HomeMy WebLinkAboutA034 - Finalize New Power Plant SiteITEM #:38
DATE:08-12-25
DEPT:ELEC
SUBJECT:PRESENTATION ON ALTERNATIVE SITES FOR
NEW GENERATION AND SELECTION OF SITE
COUNCIL ACTION FORM
BACKGROUND:
On July 22, 2025, staff presented the City Council with the results of a Request for Proposals
(RFP) for engineering services to develop new thermal electric generating units for the City's
Electric Utility. At that time, staff's expectation was that the site for the installation of these new
units would be the former Power Plant coal yard, on the south side of the railroad tracks
adjacent the existing Power Plant. However, during the discussion, the City Council asked
staff to perform a high-level review of potential alternative sites for the new electric
generation other than the coal yard site and report back at the August 12 City Council
meeting.
As staff discussed on July 22, the site will require certain infrastructure to be feasible, including
natural gas pipeline, electric transmission lines, a substation, and related electric distribution
infrastructure, including appropriate redundant capabilities. The City Council asked staff to
identify potential sites that would also be away from urban residential areas and the Main
Street area. Therefore, to evaluate potential alternative sites, staff used the following criteria to
prepare this presentation:
1. Proximity to large, high-pressure natural gas main
a. >= 10 inch line
b. >=120 psi
c. 11,000 dtherms when all running
2. Proximity to 161 kV transmission lines and/or multiple (3 or more) 69 kV lines
3. Proximity to electric distribution infrastructure
4. Distance from urban residential areas
5. Visibility from Main Street
The attached presentation will review different sites in and around Ames. It will also include
an initial budgetary estimate of potential infrastructure costs for each site based on information
from Ames Electric Engineering, Public Works and Alliant Energy.
Staff was unable to identify an alternative site that easily meets all of the evaluation
criteria. Each site would require significant investments to bring the required
infrastructure to the area, including disruption to the adjacent areas along the utility
paths.
Staff's estimates are that pursuing any alternative site will increase the cost of the
1
generation project by a minimum of 25%. Additionally, any alternative site will cause
delays in land acquisition, infrastructure design and construction, power plant
engineering, design and construction.
Council also requested additional information regarding noise and vibration from the
proposed new generating units. Information will be added to the presentation on
Monday and covered Tuesday night, as this information was not completed in time to
publish the Council agenda.
If the Council elects not to proceed with the project proposed at the former coal yard, a
preferred alternative site would need to be identified. Then, staff would negotiate with Sargent
& Lundy to amend the design contract (approval of which is a separate item on this Council
agenda) to evaluate the proposed site in detail and determine more specifically what
infrastructure is needed. Following that process, the original scope of Sargent & Lundy's work
(design of the facility itself) could begin. Staff estimates this approach would delay the project
by a minimum of six months. It is important to note that in addition to the increased cost of the
engineering work to design transmission and substation infrastructure, there will be additional
implications if the project is delayed:
If the project is not completed by June 2028 and Ames misses the MISO summer
season capacity requirements, this could result in a $2.3 million charge for capacity.
Materials costs for such things as transformers, breakers and the generating units, and
labor continue to rise (separate from the costs of the additional equipment necessary).
This by itself could cause increases of 3-5% to the cost of the project.
As more and more utilities look to add capacity, material delays can continue to grow. A
six-month delay in the engineering and design could add a year to the procurement
schedule for materials.
ALTERNATIVES:
1. Approve the Ames Power Plant Coal Yard site as the preferred location for new generation.
2. Identify an alternative site for the construction of the new power plant generation and:
a. Authorize staff to negotiate a scope of services with Sargent & Lundy to begin a detailed
site selection process based on the new site. Staff would return to City Council with a
contract change and costs related to this work.
b. Direct staff to develop a Request for Proposal for engineering services to design new
substation and transmission infrastructure.
CITY MANAGER'S RECOMMENDED ACTION:
The last time Electric Services expanded its baseload generation capacity was in the 1980s.
Customer demands have grown, and generation infrastructure has aged since then. Staff has
extensively studied the needs, the life assessment of the existing generation, the power
production technologies available, and the financial requirements to afford the additions. It is
time to add new generation resources to meet utility requirements.
2
Finalizing the site will allow the engineer to design specifically for that site. This will eliminate
delays that have the potential to result in compounding cost increases, make bidding more
straightforward, and limit the amount of potential change orders from the engineering firm.
Although the Coal Yard site is in proximity to the Downtown area, it is important to note
that even if the new generating units are sited in an alternative location, the existing
Power Plant will remain at the end of Main Street for at least 15 more years, plus the
length of time necessary to deconstruct and demolish the significant amount of
infrastructure located within it.
The new generating units are expected to require an enclosure building, chimneys, and
other accessory equipment that is far lesser in height than the equipment in place at
the Power Plant, and this equipment is planned to be located on the furthest portion of
the site away from Main Street (roughly 1/4 mile from the east end of Main Street and
further south, compared to the existing Power Plant which is only 350 feet due east
from Main Street). Additionally, staff can work with the design team to develop a facility
exterior that is more visually appealing than a typical industrial building, for a far lower
cost than the expense of relocating the facility entirely. Therefore, it is the
recommendation of the City Manager that the City Council adopt Alternative No.1 as stated
above.
ATTACHMENT(S):
Gen Siting Aug 12.pptx
3
City of
Ames
Electric
New Thermal Generation
Siting Alternatives
1
4
2
Tonight’s Agenda
•Siting the new generation units
•Siting Criteria
•Alternatives
•Primary Site
•Attributes
•Visibility
•Supported & Recommended by EUORAB
5
Siting Criteria
1.Proximity to natural gas
1. >= 10 in line
2. >=120 psi
3. 11,000 dtherms when all running
2.Proximity to 161 kV transmission line and/or multiple
3+ 69 kV lines
3.Proximity to Distribution
4.Distance from urban residential areas
5.Visibility from Main street
3
6
Possib
le
Sites
4
7
Northwest Ames Property -
$27.5 million extra cost
-Need 161kV / 69kV sub - $10 million
-161/69kV transformer - $3 million
- 2.5 miles 69kV line in and out - $2.5 million
-Gas line- $ 1.5 million
-Gas Interconnection? $1.5 million (connecting to
NNG line)
-Water and Sanitary- $3 million
-Purchase Land- 70 acres - $6 million
__________________________________________
- Inhibits development opportunities
- Major gas line in the area full
5
8
SE 5th Street and Dayton Property- $24 million
extra cost
-Need 161kV / 69kV sub - $10 million
-Transformer to 161/69kV transformer- $3 million
- 2.5 miles 69kV line in and out - $2.5 million
-Gas line and interconnection- $ 1.5 million
-Water - $0.5 million
-Purchase Land and demolition - $7 million
_____________________________________________________
-Need to purchase 4 different lots to accomplish land size needed
- Dayton already congested with transmission
South of PVIC Substation Property - $18.5 million
extra cost
-Need 161kV / 69kV sub - $10 million
-Transformer to 161/69kV transformer- $3 million
- 2.5 miles 69kV line in and out - $2.5 million
-Gas line and interconnection- $ 1.5 million
-Water - $0.5 million
-Purchase Land - $1 million
_____________________________________________________
- fairly far from city center
- electric service questions
6
9
Northeast of Target Property - $19 million
extra cost
-Need 161kV / 69kV sub - $10 million
-Gas line and interconnection- $ 1 million
-Water and Sanitary- $1 million
-Purchase Land – would need to buy 25 acres - $2
million
-Land Preparation (in flood plain) – needs to be 3ft
above flood line – roughly 6 feet raise. 10 acres =
135,000 cubic yards of dirt + prep for solid base +
build access road = $5 million
______________________________________
- This site is very close to current housing
- Flood way
7
10
Coal Yard - $0 million extra cost
-161kV / 69kV sub –Ames Plant substation
-Gas line and interconnection -On site
-Water and Sanitary-On site
-Purchase Land –already own
-Land Preparation –existing CIP for building
removal
______________________________________
- Prepping site for generation different than
prepping site for sale
- Visibility from Main street
8
11
12
13
14
12
15
Sound
Vibration
Other Issues
13
16
14
New Generation Siting
Coal Yard considerations
•Save roughly $18+ to $27
million because of
existing infrastructure
•Performing sound study
to accomplish current
conditions
•Providing design for
public tours and
interaction
•Building and site design
McIntosh Reciprocal Engine Plant, Lakeland Electric
17
Question
s
15
18