HomeMy WebLinkAboutA026 - Motion approving the Fitch Family Indoor Aquatic Center Monthly UpdateTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:August 26, 2025
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 27
MEMO
PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month.
Additionally, staff, along with representatives from Story Construction and RDG
Planning and Design, will provide an in-person update once per quarter (January,
April, July, & October). If anything occurs during the project that requires Council
action, staff will present this in a timely manner. Due to the number of agenda
items for City Council's July 22 meeting, the in-person report was deferred
to Council's August 26 meeting.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Report (Attachment A). Story
Construction and RDG Planning and Design are 97% complete with reviewing
shop drawings and submittals. This activity will continue until 100% complete.
It should be noted there have been no contaminated soils or groundwater found
to date.
CHANGE ORDER SUMMARY:
There were six change orders recently approved, and the changes thus far on
the project are shown on the change order log (Attachment B). Staff directed
contractors to implement the six change orders which are detailed below:
1) Waterproof the exterior of the aquatic mechanical room - $1,167.
2) Omit the painting of the mechanical rooms - ($3,280).
3) Close off the top of the south precast wall in the Wellness Pool area - $3,808.
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
4) The mechanical components to add a pool trench drain float alarm to the drain
pit - $2,318.
5) The electrical components to add a pool trench drain float alarm to the drain pit
- $1,356.
6) Increase the size of the concrete pad for a new CyRide Bus Stop Shelter -
$296.
To date, change orders for the project total $278,534, or 13.26% of the
contingency budget. The contingency for this project is $2.1 million with a current
balance of $1,821,466. There is also $1 million set aside for mitigation of
contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2025-8.pdf
Attachment B - Change Order Log - 8-26-25.pdf
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
August 2025
*Natatorium: Wellness, Recreation and Lap Pools
*Non-Natatorium: All supporting rooms outside of the Natatorium including Mechanical, Loading,
Locker Rooms, Offices, Main Lobby & Check-In, and the Alternate Walk Path
PROGRESS THIS PAST MONTH:
1. Lap Pool concrete reached substantial completion.
2. Interior framing for ceilings and in-wall blocking supports were nearly completed in the non-
Natatorium.
3. Ductwork, plumbing, sprinkler and electrical rough ins continued in the non-Natatorium with a
rough inspection date of end of August.
4. Electrical equipment, mechanical equipment and plumbing installations continued in the Aquatic
and Electrical Mechanical Rooms.
5. Curtain wall framing and glazing was nearly completed on the exterior of the non-Natatorium.
6. The Northeast storm water structures were installed and paving, along with light pole bases,
was completed.
7. Perimeter sidewalk demolition, prep and installation started.
8. Alliant Energy installed the gas meter set at the west building exterior.
9. Building Envelope Consult inspections continued for vapor barrier, pool water stop and curtain
wall glazing.
10. Special inspections and testing of concrete and sitework continued.
11. A Pre-Install Meeting was held for Landscaping with the City and Bid Package Contractors.
12. A Pre-Install Meeting was held for the CyRide bus stop with the City and Bid Package
Contractors.
13. Multiple design team members visited the project to perform field observations.
14. Submittals and Requests for Information continued to be processed between the Bid Package
Contractors, Story Construction, and RDG Planning & Design.
WORK PLANNED FOR NEXT MONTH:
1. Rec Pool excavation and concrete will start.
2. Mechanical and electrical rough inspections will be completed for the non-Natatorium.
3. Drywall will be completed in the west half of the non-Natatorium and drywall in the east half
will be in progress.
4. Interior painting will start in the west wing of the non-Natatorium.
Page 1 of 8 3
5. Mechanical, Plumbing and Electrical will continue in the Aquatic and Electrical Mechanical
Rooms.
6. Curtain wall framing and glazing will start in the Natatorium.
7. Exterior precast will be power washed.
8. Exterior signage will be in progress.
9. Perimeter sidewalk demolition, prep and installation will continue.
10. Alliant Energy will install the gas service piping to the meter set.
11. Building Envelope Consult inspections will continue for vapor barrier, pool water stop and
curtain wall glazing.
12. Special inspections and testing of concrete and sitework will continue.
13. Development of the Crew Workflow Plans for the pools, interior finishes and site improvements
will continue.
SCHEDULE SUMMARY:
Construction Substantial Completion Date: January 20, 2026
PROJECT PHOTOS: [Next page]
Page 2 of 8 4
Aerial Photos
Description
Taken Date
08/13/2025 at 03:26 pm
Upload Date
08/13/2025 at 03:29 pm
Uploaded By
Mitch Anderson
Name
7F3E3187-8D43-4B49-B…
Aerial Photos
Description
Taken Date
08/13/2025 at 03:24 pm
Upload Date
08/13/2025 at 03:29 pm
Uploaded By
Mitch Anderson
Name
73F54518-1CCC-4728-B…
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
PROJECT PHOTOS:
EXTERIOR VIEW TO
SOUTHWEST
EXTERIOR VIEW TO
NORTHWEST
Page 3 of 8 5
Aerial Photos
Description
Taken Date
08/13/2025 at 03:24 pm
Upload Date
08/13/2025 at 03:29 pm
Uploaded By
Mitch Anderson
Name
43CF851D-4B86-49B2-8…
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
07/25/2025 at 01:32 pm
Upload Date
07/25/2025 at 02:43 pm
Uploaded By
Eli Rochleau
Name
2CF9F61C-8D74-45CF-9…
Page 4 of 8
EXTERIOR VIEW TO
SOUTHEAST
LAP POOL DEEP
END CONCRETE
WALL FORMS
6
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
08/12/2025 at 01:37 pm
Upload Date
08/14/2025 at 05:42 pm
Uploaded By
Eli Rochleau
Name
86889056-0437-4668-8…
Progress
Description
Taken Date
08/19/2025 at 12:18 pm
Upload Date
08/19/2025 at 12:20 pm
Uploaded By
Deb Thurmond
Name
20250819_121804.jpg
Page 5 of 8
LAP POOL SHALLOW
END CONCRETE WALL
FORMS
WOMENS LOCKER
ROOM ROUGH INS AND
IN-WALL BLOCKING
7
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
08/19/2025 at 12:16 pm
Upload Date
08/19/2025 at 12:20 pm
Uploaded By
Deb Thurmond
Name
20250819_121632.jpg
Progress
Description
Taken Date
07/21/2025 at 03:56 pm
Upload Date
07/21/2025 at 03:52 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_07_21_15_56…
Page 6 of 8
AQUATIC-MECHANICAL
PIPING & EQUIPMENT
LOBBY SEATING
CURTAIN WALL
FRAMING IN PROGRESS
8
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
07/31/2025 at 01:54 pm
Upload Date
07/31/2025 at 01:51 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_07_31_13_54…
Progress
Description
Taken Date
07/31/2025 at 03:18 pm
Upload Date
07/31/2025 at 03:19 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_07_31_15_18…
Page 7 of 8
LOBBY SEATING
CURTAIN WALL
GLAZING
LOBBY SEATING
CURTAIN WALL
GLAZING
9
Story Construction Co.
Printed on Tue Aug 19, 2025 at 11:54 am CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
08/12/2025 at 12:05 pm
Upload Date
08/12/2025 at 12:02 pm
Uploaded By
Deb Thurmond
Name
IMG_2025_08_12_12_05…
Progress
Description
Taken Date
08/08/2025 at 09:21 am
Upload Date
08/08/2025 at 02:12 pm
Uploaded By
Eli Rochleau
Name
E47F5BB2-E29F-4116-A…
Page 8 of 8
GAS METER SET &
POST INDICATOR
VALVE FOR SPRINKLER
PERIMETER SIDEWALKS
IN PROGRESS
10
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
All Star Concrete 2 Increase Concrete Thickness in Maintenance Area $ 7,029 $ 2,082,961
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,060,896
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,056,917
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,059,869
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,061,072
Core Construction 5 Channel Support $ 3,739 $ 2,057,333
Forrest & Associates 1 Channel Support $ 1,163 $ 2,056,170
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,014,041
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,011,183
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,008,162
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 2,004,167
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 2,002,528
Lansink Construction 6 Wood Blocking $ 752 $ 2,001,776
Lansink Construction 7 Waterproof Exterior - Aquatic Mechanical $ 1,167 $ 2,000,609
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 1,998,962
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 1,993,846
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 1,997,669
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 1,995,926
Hilsabek Schacht 1 Wet Room Door Change $ - $ 1,995,926
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 1,995,926
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 1,992,369
Hilsabek Schacht 4 Site Signage $ (350) $ 1,992,719
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,990,121
Hilsabek Schacht 6 Omit Painting - Mechanical Rooms $ (3,280) $ 1,993,401
Hilsabek Schacht 7 Close Off Top Of South Wellness Precast $ 3,808 $ 1,989,593
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,988,223
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,985,531
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,987,851
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,949,149
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,937,116
Brockway Mechanical 4 Pool Trench Drain Float Alarm $ 2,318 $ 1,934,798
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,912,845
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,898,608
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,893,929
Van Maanen Electric 4 Conduit Change Due to Increasing Concrete Thickness in Maintenance
Area $ 1,007 $ 1,892,922
Van Maanen Electric 5 Pool Trench Drain Float Alarm $ 1,356 $ 1,891,566
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,883,819
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,838,400
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,823,882
Lakeside 1 Site Signage $ 2,120 $ 1,821,762
Lakeside 2 CyRide Concrete Pad $ 296 $ 1,821,466
Totals / Current Balance $ 278,534 $ 1,821,466
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 8/26/25)
Highlighted Rows Indicate New Change Orders Since the Last Update
11