HomeMy WebLinkAboutA055 - June 24, 2025, Regular Meeting of the Ames City CouncilTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:June 24, 2025
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 10
MEMO
PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month. Additionally, staff, along with representatives from Story Construction and
RDG Planning and Design, will provide an in-person update once per quarter
(January, April, July, & October). If anything occurs during the project that
requires Council action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Report (Attachment A).
Story Construction and RDG Planning and Design are 96% complete with
reviewing shop drawings and submittals. This activity will continue until 100%
complete.
CHANGE ORDER SUMMARY:
There were five change orders recently approved, and the changes thus far on
the project are shown on the change order log (Attachment B). The five change
orders are shown below:
Contractor Change Amount
Core Construction Channel Support $3,739
Forrest & Associates Channel Support $1,163
Lansink Construction Wood Blocking $ 752
Central States Roofing Roofing Over Hollow Core $5,116
Hilsabek Schacht Precast Pocket Covers $2,598
The following is the list of the recnt change orders:
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
1) To keep the project moving, an interior masonry wall was constructed prior to
the building being enclosed for cold weather. As a result, a crack developed due
to the fluctuation in temperatures. 2) Wood blocking was added to wall support to
provide more space for wires. 3) There were concerns with the unevenness of
the roofing membrane over the hollow core concrete ceiling in the mechanical
and electrical room. Staff directed Central States Roofing to make sure the final
surface was quality, level, and will avoid punctures, thus the additional cost. 4)
Staff did not like the look of the precast pockets and directed Hilsabek Schacht to
add covers to these areas.
To date, change orders for the project total $264,833, or 12.61% of the
contingency budget. The contingency for this project is $2.1 million with a
current balance of $1,835,167. There is also $1 million set aside for
mitigation of contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2025-6.pdf
Attachment B - Change Order Log - 6-24-25.pdf
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
June 2025
*Natatorium: Wellness, Recreation and Lap Pools
*Non-Natatorium: All supporting rooms outside of the Natatorium including Mechanical, Loading,
Locker Rooms, Offices, Main Lobby & Check-In, and the Alternate Walk Path
PROGRESS THIS PAST MONTH:
1. Wellness pool walls were backfilled.
2. Lap pool deep end basin slabs were poured. Excavations continued for shallow end.
3. Slab on grade for the non-Natatorium was completed.
4. Storm structures were prepared and concrete paving started in the NW corner of the site.
5. Interior wall framing, masonry partitions and ductwork started in the non-Natatorium.
6. Mechanical equipment installations started in the Aquatic and Electrical Mechanical Rooms.
7. Building Envelope Consult inspections continued for vapor barrier and pool water stop.
8. Special inspections and testing of interior and exterior concrete continued.
9. Submittals and Requests for Information continued to be processed between the Bid Package
Contractors, Story Construction, and RDG Planning & Design.
WORK PLANNED FOR NEXT MONTH:
1. Interior wall framing, masonry partitions and ductwork will continue.
2. Mechanical, electrical, plumbing and sprinkler piping rough ins will begin.
3. Curtain wall framing - i.e. windows - will begin.
4. Storm structures and paving in the NW corner of the site will be completed.
5. Storm structures and preparations for paving in the NE corner of the site will begin.
6. Building Envelope Consult inspections will continue for vapor barrier and pool water stop.
7. Building Envelope Consult Pre-install meeting will be held for shower waterproofing.
8. Special inspections and testing of concrete and sitework will continue.
9. MEP Commissioning Kick-Off meeting will be held with mechanical and electrical contractors.
10. Continue development of the Crew Workflow Plans for the pools, interior finishes and site
improvements and parking.
SCHEDULE SUMMARY:
Construction Substantial Completion Date: January 20, 2026
Page 1 of 6
PROJECT PHOTOS: [Next page]
3
Story Construction Co.
Printed on Tue Jun 17, 2025 at 01:31 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
05/28/2025 at 09:49 am
Upload Date
05/28/2025 at 09:46 am
Uploaded By
Deb Thurmond
Name
IMG_2025_05_28_09_49…
Progress
Description
Taken Date
06/04/2025 at 07:54 am
Upload Date
06/06/2025 at 02:11 pm
Uploaded By
Eli Rochleau
Name
8C07B61D-1EEE-4D00-8…
Page 2 of 6
PROJECT PHOTOS:
Lap Pool Deep End
Slab Preparation
Lap Pool Deep End
Slab Pour
4
Story Construction Co.
Printed on Tue Jun 17, 2025 at 01:31 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
06/06/2025 at 12:16 pm
Upload Date
06/06/2025 at 02:14 pm
Uploaded By
Eli Rochleau
Name
3BC0F3C0-8EC0-438C-9…
Progress
Description
Taken Date
06/02/2025 at 03:20 pm
Upload Date
06/06/2025 at 02:10 pm
Uploaded By
Eli Rochleau
Name
2E20226C-A9E2-49BA-8…
Page 3 of 6
Lap Pool Deep End
Slab Complete
Aquatic-Mech masonry
partition and start of
pool equipment
5
Story Construction Co.
Printed on Tue Jun 17, 2025 at 01:31 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
06/02/2025 at 01:41 pm
Upload Date
06/06/2025 at 02:10 pm
Uploaded By
Eli Rochleau
Name
53F575D4-9EAD-404A-9…
Progress
Description
Taken Date
06/03/2025 at 07:23 am
Upload Date
06/06/2025 at 02:13 pm
Uploaded By
Eli Rochleau
Name
6227BD6E-C935-4F97-8…
Page 4 of 6
Locker Rooms masonry
chases for ductwork
Walk Path & Check In
slab preparation
6
Story Construction Co.
Printed on Tue Jun 17, 2025 at 01:31 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Progress
Description
Taken Date
06/03/2025 at 11:48 am
Upload Date
06/06/2025 at 02:10 pm
Uploaded By
Eli Rochleau
Name
9FE0B3FE-7957-4532-9…
Aerial Photos
Description
Taken Date
05/30/2025 at 09:14 am
Upload Date
05/30/2025 at 09:48 am
Uploaded By
Mitch Anderson
Name
DJI_0521.JPG
Page 5 of 6
Walk Path, Check In, &
Admin slab finishing
Sitework - NW Parking
prep for paving at
detention areas
7
Story Construction Co.
Printed on Tue Jun 17, 2025 at 01:31 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Aerial Photos
Description
Taken Date
06/16/2025 at 02:49 pm
Upload Date
06/16/2025 at 03:09 pm
Uploaded By
Mitch Anderson
Name
DJI_0539.JPG
Page 6 of 6
Sitework - NW Parking
paving in progress
8
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver
Mods, Steel Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,067,925
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,063,946
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,066,898
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,068,101
Core Construction 5 Channel Support $ 3,739 $ 2,064,362
Forrest & Associates 1 Channel Support $ 1,163 $ 2,063,199
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,021,070
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,018,212
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,015,191
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 2,011,196
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 2,009,557
Lansink Construction 6 Wood Blocking $ 752 $ 2,008,805
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 2,007,158
Central States Roofing 2 Roofing Over Hollow Core $ 5,116 $ 2,002,042
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 2,005,865
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 2,004,122
Hilsabek Schacht 1 Wet Room Door Change $ - $ 2,004,122
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 2,004,122
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 2,000,565
Hilsabek Schacht 4 Site Signage $ (350) $ 2,000,915
Hilsabek Schacht 5 Precast Pocket Covers $ 2,598 $ 1,998,317
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 1,996,947
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 1,994,255
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 1,996,575
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical
Louver Mods, Glycol Feed Dual Pump $ 38,702 $ 1,957,873
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,945,840
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,923,887
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,909,650
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,904,971
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,897,224
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,851,805
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd
Ave $ 14,518 $ 1,837,287
Lakeside 1 Site Signage $ 2,120 $ 1,835,167
Totals / Current Balance $ 264,833 $ 1,835,167
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 6/24/25)
Highlighted Rows Indicate New Change Orders Since the Last Update
9