HomeMy WebLinkAboutA001 - Council Action Form dated March 25, 2025ITEM #:12 DATE:03-25-25 DEPT:ELEC SUBJECT:2025 ELECTRIC RELIABILITY PLAN COUNCIL ACTION FORM BACKGROUND: Electric Services manages its inspection and maintenance efforts under an adopted reliability plan that has been filed with the Iowa Utilities Commission (IUC). Historically, such plans were prepared and approved at the City staff level. The Iowa Utilities Commission has recently adopted changes to its administrative code (IAC 199- 27.8) and now requires each municipal electric utility to have its adopted r e l i a b il i t y plan approved by its respective governing authority prior to filing updates to its existing plans. Therefore, Electric Services is requesting that Council approve the adopted Reliability Plan to satisfy this IUC requirement. Staff has prepared a Reliability Plan using guides and reference material provided by the Iowa Association of Municipal Utilities (IAMU). The proposed Reliability Plan is attached for reference. ALTERNATIVES: 1. Approve the adoption of the 2025 Electric Reliability Plan. 2. Do not approve the 2025 Electric Reliability Plan. 3. Delay the approval and request further information from staff. CITY MANAGER'S RECOMMENDED ACTION: Iowa Administrative Code now requires the approval of the Electric Utility’s Electric Reliability Plan by the City Council. City staff has prepared this plan using reference materials supplied by IAMU to ensure compliance. Therefore, it is the recommendation of the City Manager that the City Council adopt Alternative No. 1, as described above. ATTACHMENT(S): COA Reliability Plan 2025.pdf 1 515.239.5170 main 515.239.5308 fax 502 Carroll Ave. Ames, IA 50010 www.CityofAmes.org Ames Municipal Electric Services Tuesday, March 25th, 2025 CITY OF AMES RELIABILITY PLAN The City of Ames strives to deliver its customers safe, reliable, and affordable power. While this reliability plan focuses on information pertinent to reliability, other considerations must also be taken into account to balance the needs of the customers with the business decisions of the system's managers. The purpose of this reliability plan is to meet the requirements of Iowa Administrative Code 199-27.8. This reliability plan does not replace but supplements the information provided to the utility's governing authority throughout the year. This plan has been approved by the governing authority of the City of Ames. This plan covers the reporting period of January 1, 2025, through December 31, 2025. During 2024, customers were able to contact the City of Ames 24/7 through an after-hours telephone number. They were able to promptly report service interruptions and other issues with their electric service through clearly defined communication channels. The City of Ames reliability plan represents an integrated approach addressing the electric system's operation, maintenance, and inspection. Providing safe, reliable, and affordable electric service to meet customers' needs requires a careful balance and consideration of all the above factors, as well as the resources available to achieve the desired results. The City of Ames made reasonable efforts to avoid and prevent service interruptions during the last year. However, when interruptions occurred, service was reestablished within the shortest time practicable, consistent with safety. The City of Ames has an effective preventive maintenance program and is capable of emergency repair work on an appropriate scale to its scope of operations and the physical condition of its electric facilities. This program is included in our vegetation, substation, and visual inspection plans. To improve its effectiveness, these plans are reviewed annually. Quality of work and final delivery by contractors are also assessed. The City of Ames continues to follow a written program for inspecting and maintaining its electric supply lines and substations to determine the need for replacement, maintenance, and repair for tree pruning or other vegetation management. The City of Ames is following a schedule for this written program to ensure the completion of all areas within a 36-month timeline. The City of Ames assesses the status of its distribution line equipment, including animal guarding and pole-mounted power factor correction equipment. The City of Ames models and compares consumption metrics during peak load, non-peak load, and warm and cold conditions to issue maintenance jobs based on these assessments and conditions. The City of Ames also installs lightning arresters at appropriate locations on distribution line equipment to reduce outages and protect equipment and inspects them annually using infrared and visual inspections. The City of Ames has a comprehensive pole inspection program, with the entire system scheduled for completion on a 10-year cycle, including both overhead and groundline conditions. The program consists of a complete inspection of poles over 10 years of age and a report on all rejected poles to be replaced. Poles are generally replaced within six months following an inspection. Besides these two inspections, the City of Ames also conducts a Visual Inspection of all transmission poles every fiscal year. 2