HomeMy WebLinkAboutA036 - June 24, 2025, Regular Meeting of the Ames City CouncilITEM #:38
DATE:06-24-25
DEPT:PW
SUBJECT:PHASING FOR THE 2024-26 TRAFFIC SYSTEM CAPACITY IMPROVEMENT
PROGRAM (13TH & GRAND)
COUNCIL ACTION FORM
BACKGROUND:
The Traffic Systems Capacity Improvements Program in the City's Capital Improvement Plan
(CIP) is a program that addresses issues identified in the 2045 Long Range Transportation
Plan (LRTP). The 2045 LRTP identified several critical intersections that were at or nearing
capacity and needed improvements.
The 2024-26 Traffic System Capacity Improvement Program will address the
intersection of 13th Street & Grand Avenue. The project will add dedicated left turn
lanes and a new traffic signal at the intersection, a shared use path along the west side
of Grand Avenue through the project corridor, and a leading pedestrian interval (LPI) at
the traffic signal.
The City retained WHKS & Co. of Ames, Iowa in August 2024 to prepare the design for this
project. The preliminary design is now substantially complete. One of the k e y remaining
elements to finalize is the construction phasing plan. In developing this plan, careful
consideration has been given to maintaining access for adjacent residents,
accommodating necessary construction activities including underground utility work,
ensuring the safety of both the traveling public and construction personnel, and
completing the project efficiently.
Based on these considerations, WHKS & Co. and City staff recommend a phasing plan
that would close 13th Street to the east side of Grand while the east 2 lanes of Grand
Avenue are being worked on, and close 13th Street to the west side of Grand while the
west 2 lanes of Grand Avenue are being worked on. This creates two âTâ-shaped
phases as shown in the attachment. This approach is expected to significantly
accelerate construction while enhancing safety for workers and the public.
A critical consideration along 13th Street is maintaining access and operational readiness for
Fire Station 1. Staff has met with representatives from the Fire Department to review the
proposed phasing and discuss mitigation strategies. The Fire Department has indicated that
they can continue to operate effectively under the proposed plan. To further support
emergency response, staff will evaluate on-street parking regulations along side
streets and may implement temporary changes to ensure sufficient access for
emergency vehicles.
The alternative to the two "T-shaped" phased approach is to maintain traffic flow in all
directions during the project. This approach, however, presents many hazards and practical
difficulties. First, although traffic flow would be maintained, the level of service would be
severely limited due to lane closures, resulting in major delays. Second, lane widths would be
narrowed and workers would be in close proximity to traffic, which would both slow traffic flow
1
and present safety concerns. Third, the project would need to be constructed in an estimated
12 phases, which would substantially increase project costs and the length of time the project
is underway. Finally, this many phases would also make it difficult to connect utilities and
paving sections in a manner that allows the infrastructure to work as a cohesive system, which
can lead to premature failure after construction. For these reasons, staff believes the two "T-
shaped" phase approach is preferred.
Once the phasing concept is approved by the City Council, the final design process can
proceed. Staff will be working with CyRide to evaluate route and stop adjustments.
Staff will also meet with adjacent residents to determine any accessibility needs,
property access, and construction parking. It is anticipated that the construction will
occur in the 2027 construction season. This will allow staff time to complete property
acquisition, preliminary utility relocation, and the lead time to procure the signal
equipment.
ALTERNATIVES:
1. Direct staff to proceed with the attached phasing plan for the 13th Street and Grand
Avenue project.
2. Direct staff to proceed with an alternate phasing plan that maintains traffic flow in all
directions at all times during the construction of the project.
3. Direct staff to proceed with some other phasing plan.
CITY MANAGER'S RECOMMENDED ACTION:
Closing portions of 13th Street using the two "T-shaped" phasing approach presented
by staff and the consulting engineers will significantly reduce the construction
timeframe of the project and provide safer construction activities, while maintaining
effective access for emergency response vehicles. Therefore, it is the recommendation of
the City Manager that the City Council adopt Alternative No. 1, as noted above.
ATTACHMENT(S):
13th___Grand_Traffic_Control_Sheets.pdf
Grand_13th_Street.pdf
2
Grand Ave.
13
t
h
S
t
.
Harding Ave.
Roosevelt Ave.
Wilson Ave.
12
t
h
S
t
245140140
48" x 48"
W20-1
WORK
ROAD
AHEAD
48" x 48"
W20-5
LEFT LANE
CLOSED
AHEAD
48" x 48"
W4-2
NORTHBOUND ADVANCED WARING SIGN SEQUENCE
PLACE 250' SOUTH OF FIRST DRUM
250'250'
48" x 48"
W20-1
WORK
ROAD
AHEAD
48" x 48"
W20-5
RIGHT LANE
CLOSED
AHEAD
48" x 48"
W4-2
SOUTHBOUND ADVANCED WARING SIGN SEQUENCE
PLACE 250' NORTH FROM FIRST DRUM
250'250'
48" x 48"
W1-4L
48" x 48"
W1-4R48" x 24"
G20-2A
ROAD WORK
END
48" x 24"
G20-2A
ROAD WORK
END
48" x 30"
R11-2
CLOSED
ROAD
48" x 48"
W20-3
AHEAD
CLOSED
ROAD
EASTBOUND ADVANCED WARING SIGN SEQUENCE
300'
48" x 30"
R11-2
CLOSED
ROAD
48" x 48"
W20-3
AHEAD
CLOSED
ROAD
WESTBOUND ADVANCED WARING SIGN SEQUENCE
300'
24" x 12"
R9-11
STAGE 1
48" x 48"
W20-3
AT
CLOSED
HARDING
13TH
PLACE SIGNS AT 10TH & HARDING
&
16TH & HARDING
240'140'245'
200'100'
TO ALLEY
MAINTAIN ACCESS
NOTE:
1. FOR MORE INFORMATION REFER TO IDOT STANDARD ROAD PLAN TC-423
ncollins12:40:26 PM pw:\\whks-pw.bentley.com:whks-pw-01\Documents\Projects\10147\41 CAD\Design\CADD_Files\Sheet_Files\SHT_J_10147.dgn
DESIGN TEAM PROJECT NUMBER SHEET NUMBER COUNTY
4/14/2025
ENGLISHFILE NO.98765 WHKS & CO.CITY OF AMES XXX-XXXX-XXX J.2XXX-XXXX-XXXCITY OF AMESWHKS & CO.
O 1OOO1OO
FEET
3
ncollins12:40:41 PM pw:\\whks-pw.bentley.com:whks-pw-01\Documents\Projects\10147\41 CAD\Design\CADD_Files\Sheet_Files\SHT_J_10147.dgn
DESIGN TEAM PROJECT NUMBER SHEET NUMBER COUNTY
4/14/2025
ENGLISHFILE NO.
Harding Ave.
Roosevelt Ave.
Wilson Ave.
Grand Ave.
13
t
h
S
t
.
12
t
h
S
t
.
48" x 48"
W20-1
WORK
ROAD
AHEAD
48" x 48"
W20-5
LEFT LANE
CLOSED
AHEAD
48" x 48"
W4-2
SOUTHBOUND ADVANCED WARING SIGN SEQUENCE
PLACE 250' NORTH OF THE FIRST DRUM
48" x 48"
W20-1
WORK
ROAD
AHEAD
48" x 48"
W20-5
RIGHT LANE
CLOSED
AHEAD
48" x 48"
W4-2
NORTHBOUND ADVANCED WARING SIGN SEQUENCE
PLACE 250' SOUTH OF THE FIRST DRUM
48" x 30"
R11-2
CLOSED
ROAD
48" x 48"
W20-3
AHEAD
CLOSED
ROAD
EASTBOUND ADVANCED WARING SIGN SEQUENCE
300'
48" x 30"
R11-2
CLOSED
ROAD
48" x 48"
W20-3
AHEAD
CLOSED
ROAD
WESTBOUND ADVANCED WARING SIGN SEQUENCE
300'
240 140140 200 9 Devices
245140
48" x 24"
G20-2A
ROAD WORK
END
48" x 24"
G20-2A
ROAD WORK
END
48" x 48"
W1-4L
48" x 48"
W1-4R
250'250'
250'250'
STAGE 2
48" x 48"
W20-3
AT
CLOSED
WILSON
13TH
PLACE SIGNS AT 9TH & WILSON
&
16TH & WILSON
NOTE:
1. FOR MORE INFORMATION REFER TO IDOT STANDARD ROAD PLAN TC-423
100'
140'
98765 WHKS & CO.CITY OF AMES XXX-XXXX-XXX J.3XXX-XXXX-XXXCITY OF AMESWHKS & CO.
O 1OOO1OO
FEET
4
HARDING AVE
ROOSEVELT AVE
WILSON AVE
HARDING AVE W
ILSON AVE
13th STREET
GRAND AVE
HARDING AVE
ROOSEVELT AVE
HARDING AVE
GRAND AVE
1B
13th STREET AND GRAND AVENUE
SCALE IN FEET
0
Date Figure
NOT FINAL - SUBJECT TO CHANGE
LEGEND
PROPOSED PAVEMENT
TRAFFIC SIGNAL LOCATION
STOP SIGN LOCATION
PRELIMINARY PLAN
PROPOSED SIDEWALK
N
Concept -
Aerial Photography -
2.
1.
Sources:
100
Iowa Geographic Server 2016-2018
March 2022
PAVEMENT REMOVAL
Concept Study
Grand Avenue - Ames, Iowa
HDR, March 2022
5