HomeMy WebLinkAboutA018 - Resolution approving Change Order No. 4 to 2022/23 Airport Improvements Program (South Apron Rehab), the balancing change order, a deduction in the amount of $35,531.35ITEM #:19
DATE:07-08-25
DEPT:PW
SUBJECT:2022/23 AIRPORT IMPROVEMENTS PROGRAM (SOUTH APRON REHAB)
COUNCIL ACTION FORM
BACKGROUND:
The Airport Improvements Program in the Capital Improvement Plan (CIP) provides for
projects that are included in the Federal Aviation Administration (FAA) approved Airport
Master Plan. Rehabilitation of the South Apron was included in the FY 2022/23 Airport
Improvements CIP Program.
On April 25, 2023, City Council awarded a contract to Con-Struct, Inc. for the work in the
amount of $1,251,705.
Change Order No. 1 required no additional funding, however it added requirements for
Targeted Small Business (TSB) participation. Change Order No. 2, in the amount of
$13,888.60, was administratively approved by staff and addressed gate and fencing revisions
required during construction operations. Change Order No. 3, in the amount of $21,866, was
also administratively approved by staff to cover changes to the work to further address airport
operational needs.
Change Order No. 4 (This Action), is the balancing change order for the project, a deduction
in the amount of ($35,531.35). This change order reflects final field installed quantities.
Because the sum of the absolute values of all of the project change orders exceeds $50,000,
approval by City Council is required.
The table below shows project revenue and expenses:
Revenues Amount Expenses Amount
Federal $1,181,000.00 Design $77,000.00
State $129,600.00 Inspection $107,700.00
Airport Improvements
Fund (Est.)$154,328.25 Inspection – CO #1 $28,300.00
Construction (Original
Contract)$1,251,705.00
Construction – CO#1
(TSB Requirements)$0.00
1
Construction – CO#2
(Fencing & Gate
Changes)
$13,888.60
Construction – CO#3
(Additional Work)$21,866.00
Construction – CO#4
(Final Quantity
Reconciliation)
($35,531.35)
Total $1,464,928.25 Total $1,464,928.25
Revenues Amount Expenses Amount
ALTERNATIVES:
1. Approve Change Order #4, a reduction in the amount of ($35,531.35).
2. Direct Staff to make modifications to the project.
CITY MANAGER'S RECOMMENDED ACTION:
Change Order No. 4 represents the final reconciliation of actual field quantities and
must be completed prior to the engineer ’s final statement of completion in accordance
with FAA and State grant requirements. Therefore, it is the recommendation of the City
Manager that the City Council adopt Alternative No. 1, as noted above.
ATTACHMENT(S):
128665-Change Order 4 - Final (Quanity Reconciliation)-Signed SH JR.pdf
2
06/24/2025
3
4
Previous Bid /
C. O. Quantity Unit Unit Price
Previous Bid /
Chg. Order Cost
Final
Quantity Final Cost
Quantity
Change Cost Change
BASE BID
Div 1 - Item 1 .500 LF $5.60 $2,800.00 401.00 $2,245.60 (99.00)$(554.40)
Div 1 - Item 2 .500 LF $1.50 $750.00 401.00 $601.50 (99.00)$(148.50)
Div 2 - Item 3 .500 LF $0.15 $75.00 0.00 $- (500.00)$(75.00)
Div 1 - Item 4 .1 LS $2,050.00 $2,050.00 1.00 $2,050.00 0.00 $-
Div 1 - Item 5 .1 LS $95,000.00 $95,000.00 1.00 $95,000.00 0.00 $-
Div 1 - Item 6 .1 LS $20,000.00 $20,000.00 1.00 $20,000.00 0.00 $-
Div 1 - Item 7 .1 LS $11,850.00 $11,850.00 1.00 $11,850.00 0.00 $-
Div 1 - Item 8 .40 SY $35.00 $1,400.00 54.60 $1,911.00 14.60 $511.00
Div 1 - Item 9 .5800 SY $10.00 $58,000.00 5,673.00 $56,730.00 (127.00)$(1,270.00)
Div 1 - Item 10 .1350 CY $20.00 $27,000.00 1,350.00 $27,000.00 0.00 $-
Div 1 - Item 12 .200 CY $50.00 $10,000.00 0.00 $- (200.00)$(10,000.00)
Div 1 - Item 13 .5600 SY $8.00 $44,800.00 5,521.00 $44,168.00 (79.00)$(632.00)
Div 1 - Item 14 .260 TON $260.00 $67,600.00 215.91 $56,136.60 (44.09)$(11,463.40)
Div 1 - Item 15 .5650 SY $10.50 $59,325.00 5,574.70 $58,534.35 (75.30)$(790.65)
Div 1 - Item 18 .5550 SY $95.00 $527,250.00 5,470.60 $519,707.00 (79.40)$(7,543.00)
Div 1 - Item 20 .120 SF $38.00 $4,560.00 120.00 $4,560.00 0.00 $-
Div 1 - Item 23 .1100 LF $45.00 $49,500.00 992.30 $44,653.50 (107.70)$(4,846.50)
Div 1 - Item 24 .7 EA $4,100.00 $28,700.00 9.00 $36,900.00 2.00 $8,200.00
Div 1 - Item 25 .1 LS $14,000.00 $14,000.00 1.00 $14,000.00 0.00 $-
Div 1 - Item 26 .300 LF $11.00 $3,300.00 276.00 $3,036.00 (24.00)$(264.00)
Div 1 - Item 29 .300 LF $12.30 $3,690.00 247.00 $3,038.10 (53.00)$(651.90)
Div 1 - Item 30 .2 EA $2,465.00 $4,930.00 2.00 $4,930.00 0.00 $-
Div 1 - Item 31 .1 EA $10,670.00 $10,670.00 1.00 $10,670.00 0.00 $-
Div 1 - Item 32 .1 LS $18,050.00 $18,050.00 1.00 $18,050.00 0.00 $-
Div 2 - Item 10 .50 CY $20.00 $1,000.00 50.00 $1,000.00 0.00 $-
Div 2 - Item 11 .400 SY $3.50 $1,400.00 352.20 $1,232.70 (47.80)$(167.30)
Div 2 - Item 16 .300 SY $18.50 $5,550.00 264.00 $4,884.00 (36.00)$(666.00)
Div 2 - Item 17 .250 SY $85.00 $21,250.00 222.00 $18,870.00 (28.00)$(2,380.00)
Div 2 - Item 19 .125 SY $65.00 $8,125.00 109.00 $7,085.00 (16.00)$(1,040.00)
Div 2 - Item 21 .25 LF $21.00 $525.00 25.00 $525.00 0.00 $-
Div 2 - Item 22 .1 LS $23,750.00 $23,750.00 1.00 $23,750.00 0.00 $-
Div 2 - Item 27 .700 LF $5.75 $4,025.00 700.00 $4,025.00 0.00 $-
Div 2 - Item 28 .400 LF $5.75 $2,300.00 400.00 $2,300.00 0.00 $-
Div 2 - Item 29 .100 LF $31.50 $3,150.00 77.00 $2,425.50 (23.00)$(724.50)
TOTAL - BASE BID $1,136,375.00 $1,101,868.85 $(34,506.15)
TOTAL - DIVISION 1 $1,065,300.00 $1,035,771.65 $(29,528.35)
TOTAL - DIVISION 2 $71,075.00 $66,097.20 $(4,977.80)
NO. 6 AWG, 600V, THWN-2, INSTALLED IN TRENCH, DUCT BANK OR CONDUIT
NO. 6 AWG, 600V EQUIPMENT GROUND, THWN-2, INSTALLED IN TRENCH, DUCT
BANK OR CONDUIT
SUBGRADE PREPARATION, 12"
MODIFIED SUBBASE, 8"
PAVEMENT, PCC, 8"
PAVEMENT, PCC, 4", SIDEWALK
FENCE REMOVAL, CHAIN LINK
GATE, AUTOMATIC POWERED 25' ALUMINUM CANTILEVER, 4' TALL, BLACK PVC
COATED
NON-ENCASED 2" PVC/HDPE CONDUIT
NO. 8 AWG 5KV, L-824, TYPE C CABLE, INSTALLED IN TRENCH, DUCT BANK OR
CONDUIT
PAVEMENT MARKING REMOVALS
SUBDRAIN CLEANOUT
6" SUBDRAIN
SEEDING FERTILIZING AND MULCHING
NON-ENCASED 2" PVC/HDPE CONDUIT
L-861 T (L) MITL, BASE MOUNTED TAXIWAY EDGE LIGHT (REMOVE AND REINSTALL
ON NEW BASE)
L-858 (L) GUIDANCE SIGN, SIZE 1, DOUBLE FACE, 2 MODULE
DEMOLITION AND REMOVAL OF PARTIAL EXISTING EDGE LIGHTING SYSTEM
UNCLASSIFIED EXCAVATION
Change Order No.
FAA AIP:030-2023, 031-2023 & 032-2024
IDOT Project No.9I240AMW100
ENGINEER'S PROJECT NO.:0T5.128665
CEMENT TREATED SUBGRADE, 12"
Reconciliation of Final Quantities
Ames Municipal Airport - South Apron Reconstruction
REMOVE AND REPLACE UNSUITABLE MATERIAL
DescriptionItem No.
PAVEMENT, PCC, 9.5"
RECYCLED CONCRETE AGGREGATE BASE COURSE, 6"
CEMENT, 8%
SWPPP ESTABLISHMENT AND MANAGEMENT
UNCLASSIFIED EXCAVATION
PAVEMENT REMOVAL, HMA PAVEMENT
REMOVAL OF FILTER SOCKS
FILTER SOCK CLEANOUT
CONSTRUCTION SURVEY
TRAFFIC CONTROL
MOBILIZATION
INSTALLATION OF FILTER SOCKS
PAVEMENT REMOVAL, PCC PAVEMENT
128665-Change Order 4 - Final (Quanity Reconciliation).xlsxCO #4 Reconciliation Page 1 of 2
4
BID ALTERNATE "A"
Div 1 - Item A1 .1600 LF $5.75 $9,200.00 1,600.00 $9,200.00 0.00 $-
Div 1 - Item A2 .800 LF $5.75 $4,600.00 800.00 $4,600.00 0.00 $-
Div 1 - Item A3 .500 LF $10.00 $5,000.00 472.00 $4,720.00 (28.00)$(280.00)
Div 1 - Item A4 .5 EA $17,000.00 $85,000.00 5.00 $85,000.00 0.00 $-
TOTAL - BID ALTERNATE "A"$103,800.00 $103,520.00 $(280.00)
TOTAL - DIVISION 1 $103,800.00 $103,520.00 $(280.00)
TOTAL - DIVISION 2 $- $- $-
- -
BID ALTERNATE "B"
Div 2 - Item B1 .140 SY $3.50 $490.00 131.50 $460.25 (8.50)$(29.75)
Div 2 - Item B2 .140 SY $18.50 $2,590.00 131.50 $2,432.75 (8.50)$(157.25)
Div 2 - Item B3 .130 SY $65.00 $8,450.00 125.00 $8,125.00 (5.00)$(325.00)
TOTAL - BID ALTERNATE "B"$11,530.00 $11,018.00 $(512.00)
TOTAL - DIVISION 1 $- $- $-
TOTAL - DIVISION 2 $11,530.00 $11,018.00 $(512.00)
CHANGE ORDER NO. 2
CO2-1 .1 LS $9,521.60 $9,521.60 1.00 $9,521.60 0.00 $-
CO2-2 1 LS $4,367.00 $4,367.00 1.00 $4,367.00 0.00 $-
TOTAL - CHANGE ORDER NO. 2 $13,888.60 $13,888.60 $-
TOTAL - DIVISION 1 $- $- $-
TOTAL - DIVISION 2 $13,888.60 $13,888.60 $-
CHANGE ORDER NO. 3
CO3-1 .1 LS $$4,500.00 $4,500.00 1.00 $4,500.00 0.00 $-
CO3-2 1 LS $5,706.00 5,706.00 1.00 5,706.00 0.00 -
CO3-3 100 SY $4.00 400.00 98.00 392.00 (2.00)(8.00)
CO3-4 100 SY $$19.60 $1,960.00 98.00 $1,920.80 (2.00)$(39.20)
CO3-5 100 SY $$93.00 $9,300.00 98.00 $9,114.00 (2.00)$(186.00)
TOTAL - CHANGE ORDER NO. 2 $21,866.00 $21,632.80 $(233.20)
TOTAL - DIVISION 1 $- $- $-
TOTAL - DIVISION 2 $21,866.00 $21,632.80 $(233.20)
CHANGE ORDER NO. 4 (FINAL)
CO4-1 .N/A $(35,531.35)
TOTAL - CHANGE ORDER NO. 4 (FINAL)$- $- $(35,531.35)
TOTAL - DIVISION 1 $1,169,100.00 $1,139,291.65 $(29,808.35)
TOTAL - DIVISION 2 $118,359.60 $112,636.60 $(5,723.00)
Reconciled Cost Total for Base Bid, Awarded Bid Alternates, and Approved Change Orders $1,287,459.60 $1,251,928.25 $(35,531.35)
N/A
SUBGRADE PREPARATION, 12"
MODIFIED SUBBASE, 8"
PAVEMENT, PCC, 6"
OVERHEAD AREA LIGHTING POLE WITH FIXTURES
ADDITIONAL MOBILIZATION
MODIFIED SUBBASE, 6"
UNCLASSIFIED EXCAVATION (INCLUDING TOPSOIL STRIP, SALVAGE, AND RESPREAD)
NO. 6 AWG, 600V EQUIPMENT GROUND, THWN-2, INSTALLED IN TRENCH, DUCT
BANK OR CONDUIT
SUBGRADE PREPARATION, 12"
INCREASE HEIGHT OF 25' AUTOMATIC POWERED CHAIN LINK CANTILEVER GATE TO
8' TALL, REMOVE EXISTING 4' CHAIN LINK FENCE AND REPLACE WITH 8' TALL BLACK
PVC COATED CHAIN LINK FENCING
NO. 6 AWG, 600V, THWN-2, INSTALLED IN TRENCH, DUCT BANK OR CONDUIT
NON-ENCASED 2" PVC/HDPE CONDUIT
Note:(1) Parentheses indicate negative change in quantity and cost.
Reconciliation of Final Quantities
Costs Associated with this Item shown in lower right as sum of "Cost Change" column, so not duplicated in columns on this line marked "N/A"
Total of "Cost Change" column
PAVEMENT, PCC, 8"
ADD 6' WIDE 8' TALL, BALCK PVC COATED, CHAIN LINK PEDESTRIAN GATE WITH
GATE CLOSURE AND MECHANICAL KEYLESS LEVER LOCK SET, OUTDOOR RATED
128665-Change Order 4 - Final (Quanity Reconciliation).xlsxCO #4 Reconciliation Page 2 of 2
5