HomeMy WebLinkAboutA008 - October 28, 2025, Regular Meeting of the Ames City CouncilITEM #:11 DATE:10-28-25 DEPT:PW SUBJECT:2021/22 STORMWATER DETENTION/RETENTION MAINTENANCE PROGRAM - (NORTHRIDGE HEIGHTS POND) COUNCIL ACTION FORM BACKGROUND: This annual program provides for long-term maintenance of stormwater detention facilities within the City of Ames. These facilities provide regional stormwater detention and retention across the community. As a standard provision of developers' agreements, the City of Ames has responsibility for the long-term maintenance of many of these facilities in residential areas. As these facilities age, sediment accumulates, volunteer vegetation becomes more prevalent, erosion occurs, and structures need to be improved. The program location for this project is the Northridge Heights Pond. On April 9, 2024, City Council awarded the contract to Tallgrass Land Stewardship Co., of Waukee, Iowa in the amount of $111,600. To date, staff has administratively approved seven change orders totaling $13,415. Change Order No. 8 (this Council action) in the amount of $23,843.50 includes costs for the disposal of unsuitable materials, additional required drainage pipe, and tied concrete block matting for erosion control. This change order requires City Council approval because the change is over 20% of the original contract value. Additional project revenue is required to fund Change Order No 8. Staff has identified $50,000 in project savings in the available Stormwater Utility Fund that can be utilized to cover this expense. Revenue and expenses associated with this program are as follows: Funding Source Available Revenue Estimated Expenses 21/22 Stormwater Detention/Retention (Stormwater Utility Fund)$150,000.00 Stormwater Utility Fund $ 50,000.00 Construction (As Bid) $ 111,600.00 Change Orders (previously approved by staff) $ 13,415.00 Change Order 8 (this Council action) $ 23,843.50 Engineering/Administration (est.) $ 35,000.00 TOTAL $ 200,000.00 $ 183,858.50 1 ALTERNATIVES: 1. Approve Change Order No. 8 to Tallgrass Land Stewardship Co., of Waukee, Iowa, in the amount of $23,843.50 for the 2021/22 Stormwater Detention/Retention Maintenance Program - (Northridge Heights Pond). 2. Direct staff to pursue changes to the project. CITY MANAGER'S RECOMMENDED ACTION: This change order is necessary to address site conditions and provide necessary quantity adjustments to ensure proper project completion and compliance with design requirements. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as noted above. ATTACHMENT(S): Project Map.pdf CO 8, Unsigned, 2021-22 Stormwater Facility Rehab (Northridge Heights).pdf 2 G( D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D ) G(D) G(D) G(D) G(D) G(D) G(D) G(D) G(D) G(D) G(D) G(D) G(D) M M E T TVTM TVT T M CP #5001 ERIC & BETH VAUGHN 3332 FOXLEY DR CHUONG-TENG & LI-WEN TSENG 3326 FOXLEY DR KENNETH & MARIE MCCUSKEY 3320 FOXLEY DR MICHAEL & KRISTEN MYERS 3316 FOXLEY DR MARY & STEPHEN HOWELL 3308 FOXLEY DR JOHN & RUTH MACDONALD 3302 FOXLEY DR KENNETH TALBERT & KAREN BREITLING 3807 BRIDGEPORT DR JAMES & DIANNE JONES 3731 BRIDGEPORT DR JOHN & JOAN FITZSIMMONS 3725 BRIDGEPORT DR MATTHEW & RHONDA CARNEY 3719 BRIDGEPORT DR JON & TINA RICHARD 3713 BRIDGEPORT DR JOHN & BETH JOHNSON 3707 BRIDGEPORT DR JIANHUA YANG 3701 BRIDGEPORT DR StS( C ) StS( C ) EXISTING 54" APRON RCP FL: 924.36 (SE) EXISTING 54" APRON RCP FL: 923.42 (NW) CP #5002 EXISTING 48" APRON RCP FL: 920.67 (NE) EXISTING 48" APRON RCP FL: 921.59 (SW) EXISTING 18" APRON RCP FL: 921.98 (SW) EXISTING MH RIM: 930.42 BOTTOM: 911.36 StS(D) SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD CP #5000 EXISTING 48" APRON RCP FL: 923.52 (SE)StS ( D ) StS ( D ) StS ( D ) StS(C) StS(C) StS(C) EXISTING INTAKE 15" FL: 939.54 (NE) 15" FL: 939.44 (SW) EXISTING 15" APRON RCP FL: 928.84 (NE) St S ( C ) St S ( C ) St S ( C ) EXISTING 36" APRON RCP FL: 927.41 ACC PCC SHORT WIRE FENCE BRICK RETAINING WALL STEPS LANDSCAPE GRAVEL LANDSCAPE GRAVEL FL: 933.76 LANDSCAPE GRAVEL PCC EXISTING MH RIM: 931.85 StS(D) STORM SEWER (UNKNOWN) 6" SUBDRAIN 6" SUBDRAIN 48" RCP STORM SEWER 54" X 88" ARCH RCP STORM SEWER 15" RCP STORM SEWER 36" RCP STORM SEWER ADS STORM SEWER G( D ) G( D ) G( D ) G( D ) G( D ) G( D ) G( D ) G( D ) G( D ) G( D ) G(D ) G(D) G(D) G(D)G(D)G(D)G(D)G(D) E( D ) E( D ) E( D ) E( D ) E( D ) E( D ) E(D ) E(D ) E(D) E(D)E(D)E(D)E(D)E(D)E(D) G(D)G(D) G(D)G(D) G(D)G(D)G(D)G(D)G(D)G(D) G(D) G(D) G(D) E(D) E(D) E(D) E(D) E(D) E(D) E(D)E(D)E(D)E(D)E(D) E(D) E(D) E(D) E( D ) E( D ) E( D ) E( D ) E( D ) W(D ) W(D) W(D) W(D) W(D) W(D) W(D) W(D) W(D) W(D)W(D)W(D)W(D)W(D) W( D ) W( D ) W( D ) W( D ) W( D ) W( D ) W( D ) W( D ) W(D ) W(D ) W(D ) W(D) W(D) W(D) W(D)W(D)W(D)W(D)W(D)W(D) EXISTING MH RIM: 931.04 CP #5011 APPROXIMATE AREA OF OBSERVED SEEPAGE IN SLOPE 20.00' STORM SEWER & SURFACE FLOW EASEMENT 20 . 0 0 ' S T O R M S E W E R & SU R F A C E F L O W E A S E M E N T 30.00' P.U.E. PERMENENT POOL ELEVATION: 921.59 T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T T 12" P V C 12" PVC 12" P V C N 0 GRAPHIC SCALE 80'40'120' Clapsaddle-Garber Associates, Inc 1523 S. Bell Ave. Suite 101 Ames, Iowa 50010 Ph 515-232-1784 www.cgaconsultants.com SHEET NO. DRAWN: CHECKED: DATE: DATE: APPROVED:DATE: PROJECT NO.DESIGNED:DATE:REVISIONNO.DATEBY DATEBYREVISIONNO. J: \ 2 3 - W R - 0 0 7 3 \ d w g s \ 5 _ S h e e t s \ 2 3 W R 0 0 7 3 - C . 2 0 1 ( C o n s t r u c t i o n B o u n d a r y ) . d w g - C . 2 0 1 C O N S T R U C T I O N B O U N D A R Y - 0 1 - 2 5 - 2 4 - 1 1 : 2 1 a m - r w a 2 8 6 CGA NORTHRIDGE HEIGHTS STORM WATER FACILITY REHAB C.201 23-WR-0073 AMES, IOWA CONSTRUCTION BOUNDARY JMG JMG MMB TSM ---- ---- ---- ---- CONSTRUCTION NOTES: CONSTRUCTION ENTRANCE. TO BE RESTORED AFTER PROJECT COMPLETION. CONSTRUCTION LIMITS. A B B B B B B B B B B B A A A GENERAL NOTES: ALL AREAS WITHIN CONSTRUCTION LIMITS SHALL BE RESTORED TO ORIGINAL CONDITIONS OR BETTER. THIS PROJECT IS LOCATED IN A HOMEOWNERS ASSOCIATION COMMON PROPERTY. THE CONTRACTOR SHALL USE CAUTION TO NOT DISTURB INDIVIDUAL HOMEOWNERS PROPERTY OUTSIDE OF THE PROJECT LIMITS TO ENSURE THE SAFETY OF THE PUBLIC DURING CONSTRUCTION. CONSTRUCTION DETAILS STABILIZED CONSTRUCTION ENTRANCEC.501 3 C.501 3 5.00' 35.00' 3 Date 21-Oct-25 CONTRACT CHANGE ORDER # 8 P.O.#63112 ACCT#Various CONTRACTOR CHANGE ORDERS APPROVED TO DATE: 1 $3,700.00 11 PREVIOUS APPROVED 2 12 CHANGE ORDERS 3 $950.00 13 $13,415.00 ORIGINAL CONTRACT: 5 ($4,385.00)15 $111,600.00 CURRENT ADJUSTMENT 7 $9,100.00 17 $23,843.50 8 18 CUMULATIVE CHANGE 9 19 ORDER AMOUNT 10 20 $46,028.50 $22,185.00 ADJUSTED CONTRACT $148,858.50 The contract is hereby modified and amended as follows: ITEM DESCRIPTION UNIT PRICE QUANTITY TOTAL Add 7 2" River Stone Ton $130.00 25.60 $3,328.00 It is mutually agreed that the contract price is increased/decreased by:Total:$23,843.50 0 days. Contractor/Owner Date Municipal Engineer Date Public Works Director Date City Manager Date Page 1 of 1 For the City of Ames: (Address) Waukee, IA 50263 (City, State, Zip) 2021/22 Stormwater Facility Rehab (Northridge Heights) Tallgrass Land Stewardship Co. (Name) PO Box 938 PROJECT: CI TY OF AMES PUBLI C WORKS - ENGI NEERI NG DI VI SI ON CC: Project Engineer, PW Mgmt. Asst., Finance, Contractor 10/21/2025 | 9:21 AM 4