RESOLUTION ACCEPTING COMPLETION OF
BAKER SUBDIVISION GEOTHERMAL WELL INSTALLATION PROJECT
FOR THE CITY OF AMES, IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Baker Subdivision Geothermal Well Installation project for the City of Ames, Iowa, in accordance
with a contract dated the 9th day of February, 2021, by and between the City of Ames, Iowa, and
Thorpe Water Development Company of Ankeny, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Baker Subdivision Geothermal Well Installation
project has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $227,208.31 (inclusive of sales tax).
Section 3. The amount due Thorpe Water Development Company of Ankeny, Iowa, is
hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 25th day of March, 2025.
_________________________________ ___________________________________
Renee Hall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 25th day of March, 2025.