HomeMy WebLinkAboutA032 - Shared Use Path System Expansion Program UpdateITEM #:34
DEPT:PW
July 22, 2025
Staff Report
SHARED USE PATH SYSTEM EXPANSION PROGRAM UPDATE
BACKGROUND:
At its July 9, 2024 meeting, City Council directed staff to provide an update on the proposed
connection of the Ioway Creek Trail. This trail is located on the north bank of Ioway Creek and
currently terminates at a privately-owned well access road approximately one half-mile east of
South Duff Avenue. The Ioway Creek Trail was constructed so that it could be extended
further east when property rights were acquired.
While preliminary plans were developed as far back as 2010 to construct a trail
alignment along the west side of the Skunk River between E. 13th Street and the
Hunziker Youth Sports Complex, the project was not fully completed due to the City’s
inability to secure voluntary easements from all property owners. Ultimately, the
segment between E. Lincoln Way & SE 16th Street was removed and the Skunk River
Trail was constructed, leaving a gap in the trail network.
Following a staff transition in 2024, staff reengaged with the property owner to again attempt to
secure property rights to close this gap in the network. Working with WHKS & Co., staff
prepared updated exhibits that illustrated both the proposed trail easement and the extent of
recent Skunk River bank erosion. To create a mutually beneficial project, staff proposed
combining the trail project with riverbank stabilization work that would directly benefit
the property owner.
The proposed river alignment map (attached) shows the details regarding this
proposed work. This trail alignment is beneficial because the City intends to utilize the
pedestrian bridge that was salvaged and has been stored since the construction of the
Grand Avenue extension over Ioway Creek.
In December 2024, WHKS staked the proposed easement limits, and staff conducted an on-
site meeting with the property owner. Initial feedback was generally positive; however, no
further progress was made in the following months as the property owner expressed
reluctance to grant an easement or to sell the affected property.
Staff has suggested to the property owner that an agreement, either in the form of an
easement or acquisition of the necessary property to construct the trail, was an option to
continue with the project. As progress has stalled, staff has indicated to the property
owner that the City's interest in armoring the banks of the Skunk River to minimize
future bank erosion would be less of a priority if there is not a river trail alignment to
protect in the area.
Throughout discussions, the property owner emphasized that no distinction was made
between farmable and non-farmable land when the family originally purchased the property.
1
Accordingly, the owner believes that any land within the river corridor should be compensated
at the same value as cropland.
Staff consulted the Farmland Value Survey from the REALTORS Land Institute and Iowa
State University Extension and Outreach, which shows that timber ground is valued at roughly
25% of high-quality cropland. No specific data exists for riverbank ground, but staff believes it
would be similar to or less than timber value.
Staff has offered to obtain an appraisal of the necessary land acquisition; however, the
property owner has continued to indicate that there is not an interest in selling
regardless of valuation. It is important to note that if the property owner is unwilling to
voluntarily grant rights for the trail to the City, Iowa Code does not allow for the use of
eminent domain on agricultural land for the construction of a recreational trail.
Given the limited progress on the west side river alignment, staff is seeking Council
direction as to whether to continue pursuing the Skunk River alignment or to shift
focus to a potential alternate connection west of the river, near the City-owned well
access road.
Considerations for Alternate Alignments
If the Skunk River alignment is not feasible, an alternate route adjacent to the well access road
could be pursued. However, this option presents several challenges:
The existing easement does not currently allow for shared use path access.
Additional coordination with adjacent landowners would be necessary.
The corridor is narrow and used for both farm and utility access, so widening or
separation would be needed to accommodate trail users safely.
A new pedestrian bridge would likely be required over Ioway Creek, as the existing
bridge location is tied to the Skunk River alignment. This would also require a temporary
easement during construction to perform Ioway Creek modifications.
Staff has prepared and attached a concept map outlining these alignment
considerations.
Future Trail Network Context
This part of Ames lacks continuous trail connectivity; however, the planned South Dayton
Shared Use Path Project, estimated for construction in 2026/27, will complete a significant
loop between E. Lincoln Way and SE 16th Street in the southeast quadrant. This connection
may reduce the urgency for the Skunk River alignment and allow time for future opportunities
to emerge (e.g., renewed interest from the current landowner, changes in property ownership,
or area redevelopment).
In parallel to Skunk River Trail efforts, staff is also working on a pedestrian bridge and trail
connection over Ioway Creek at S. 4th Street. Recent cost estimates have escalated beyond
the original $760,000 budget. A single-span prefabricated bridge is now estimated at
2
$860,000, with total project costs expected to reach $1,500,000.
Local Option Sales Tax funds allocated to the Skunk River Trail have been identified as a
potential source to cover the funding gap for this important 2026 construction project. The
potential for realignment or delay in the Skunk River trail corridor would open an
opportunity to continue with additional trail and pedestrian projects, including the
Ioway Creek at S. 4th Street project, that do not currently have impediments due to
acquiring property rights.
Additionally, the salvaged pedestrian bridge from the Grand Avenue extension that was
planned for the river crossing on the Skunk River alignment could be utilized for
another project. This project would be the crossing of Ioway Creek, north of the Applied
Sciences Complex, west of Moore Memorial Park. Further evaluation would need to be
completed to ensure this is feasible. However the span appears to be long enough to
accomplish the crossing at this new location. This may help accelerate this trail
connection as well.
OPTIONS:
Option 1:
Continue pursuing the west side Skunk River alignment, including a crossing of Ioway Creek
using the City's existing pedestrian bridge. This would require securing either an easement or
fee title acquisition from the current property owner. This is the option that has been sought
since 2010 without meaningful progress towards obtaining an agreement. There is not an
estimate as to a timeframe, if at all, when an agreement may be finalized for the trail
connection.
Option 2:
Redirect efforts to the well access road alignment, which would involve coordination with
multiple property owners, a modification of existing easements, potential purchase of
additional adjacent property, and the purchase of a new pedestrian bridge due to the
realignment of the crossing over Ioway Creek.
If Council selects this option, staff recommends also reallocating Skunk River Trail Local
Option Sales Tax funds to fully fund the S. 4th Street pedestrian bridge project, ensuring its
continued progress toward 2026 construction.
The Skunk River Trail connection remains programmed in the fifth year of the Capital
Improvements Plan and can be reprioritized based on future property rights. Additionally, the
salvaged bridge could be relocated to the Moore Memorial Park crossing.
Option 3:
Pause efforts to establish a trail connection in this area, allowing time for the South Dayton
project to be completed. Staff would continue monitoring the situation for future opportunities
(e.g., landowner interest or area redevelopment). The South Dayton Avenue connection
between E. Lincoln Way and SE 16th Street in 2026/27 could serve as the network connection
in the area.
If Council selects this option, staff recommends also reallocating Skunk River Trail Local
Option Sales Tax funds to fully fund the S. 4th Street pedestrian bridge project, ensuring its
3
continued progress toward 2026 construction. The Skunk River Trail connection remains
programmed in the fifth year of the Capital Improvements Plan and can be reprioritized based
on future property rights. Additionally, the salvaged bridge could be relocated to the Moore
Memorial Park crossing.
STAFF COMMENTS:
Staff believes all reasonable efforts have been made to establish a west side river
alignment and that the direction forward is unlikely to change without a shift in
ownership or interest. Accordingly, Option 2 offers the most viable route to achieving
connectivity of the Ioway Creek Trail. Furthermore, Option 2 would allow for the continued
development of other trail projects such as the S. 4th Street crossing, and Ioway Creek
crossing near Moore Memorial Park, which are facing funding challenges due to inflationary
pressures of raw materials for bridge construction.
Given the potential challenges with the well access road alignment, staff may initially focus on
the Ioway Creek to SE 16th Street connection, pending the outcome of preliminary
conversations with affected property owners.
Option 2 would not preclude the City from obtaining a trail alignment along the Skunk
River corridor in the future if the opportunity arose.
ATTACHMENT(S):
Proposed River Alignment Map.pdf
Well Access Road Alignment Notes.pdf
Referenced Locations Map.pdf
4
0
HORIZ.
250250 500
E LINCOLN WAYE LINCOLN WAY
SE 5TH ST
FR
E
E
L
D
R
S DA
Y
T
O
N
A
V
E
SE 5TH ST
SE 3RD ST
IOWAY CRE
E
K
30" RAW WATER MAIN
RIPRAP/BROKEN CONCRETE
PLACED IN ~2016 TO PROTECT
EXISTING 30" RAW WATER MAIN
2030
LEGEND
PROPERTY LINE
2030 PROJECTED
RIVER BANKS
RIVER BANKS 2023
PROJECTED LOCATION
CONNECT TO
EXISTING TRAIL
CONNECT TO
EXISTING TRAIL
CONNECT TO
EXISTING TRAIL
PROPOSED PEDESTRIAN
BRIDGE ACROSS IOWAY CREEK
3:1 STREAM BANK
STABILIZATION GRADING
3:1 BANK STABILIZATION
GRADING
3:1 STREAM BANK
STABILIZATION GRADING
PROPOSED TRAIL (TYP.)
PLACE RIPRAP STREAM
BANK STABILIZATION
TO PROTECT EXISTING
RAW WATER MAIN
TEMPORARY
ACCESS
EASEMENT
PROPOSED TRAIL
EASEMENT (TYP.)
APPROXIMATE EASEMENT
SUMMARY (WEST OF RIVER)
FARM LAND - 9 ACRES
FORESTED AREA - 17 ACRES
STREAM - 6 ACRES
BANK GRADING
PROPOSED PERMANENT
EASEMENT
PROPOSED GREEN
SPACE (2 ACRES)
FARMLAND SUMMARY
SECTION 12 NW 1
4 NW 1
4
FARM LAND FOR EASEMENT:
1.12 ACRES
FARM LAND REMAINING:
26.16 ACRES
FARMLAND SUMMARY
SECTION 12 SW 1
4 NW 1
4
FARM LAND FOR EASEMENT:
2.43 ACRES
FARM LAND REMAINING:
28.62 ACRES
FARMLAND SUMMARY
SECTION 12 NW 1
4 WW 1
4
FARM LAND FOR EASEMENT:
5.03 ACRES
FARM LAND REMAINING:
17.68 ACRES
EXISTING 20' PERMANENT
EASEMENT CENTERED ON
RAW WATER MAIN
PERMANENT EASEMENT
FOR RAW WATERMAIN
AND REVETMENT ACCESS
PROPOSED TEMPORARY
EASEMENT
APPROXIMATE EASEMENT SUMMARY
(EAST OF RIVER)
FARM LAND - 3 ACRES
FORESTED AREA - 7 ACRES
STREAM - 5 ACRES
TEMP ACCESS EASEMENT -3 ACRES
NOTE: FARM LAND WILL REMAIN TILLABLE
5
6
7