HomeMy WebLinkAboutA007 - Motion accepting Fitch Family Indoor Aquatic Center Monthly UpdateTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:May 27, 2025
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 10
MEMO
PROJECT UPDATE:
In accordance with a previous directive, staff is required to keep the City Council
informed of the construction status of the Fitch Family Indoor Aquatic Center
(FFIAC) and will provide a written update at Council's second meeting of each
month. Additionally, staff, along with representatives from Story Construction and
RDG Planning and Design, will provide an in-person update once per quarter
(January, April, July, & October). If anything occurs during the project that
requires Council action, staff will present this in a timely manner.
In accordance with this directive, the City's Construction Manager for the project,
Story Construction, has provided a Project Status Report (Attachment A). Please
note that groundwater was present when digging the deep end of the Lap
Pool. The groundwater was tested, and no contamination was present.
Story Construction and RDG Planning and Design are 96% complete with
reviewing shop drawings and submittals. This activity will continue until 100%
complete.
CHANGE ORDER SUMMARY:
There were two change orders recently approved, and the changes thus far on
the project are shown on the change order log (Attachment B). The two change
orders are related to sink countertop brackets and affect Core Construction
Services (-$1,203) and Lansink Construction ($1,639). The installation of the
brackets were moved from Core's contract to Lansink's contract. Staff also
requested additional brackets be installed on the double sink countertops which
increased Lansink's cost by $436.
To date, change orders for the project total $251,465, or 11.97% of the
contingency budget. The contingency for this project is $2.1 million with a current
balance of $1,848,535. There is also $1 million set aside for mitigation of
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Update 2025-5.pdf
Attachment B - Change Order Log - 5-22-25.pdf
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
2
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
May 2025
PROGRESS THIS PAST MONTH:
1. Roof edge metals and downspouts were completed on the Natatorium.
2. Precast touch up and repairs were completed.
3. Joint sealant work related to the precast concrete panels was completed.
4. High ceiling painting in all the Natatorium was completed.
5. Wellness pool basin slab and walls were poured.
6. Wellness pool plumbing fixtures and piping started.
7. Lap pool excavation started at the deep end.
8. Soil sampling of excavations for hazardous waste continues with clean test results.
9. Ground water was visible in the Lap pool excavation and was sampled with clean test results.
10. Underslab piping for plumbing and underslab electrical conduit in the mechanical room, locker
rooms, and alternate was completed.
11. Rock, vapor barrier and slab on grade were completed in mechanical room.
12. Special inspections and testing were completed for mechanical trenching compaction and
concrete strength.
13. Storm structures and preparation for paving started in the NW corner of the site.
14. Building Envelope Consult inspections were completed for joint sealants and membrane roofing
and continues for vapor barrier and swimming pool water stop.
15. Building Envelope Consult Pre-Install meetings were held for Wall Assemblies and Wall
Openings & Penetrations.
16. The project team held an Owner Move-In Expectations meeting to start discussions of turnover.
17. Submittals and Requests for Information continued to be processed between the Bid Package
Contractors, Story Construction, and RDG Planning & Design.
WORK PLANNED FOR NEXT MONTH:
1. Lap pool basin slab and walls will be poured.
2. Rock, vapor barrier and slab on grade will be completed for locker rooms, admin and alternate.
3. Interior wall framing, masonry partitions and ductwork starts in locker rooms and adjacent areas.
4. Door frames and main electrical switch gear will be delivered to the site.
5. Building Envelope Consult inspections will continue for vapor barrier and pool water stop.
6. Storm structures and paving in the NW corner of the site will be completed.
7. Special inspections and testing of concrete and sitework continues.
8. Development of the Crew Workflow Plan for interior finishes.
Page 1 of 10 3
9. Development of the Crew Workflow Plan for the pools.
10. Development of the Crew Workflow Plan for site improvements for storm water and parking.
SCHEDULE SUMMARY:
Construction Substantial Completion Date: January 20, 2026
PROJECT PHOTOS: [Next page]
Page 2 of 10 4
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 3 of 10 5
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 4 of 10 6
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 5 of 10 7
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 6 of 10 8
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 7 of 10 9
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 8 of 10 10
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 9 of 10 11
Story Construction Co.
Printed on Mon May 19, 2025 at 03:50 pm CDT
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 10 of 10 12
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver Mods, Steel
Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,067,925
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,063,946
Core Construction 3 Geared Trolley and Hoist $ (2,952) $ 2,066,898
Core Construction 4 Sink Countertop Brackets $ (1,203) $ 2,068,101
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,025,972
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,023,114
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,020,093
Lansink Construction 4 Check-In Standing Desk $ 3,995 $ 2,016,098
Lansink Construction 5 Sink Countertop Brackets $ 1,639 $ 2,014,459
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 2,012,812
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 2,016,635
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 2,014,892
Hilsabek Schacht 1 Wet Room Door Change $ - $ 2,014,892
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 2,014,892
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 2,011,335
Hilsabek Schacht 4 Site Signage $ (350) $ 2,011,685
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 2,010,315
Sande Construction 2 CO2 Tank Distribution Piping $ 2,692 $ 2,007,623
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 2,009,943
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical Louver Mods,
Glycol Feed Dual Pump $ 38,702 $ 1,971,241
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,959,208
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,937,255
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,923,018
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,918,339
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,910,592
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,865,173
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd Ave $ 14,518 $ 1,850,655
Lakeside 1 Site Signage $ 2,120 $ 1,848,535
Totals / Current Balance $ 251,465 $ 1,848,535
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 5/22/25)
Highlighted Rows Indicate New Change Orders Since the Last Update
13