HomeMy WebLinkAboutA001 - Council Action Form dated June 24, 2025ITEM #:42
DATE:06-24-25
DEPT:P&R
SUBJECT:DALEY PARK SPLASH PAD
COUNCIL ACTION FORM
BACKGROUND:
The proposed Daley Park Splash Pad was included as part of the FY 2020/21 Capital
Improvement Plan. The splash pad will include a recirculation system with chlorine and UV
disinfection. The play area components will consist of ground sprays, geysers, directional jets,
and a medium-sized dump bucket.
The splash pad construction will adhere to the State of Iowa Swimming Pool Code and will be
annually inspected by State inspectors. The City has received notice from the Iowa
Department of Inspections and Appeals that a waiver will be granted exempting the City from
constructing additional bathroom fixtures due to the existing restroom located at Daley Park.
However, outdoor showers will be required to be installed.
Splash Pad Equipment:
Since the splash pad equipment is very specialized, Snyder and Associates, Ankeny, Iowa
was hired to develop a Request for Proposals (RFP) which included the splash pad
equipment, mechanical equipment, and installation. The RFP was sent to qualified splash pad
equipment vendors for them to provide proposals for a cost that was not to exceed $535,000.
This approach to purchase equipment is how the Agility Course Equipment for Carr Park was
purchased.
The scope of work required vendors to provide a minimum of 25 play components (in-ground
and above ground) and also include chlorine disinfection equipment that would match the
existing equipment installed at the Furman Aquatic Center, Steven L. Schainker Plaza, and the
equipment that will be installed at the Fitch Family Indoor Aquatic Center. Request for
Proposals (RFP) were sent to eight vendors. Staff received three proposals from two vendors.
The table below outlines the vendors, number of components, and cost for the equipment and
installation.
Vendor # of Components
Cost for
Equipment and
Installation
Commercial Recreation Specialists, Verona,
Wisconsin Option #1 37 $577,934.13
Commercial Recreation Specialists, Verona,
Wisconsin Option #2 31 $526,494.63
Crouch Recreation, Omaha, Nebraska 28 $534,963.00
1
Commercial Recreation Specialists (CRS) Option 1 (Attachment A): Provides a variety of
in-ground and above ground features including a medium sized dump bucket, multiple play
pieces for young children (2-5 years of age), and play components for individuals of all ages.
Commercial Recreation Specialists Option 2 (Attachment B): Provides a lot of the same
components as Option 1, but the above ground components are reduced by six, in order for
the cost to be below $535,000.
Crouch Recreation (Attachment C): The majority of the spray components are in-ground
with minimal above ground components. Unfortunately, the proposal is not as appealing as
the two proposed by Commercial Recreation Specialists.
The public had the opportunity to vote on their preferred option at the Juneteenth Celebration
at Bandshell Park on June 14. There were 163 votes cast for the proposals with Commercial
Recreation Specialists Option 1 receiving 157 votes and Crouch Recreation receiving six
votes.
Construction - Concrete, Utilities, Furnishings;
For most of the remaining items of this project, Snyder was hired to provide engineered plans
and specifications and construction administration. The construction documents include the
installation of the water, sewer, and electric utilities, grading, concrete, benches, outdoor
showers, and shade structure necessary to complete the construction of the splash pad. Not
included as part of the specifications, but included in the total cost of the project, is a building
that will house the mechanical equipment. The building will be approximately 15' x 15' and
may be constructed by City staff.
The Plans and Specifications were distributed on May 14, 2025 with bids due on June 11,
2025. The construction documents were split into a Base Bid, Alternate #1 (Shade Structures),
and Alternate #2 (Benches). Two bids were received and the results are shown below:
Bidders Base Bid Alternate #1 Alternate #2 Total
TK Concrete, Inc.,
Pella, IA $295,595 $27,225 $10,000 $332,820
Caliber Concrete
LLC, Adair, IA $344,145 $54,000 $ 8,000 $406,145
The bid from TK Concrete, Pella, Iowa, is the lowest and is acceptable.
Project Total:
To understand the total project costs for the Daley Park Splash Pad, the following table
provides a breakdown of the project components, the cost opinion and funding, the low bid
amounts, as well as what staff is recommending Council approve. The recommendation
includes the Base Bid, Alternate #1, CRS Option 1, and a reduced cost for the mechanical
building. Staff is not recommending Alternate #2 (Benches) as these can be procured at
a lower cost through the Parks and Recreation operating budget. Additionally, Snyder
recommends reducing the construction base bid contingency to 5%.
2
Component Cost Opinion /
Funding Amount Low Bid Recommendation
Construction Base Bid $ 231,749 $ 295,595 $ 295,595
Construction Base Bid
Contingency (10%)$ 23,175 $ 29,560 $ 14,780
Alternate #1 - Shade Structure $ 25,000 $ 27,225 $ 27,225
Alternate #2 - Benches $ 8,000 $ 10,000 $ 0
Splash Pad Equipment and
Installation $ 535,000 $ 526,495 $ 577,934
Mechanical Building $ 75,000 $ 75,000 $ 50,000
A & E $ 26,500 $ 26,500 $ 26,500
TOTAL PROJECT COST $ 924,424 $ 990,375 $ 992,034
FUNDING AVAILABLE $1,349,392 $1,349,392 $1,349,392
SURPLUS / (SHORTFALL)$ 424,968 $ 359,018 $ 357,358
There is sufficient funding for this project and it is recommended that surplus funding for this
project be used for the Park Maintenance Facility Expansion Project. A detailed breakdown of
funding for this project, the facility expansion project, and the Ada Hayden Trail Replacement
project is shown in Attachment D. This project is expected to be completed by June 1, 2026.
ALTERNATIVES:
1. The City Council can:
a. Accept the report of bids
b. Approve final plans and specifications and award a contract to TK Concrete, Inc. of
Pella, IA, in the amount of $322,820 for the Base Bid and Alternate #1
c. Award a contract to Commercial Recreation Specialists, of Verona, WI, for Splash
Pad Equipment and Installation, in the amount of $577,934
2. Award contracts to one of other bidders.
3. Accept the report of bids but do not award contracts at this time.
4. Refer back to staff.
CITY MANAGER'S RECOMMENDED ACTION:
The Splash Pad is an amenity that has been desired in the community for many years
and it will be located in west Ames, where there currently is a lack of large park
amenities, especially aquatic activities. The residents in west Ames are excited about
the addition of the splash pad, which will be a staple for many years. Based on public
feedback and staff's recommendation, the CRS Option 1 design is the desired choice
and there is ample funding available to cover the additional cost. Therefore, it is the City
Manager's recommendation that City Council approve Alternative #1, as described above.
ATTACHMENT(S):
Attachment C - Crouch Recreation.pdf
Attachment A - CRS Option #1.pdf
3
Attachment D - Project Cost Breakdown.pdf
Attachment B - CRS Option #2.jpeg
4
5
6
Component
Cost Opinion / Funding
Amount Low Bid Recommendation
Construction Base Bid 231,749$ 295,595$ 295,595$
Construction Base Bid Contingency (10%)23,175$ 29,560$ 14,780$
Alternate #1 - Shade Structure 25,000$ 27,225$ 27,225$
Alternate #2 - Benches 8,000$ 10,000$ -$
Splash Pad Equipment and Installation 535,000$ 526,495$ 577,934$
Mechanical Building 75,000$ 75,000$ 50,000$
A & E 26,500$ 26,500$ 26,500$
TOTAL PROJECT COST 924,424$ 990,375$ 992,034$
FUNDING AVAILABLE 1,349,392$ 1,349,392$ 1,349,392$
SURPLUS / (SHORTFALL)424,968$ 359,018$ 357,358$
Component
Cost Opinion / Funding
Amount Low Bid Recommendation
Base Bid 1,234,615$ 1,066,989$ 1,066,989$
Base Bid Contingency (5%)61,731$ 53,349$ 53,349$
Alternate #1 - Fletcher Connector 53,507$ 49,201$ 49,201$
Alternate #2 - Stone Brooke Connector 23,335$ 20,673$ 20,673$
Alternate #3 - Edgewater Connector 11,595$ 11,345$ -$
Alternate Contingency (5%)4,422$ 4,061$ 3,494$
Public Works Staff Time -$ -$ 25,000$
A & E 88,600$ 88,600$ 75,000$
TOTAL PROJECT COST 1,477,805$ 1,294,218$ 1,293,706$
FUNDING AVAILABLE 1,400,000$ 1,400,000$ 1,400,000$
SURPLUS / (SHORTFALL)(77,805)$ 105,782$ 106,294$
Component
Cost Opinion / Funding
Amount Low Bid Recommendation
Base Bid 755,650$ 990,000$ 990,000$
Base Bid Contingency (5%)37,783$ 49,500$ 49,500$
Alternate #1 - Cold Storage Expansion 147,605$ 195,700$ 195,700$
Alternate #2 - Concrete 85,000$ 44,900$ 44,900$
Alternate #3 - Door Opener Retrofit 15,000$ 10,325$ -$
Alternate #4 - Relocate Bulk Water Station 118,500$ 113,475$ 113,475$
Alternate #5 - 13th Street Sidewalk 10,340$ -$ -$
Alternate Contingency (5%)18,822$ 18,220$ 17,704$
A & E, Survey, Etc.102,760$ 102,760$ 102,760$
Special Inspections 3,000$ 19,000$ 19,000$
FFE (Furniture, Fixtures, Equipment)35,000$ 35,000$ 35,000$
TOTAL PROJECT COST 1,329,460$ 1,578,880$ 1,568,039$
FUNDING AVAILABLE 897,464$ 897,464$ 897,464$
SURPLUS / (SHORTFALL)(431,996)$ (681,416)$ (670,575)$
Cost Opinion / Funding
Amount Low Bid Recommendation
TOTAL PROJECT COST 3,731,689$ 3,863,473$ 3,853,779$
FUNDING AVAILABLE 3,646,856$ 3,646,856$ 3,646,856$
SURPLUS / (SHORTFALL)(84,833)$ (216,617)$ (206,923)$
MINI PITCH SAVINGS 64,500$
AGILITY COURSE SAVINGS 30,000$
DISC GOLF COURSE IMPROVEMENTS 10,000$
BROOKSIDE STAIR RAILINGS 1,698$
PARK DEVELOPMENT FUND 100,725$
TOTAL 206,923$
THREE PROJECTS COMBINED
OPTIONS TO COVER SHORTFALL
P & R MAINTENANCE FACILITY
ADA HAYDEN PATH REPLACEMENT
DALEY PARK SPLASH PAD
7
8