Loading...
HomeMy WebLinkAboutA017 - Resolution approving Change Order No. 4 with Keller Excavating, Inc. of Boone, IA, for the North River Valley Well Field and Pipeline Project, in the amount of $47,336ITEM #:18 DATE:07-08-25 DEPT:W&PC SUBJECT:NORTH RIVER VALLEY WELL FIELD AND PIPELINE PROJECT CHANGE ORDER #4 COUNCIL ACTION FORM BACKGROUND: On April 11, 2023, Council awarded a contract to Keller Excavating, Inc. in the amount of $10,200,955.80 for construction of a new well field. During the progress of the contract, three change orders have been processed. A fourth change order is ready for Council authorization. This fourth change is for the placement of 194 square yards of additional asphalt requested by Parks and Recreation to widen the access drive and shared use path in South River Valley Park, and the access drive in North River Valley Park, for a total of $47,336. The cost of the change order will be deducted from the available project contingency. The updated project budget, including Change Order #4, is as follows. Funding Sources Project Expenses Drinking Water State Revolving Loan 12,161,000 Test Drilling 124,005 Engineering, Admin, Legal 725,272 Land 111,038 Construction Original Contract 10,200,956 Change Order #1 30,125 Change Order #2 228,565 Change Order #3 (17,305) Change Order #4 (This action) 47,336 Geotechnical Services 14,839 Programming Services 36,225 Archaeological Services Contract 1 Original Contract 22,773 Contract 1 Change Order 1 35,240 Contract 2 134,924 Available Contingency 467,007 Project Totals 12,161,000 12,161,000 Staff is still working with the contractor on a large deduct change order to remove one of the three wells from the project's scope of work. 1 ALTERNATIVES: 1. Approve Change Order #4 with Keller Excavating, Inc. in the amount of $47,336, bringing the revised total contract amount to $10,489,676.95. 2. Do not approve the change order at this time. CITY MANAGER'S RECOMMENDED ACTION: The increased asphalt was requested by the Parks and Recreation Department to provide wider access for the public into the River Valley Park recreation areas. Funding for the change will come from the available balance in the project contingency. Therefore, it is the recommendation of the City Manager that the City Council approve Alternative #1 as described above. ATTACHMENT(S): CO 4 - Keller HDR Signed.pdf 2 CHANGE ORDER NO.:4 Owner's Project No.: Owner: City of Ames W2020-0437 Engineer's Project No.: Engineer: HDR, lnc. 10040876 Contractor's Project Ames WPC Contractor: Keller Excavating, lnc. No.: Raw Project:Ames Raw Water Pipeline & Electrical Contract Name: Bid No, 2023-L22 Date lssued: April11,2023 Effective Dateof ChangeOrder: 5/5/25 The Contract is modified as follows upon execution of this Change Order: Description: Item 1: Modify Division 2, Bid ltem No. 34, to increase the quantity by 194 square yards to account for additional asphalt surface restoration. This includes repairs tothe access drive and shared use path south of 13th Street related to fiber and electrical work, as well as the entrance to the soccer fields north of 13th Street. Add 547,336.00. Attachments: Attachment 1 - Map of Additional Asphalt Surface Restoration Change in Contract Tmes Recommended by Engineer (if required) Accepted by Contractor By: Geesman,Ashley fE'"]-'"-.:*= -J.:.ilL/..t-,,t t1.. 1,,' .1 .r..,,i,,,::,, t BCDCo C-941, Change Order BCDC@ C-941, Change Order, Rev.l. Copyright@ 2018 National Society of Professional Engineers, American Council of Engineering Companies and American Society of Civil Engineers, All rights reserved. Page 1 of 2 in Contract Price Change in days Original Contract Price: s 10,200,955.80 Origi nal Contract Times: Substantial Completion: September 27, 2024 Ready for final payment: I ncrease from previously app roved Chan ge O rde rs No. 1,2,&3 s 241,385.15 lncrease from previously approved Change Orders Substantial Completion: 84 days Ready for final 62 daysafter substantial payment: completion Contract Price prior to this Change Order: 5 10,442,340.95 Contract Times prior to this Change Order: Substantial Completion: December 20th, 2024 Ready for final February 20th,2025 payment: lncrease this Change Order: s 47,336.00 No Change this Change Order: Su bstantial Completion: Ready for final payment: Contract Price incorporating this Change Order: s 10,499,676.95 Contract Times with all approved Change Orders: Substantial Completion: December 20th, 2024 Ready for final February 20th,2025 payment: 3 Title: Project Engineer Date: 5112125 Authorized by Owner Approved by Funding Agency (if applicable) By: Title: Date: ECDC@ C-941, Change Order gCDC@ C-941, Change Order, Rev.1, Copyright@ 2018 National Society of Professional Engineers, American Council of Engineering Companies and American Society of Civil Engineers. All rights reserved. Page 2 ol 2 4