3EBA1591-6D5A-43AB-B…
Progress
Description
Taken Date
10/03/2025 at 10:04 am
Upload Date
10/03/2025 at 02:43 pm
Uploaded By
Eli Rochleau
Name
E5695DEE-8942-4C84-B…
Recreation Pool Shallow
End Walls and Pool
Deck Prep
Recreation Pool
Shallow End Prepared
for Slab Pour
8
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 7 of 15
Progress
Description
Taken Date
10/07/2025 at 01:44 pm
Upload Date
10/10/2025 at 05:07 pm
Uploaded By
Eli Rochleau
Name
DADC79AD-5752-40C4-…
Progress
Description
Taken Date
10/17/2025 at 07:54 am
Upload Date
10/17/2025 at 08:40 am
Uploaded By
Eli Rochleau
Name
2EABF75D-DF72-498B-9…
Lap Pool Deck and
Protection
Mechanical Room
Equipment Pad Pour
9
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 8 of 15
Progress
Description
Taken Date
10/20/2025 at 04:23 pm
Upload Date
10/20/2025 at 04:23 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_10_20_16_23…
Progress
Description
Taken Date
09/25/2025 at 02:40 pm
Upload Date
09/25/2025 at 02:43 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_09_25_14_40…
Mechanical Room Boiler
Equipment Placed
Aquatic Mechanical Room
Guardrail Install
10
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 9 of 15
Progress
Description
Taken Date
09/18/2025 at 01:18 pm
Upload Date
09/18/2025 at 01:18 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_09_18_13_18…
Progress
Description
Taken Date
09/30/2025 at 02:33 pm
Upload Date
10/03/2025 at 08:07 pm
Uploaded By
Eli Rochleau
Name
78B3CE89-4F67-4A7A-B…
Lobby Vestibule Framing
and Drywall
Track and Classroom
Drywall View to South
11
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 10 of 15
Progress
Description
Taken Date
10/20/2025 at 04:24 pm
Upload Date
10/20/2025 at 04:25 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_10_20_16_24…
Progress
Description
Taken Date
10/20/2025 at 04:24 pm
Upload Date
10/20/2025 at 04:25 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_10_20_16_24…
Track and Classroom
Painted View to South
Lobby View to East Wall
Painting in progress
12
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 11 of 15
Progress
Description
Taken Date
09/25/2025 at 10:29 am
Upload Date
09/26/2025 at 02:50 pm
Uploaded By
Eli Rochleau
Name
54AFDAC4-4C3A-4E3C-9…
Progress
Description
Taken Date
10/16/2025 at 03:04 pm
Upload Date
10/17/2025 at 08:30 am
Uploaded By
Eli Rochleau
Name
E836BD37-7247-4D7A-8…
Exterior Curtain Wall
Southeast Corner of
non-Natatorium
Exterior Curtain Wall
Framing Southeast
Corner of Natatorium
13
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 12 of 15
Progress
Description
Taken Date
09/25/2025 at 02:37 pm
Upload Date
09/25/2025 at 02:39 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_09_25_14_37…
Progress
Description
Taken Date
09/22/2025 at 10:54 am
Upload Date
09/29/2025 at 10:42 am
Uploaded By
Eli Rochleau
Name
4A9EE31F-C569-4CF5-B…
Exterior Main Entry
Bollards
Northwest Bioretention
Cell in progress
14
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 13 of 15
Progress
Description
Taken Date
10/09/2025 at 02:21 pm
Upload Date
10/10/2025 at 05:06 pm
Uploaded By
Eli Rochleau
Name
0DBAC9B7-887F-42B6-9…
Progress
Description
Taken Date
10/16/2025 at 03:09 pm
Upload Date
10/17/2025 at 08:40 am
Uploaded By
Eli Rochleau
Name
E984CAE3-B765-4D5A-A…
Northwest Bioretention
Cell Final Grading
Northwest Bioretention
Cell Plantings in progress
15
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 14 of 15
Progress
Description
Taken Date
10/09/2025 at 02:22 pm
Upload Date
10/09/2025 at 02:24 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_10_09_14_22…
Progress
Description
Taken Date
10/09/2025 at 02:26 pm
Upload Date
10/09/2025 at 02:26 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_10_09_14_26…
Landscape Plantings
North Parking Lot
Exterior Sign South
Elevation Template
16
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 15 of 15
Progress
Description
Taken Date
10/09/2025 at 02:24 pm
Upload Date
10/10/2025 at 05:07 pm
Uploaded By
Eli Rochleau
Name
AB00723B-7311-4AE4-9…
Progress
Description
Taken Date
10/10/2025 at 11:45 am
Upload Date
10/10/2025 at 05:06 pm
Uploaded By
Eli Rochleau
Name
BCCE6FB6-EA96-4DE0-A…
Exterior Sign South
Elevation Letters Ready
Exterior Sign South
Elevation Installed
17
Story Construction Co.
Printed on Tue Oct 21, 2025 at 09:44 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 15 of
Precast South Elevation
after Power Wash
16 18
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
All Star Concrete 2 Increase Concrete Thickness in Maintenance Area $ 7,029 $ 2,082,961
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,060,896
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,056,917
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,059,869
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,061,072
Core Construction 5 Channel Support $ 3,739 $ 2,057,333
Forrest & Associates 1 Channel Support $ 1,163 $ 2,056,170
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,014,041
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,011,183
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,008,162
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 2,004,167
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 2,002,528
Lansink Construction 6 Wood Blocking $ 752 $ 2,001,776
Lansink Construction 7 Waterproof Exterior - Aquatic Mechanical $ 1,167 $ 2,000,609
Lansink Construction 8 Converting Room 108 Shower to a Roll In Shower $ 2,653 $ 1,997,956
Lansink Construction 9 Donor Wall $ 33,224 $ 1,964,732
Lansink Construction 10 Additional Changing Room Tile $ 2,597 $ 1,962,135
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 1,960,488
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 1,955,372
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 1,959,195
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 1,957,452
Orning Glass Company 3 Auto Door Operators $ 9,757 $ 1,947,695
Hilsabek Schacht 1 Wet Room Door Change $ - $ 1,947,695
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 1,947,695
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 1,944,138
Hilsabek Schacht 4 Site Signage $ (350) $ 1,944,488
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,941,890
Hilsabek Schacht 6 Omit Painting - Mechanical Rooms $ (3,280) $ 1,945,170
Hilsabek Schacht 7 Close Off Top Of South Wellness Precast $ 3,808 $ 1,941,362
Hilsabek Schacht 8 Wellness Precast Vertical Joints & Frame Top of Masonry $ 3,656 $ 1,937,706
Hilsabek Schacht 9 Curtain Wall 12 & Metal Panels $ 599 $ 1,937,107
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,935,737
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,933,045
Sande Construction 3 Sump Pump Rail System and Backwash Pit Grate $ 4,744 $ 1,928,301
Midwest Fire Sprinkler 1 Omit Sprinkler Heads at Main Entry Exterior $ (700) $ 1,929,001
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,931,321
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,892,619
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,880,586
Brockway Mechanical 4 Pool Trench Drain Float Alarm $ 2,318 $ 1,878,268
Brockway Mechanical 5 Converting Room 108 Shower to a Roll In Shower $ 7,180 $ 1,871,088
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,849,135
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,834,898
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,830,219
Van Maanen Electric 4 Exterior Signage Lighting Controls $ 1,007 $ 1,829,212
Van Maanen Electric 5 Pool Trench Drain Float Alarm $ 1,356 $ 1,827,856
Van Maanen Electric 6 Wiring Auto Door Operators in Corridor 108 $ 959 $ 1,826,897
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,819,150
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,773,731
Con-Struct 3 Planting Revisions $ (737) $ 1,774,468
Con-Struct 4 Curb Strip Restoration $ 9,702 $ 1,764,766
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,750,248
Lakeside 1 Site Signage $ 2,120 $ 1,748,128
Lakeside 2 CyRide Concrete Pad $ 296 $ 1,747,832
Lakeside 3 Replace Curb & Gutter on Oak Avenue $ 27,130 $ 1,720,702
Totals / Current Balance $ 379,298 $ 1,720,702
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 10/28/25)
Highlighted Rows Indicate New Change Orders Since the Last Update
19