HomeMy WebLinkAboutA001 - Council Action Form dated October 22, 2024ITEM #:14 DATE:10-22-24 DEPT:PW SUBJECT:2024/25 AIRPORT ENTRYWAY IMPROVEMENTS (AIRPORT ENTRYWAY RECONSTRUCTION) COUNCIL ACTION FORM BACKGROUND: The Capital Improvements Plan's 2024/25 Airport Entryway Improvements project is for reconstructing the main entrance road. The work includes the removal and replacement of the existing road with a concrete pavement section, reworking the subgrade, and installing subdrains. These improvements support the Airport Master Plan’s goals for enhanced accessibility and operational efficiency. In August 2023, City staff conducted a qualifications-based selection following federal requirements for a Master Agreement to develop plans and specifications for this and other upcoming airport projects. One submittal was received from Bolton & Menk of Ames, Iowa, and was determined to be qualified and approved by the Federal Aviation Administration (FAA). Each project is designed and administered under a separate work order approved by the City Council. Therefore, the 2024/25 Airport Entryway Improvements (Airport Entryway Reconstruction) is the next project ready for design, as detailed in the attached draft agreement. Below is a summary of the project's budget: Revenues Expenses G.O. Bonds (FY 2024/25)$680,000 Design $ 72,700 Construction/Project Admin $607,300 Total $680,000 Total $680,000 ALTERNATIVES: 1. Approve the professional services agreement (Work Order #6) with Bolton & Menk in the amount not to exceed $72,700 for design of the 2024/25 Airport Entryway Improvements. 2. Reject the agreement, and direct staff to solicit other proposals. CITY MANAGER'S RECOMMENDED ACTION: By moving forward with the contract for the 2024/25 Airport Entryway Improvements, the Airport will enhance access and traffic flow, thereby improving safety and operational efficiency for all users. Therefore, it is the recommendation of the City Manager that the City Council approve Alternate No. 1, as shown above. ATTACHMENT(S): Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.pdf 1 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16- 2024.docx Page 1 WORK ORDER #6 TO PROFESSIONAL SERVICES CONTRACT (DESIGN, BIDDING AND CONSTRUCTION ADMINISTRATION SERVICES) 2025 ENTRANCE ROAD IMPROVEMENTS AMES MUNICIPAL AIRPORT Ames, IOWA BETWEEN: The City of Ames An Iowa municipal corporation (CLIENT/SPONSOR) AND: Bolton & Menk, Inc. (CONSULTANT) EFFECTIVE DATE: October _________, 2024 RECITALS 1. The City of Ames owns and operates the Ames Municipal Airport located near Ames, Iowa. 2. This is Work Order #6 to the Professional Services Contract, between City of Ames and Bolton & Menk, Inc. The Professional Services Contract effective September 6, 2023, is referred to herein as the “Master Agreement”. EXCLUSIONS Since this project is a non-federal funded project, exclusions are required to amend the terms and conditions of the MASTER AGREEMENT for this work order only. The following sections of the MASTER AGREEMENT will not apply to this Work Order #6. 1. Exclude Section V – SECTION 508 OF THE REHABILITATION ACT in its entirety. 2. Exclude Section W – FEDERAL CONTRACT PROVISIONS in its entirety. 3. Exclude Section X – AUDIT REVIEW in its entirety. 4. Exclude Exhibit I – Federal Contract Provisions for A/E Agreements in its entirety. All other provisions shall remain in effect as originally purposed. 2 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 2 AGREEMENT DESCRIPTION The CONSULTANT agrees to provide Design and Bidding for the 2025 Entrance Road Improvements at the Ames Municipal Airport (herein referred to as the Project) that consist of the following scope of work: 1. The project will include removal and replacement of the existing entrance road, as local funding allows, with a PCC pavement section that will contain a curb. a. Pavement section will include re-working subgrade b. Installing new subbase c. Installing subdrains where allowed by grade or depth provided by storm sewer system. 2. It is not anticipated that that the in-situ subgrade will be chemically treated or stabilized in any manner as part of the project. 3. As the entrance road will be replaced as funding allows, it is anticipated that there will be minimal changes made to the existing grades or drainage patterns. Also, the centerline alignment is anticipated to remain unchanged. As part of the design, turning movements of a WB-67 or similar sized vehicle representing the vehicle utilized to deliver aircraft fuel will be used to confirm the geometry of the future pavement. 4. City of Ames UM crews will televise storm sewer to confirm replacement is warranted prior to the start of design. If existing storm sewer intakes within the section of the entrance road indicate needing replacement, they will be replaced along with the associated piping under the proposed entrance road. Any replacement of storm sewer piping outside of the anticipated construction limits of the proposed entrance road is not included within the scope of the project. Storm sewer replacement will include: a. Storm Sewer piping will be the same size as existing b. No modeling will be provided for storm sewer or drainage of the area. Intakes will be replaced in kind or of a similar kind. c. Special consideration may be given to the replacement of existing storm sewer pipes or intakes that end in an intake upstream that are generally within the limits of the reconstructed area. This will be validated by City of Ames UM crews via televising. Available funding will be a consideration and discussion with Client will occur as to whether to add additional storm sewer or not. 5. No other utilities are expected to be replaced under the pavement section, outside of the pavement section or improved in the general vicinity of the entrance road as part of the project. 6. Any driveways to hangar buildings or sidewalk that connect perpendicular will be replaced to approximately 10’± from the back of curb or further if needed due to grade adjustment of the replaced entrance road. The driveways and /or connections removed and replaced shall be: 3 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 3 a. Replaced with PCC material b. Of a similar geometry, unless otherwise indicated by the City of Ames c. The minimum necessary for reconnection after replacing the adjacent section of roadway. Any improvements to driveways or sidewalks outside of the minimum necessary for reconnection after reconstruction shall be either done by the City of Ames or the affected hangar tenant. 7. All coordination with affected hangar tenants and coordinating access routes or parking areas for affected hangar tenants shall be the responsibility of the City of Ames. 8. Mailboxes within the affected area of the reconstruction will be moved to a single temporary location during construction to allow for mail service during construction. After completion of improvements, mailboxes will be reinstalled in a similar location at the original location. The City of Ames shall be responsible for coordination with affected hangar tenants. 9. Landscaping improvements or way finding signage are not anticipated to be provided or impacted as part of the project. 10. Lighting improvements along the reconstructed portion of the entrance road are not anticipated to be a part of the project. 11. It is anticipated that the project will be segmented by a phasing plan into fundable segments for bidding, to maximize local funding available. It is anticipated that the phasing plan will utilize existing infrastructure where available to provide as much accessibility to the existing parking lot as feasible. It is not anticipated that the phasing plan will require additional design of temporary access routes for the project. If additional design is required to accommodate temporary access routes as part of the phasing plan, it shall be considered additional services. 12. Provide a conceptual level parking lot layout of the interior area available for future parking lot, between the existing entrance road segments. This will include preparation of the concept and preparation of a PDF exhibit as well as CAD files. . An exhibit will be provided to the City of Ames for review and comment. After receipt of any comments, we will make revisions to the provided conceptual layout in a single effort. The conceptual parking lot layouts will be provided after completion and processing of the topographic survey data. I.A. BASIC SERVICES For purposes of this Work Order, the Basic Services to be provided by the CONSULTANT are as follows: 1. DESIGN AND BIDDING SERVICES Task 1: Project Initiation Subtask 1.1: Kickoff meeting Description: The Bolton & Menk project team will facilitate a kick-off meeting with the City of Ames and Airport staff to accomplish the following: • Review and confirm the scope and nature of proposed improvements • If requested, review special conditions regarding project staging during construction 4 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 4 • If requested, conduct a field review of project area by project team members and City staff Task 2: Data Collection Subtask 2.1: Field Data Collection Description: Collect detailed field survey information within project limits and adjacent areas as well as the areas on airport property where improvements will be implemented as required for final design and preparation of construction documents. The field survey will be supplemented by other available information such as aerial photos and mapping, utility maps, as-built drawings, reports, and studies, etc. Subtask 2.2: Geotechnical Investigations Description: Collect and review geotechnical data to gather information on existing soil conditions, and existing pavement depths. Coordination will be done with the geotechnical subconsultant to schedule work and establish any work constraint parameters. Field work will be performed by a qualified geotechnical subconsultant. The geotechnical investigation will include up to three (3) soil borings to a depth of 5 feet. A geotechnical report will be prepared to discuss the findings of the soil borings and discuss soil classifications, site conditions, groundwater observations, grading concerns, paving design and subbase design. Subconsultant services will be provided by Construction Materials Testing. After receiving the testing report from the geotechnical firm, the Consultant will analyze the data and any existing geotechnical data received from Sponsor, consisting of the following tasks: o Review geotechnical recommendations o Review the geotechnical pavement recommendations from the geotechnical report o Incorporate pavement design recommendation from geotechnical report on plan sheets Task 3: Plan and specification preparation Final design and plans will conform to requirements of the City of Ames, or SUDAS Specification requirements. Plans will be reviewed with the City of Ames and/or Airport staff throughout the project. The Project Manual will be reviewed at the 95% complete stage. Subtask 3.1: 2025 Entrance Road Improvements Plans Description: Complete preliminary and final plans. Major design components to include the following: • Horizontal alignment and profile view of entrance road reconstruction improvements • Pavement sections of proposed pavements • Removal plans • Applicable Storm Sewer Plan and Profile plans • Applicable Grading Improvements • General layout plan of the proposed improvements • Preparation of traffic control sheet 5 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 5 • Miscellaneous plan sheets, including, but not limited to: Title sheet, tabulations, typical sections, details, and other required information Subtask 3.2: Project Manual Description: Prepare project manual for the project, including: • General information for bidders: Advertisement for bids, instructions to bidders, special bidding requirements/provisions • General conditions and supplementary conditions • Information to be submitted with bid: Proposal, bid bond, information requested from bidder, etc. • Agreement, performance, payment and maintenance bond forms • General conditions • Supplemental Technical specifications, where a Iowa SUDAS Specification is not available Deliverables: • Preliminary plans and final plans • Preliminary and final project manual • Statement of estimated quantities and construction cost at preliminary and final plans Task 4: Bidding Services Subtask 4.1: Bidding Phase Services Description: Provide the following services during the bidding phase: • Provide copies of the contract/bidding documents • Address questions from prospective bidders, subcontractors, and suppliers, and prepare and issue addenda as required Subtask 4.2: Bid Letting and Post-Bid Services Description: Provide the following services during the bid and post -bidding phase: • Attend bid letting • Review and evaluate bids submitted • Prepare a bid tabulation • Prepare a recommendation of award and/or alternate action by the Sponsor Deliverables: • Bid Tabulation • Recommendation for award to Sponsor 6 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 6 2. CONCEPTUAL PARKING LOT LAYOUT Subtask 5.1: Parking Lot Concept Description: Prepare conceptual layout for the future parking lot shown on the Airport Layout Plan for the project, including: • Provide a conceptual layout of the interior area available for future parking lot, between the existing entrance road segments. • Validate existing entrance road route is compatible with future parking needs. • Provide concept to City of Ames for review in comment. • Incorporate any comments received on conceptual layout in a single effort. Deliverables: • PDF of parking lot concept plan 3. CONSTRUCTION PHASE SERVICES Construction related services are not desired at this time for the project. If the City of Ames desires Bolton and Menk provide any construction related services such as attendance at the pre-construction meeting, construction observation, contract administration, construction administration or construction testing those services could be included in a mutually agreed upon future work order addendum. I.B. ADDITIONAL SERVICES Consulting services performed other than those authorized under Section 1 (Design and Bidding Services) Section 2 (Conceptual Parking Lot Layouts), or Section 3 (Construction Phase Services) above shall be considered not part of the I.A Basic Services and may be authorized by the CLIENT as Additional Services. Additional Services consist of those services that are not generally considered to be Basic Services or Construction Phase Services; or exceed the requirements of the Basic Services or Construction Phase Services; or are not definable prior to the bidding of the project; or vary depending on the technique, procedures, or schedule of the project contractor. Additional services, available upon request, may include: • CONSTRUCTION STAKING. Perform construction staking and furnish necessary equipment and supplies to establish grade and line for the contractor's guidance in construction of the project and in accordance with the contract documents. As part of the plans and specifications for the project, it is assumed that the contractor will be providing layout and construction staking for the project. • CONSTRUCTION TESTING. Perform any construction testing needed in the construction of the proposed improvements and in accordance with the contract documents. As part of the plans and specifications for the project, it is assumed that the contractor will be providing all quality control testing and quality acceptance testing for the project. 7 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 7 • PRECONSTRUCTION CONFERENCE. Preparation, organization or attendance at a preconstruction meeting. • CONSTRUCTION ADMINISTRATION. Perform preparation of construction pay request, preparation of changes orders, review test results, review shop drawings, perform visits to the construction site by the project engineer, conduct final inspections, preparation of punch list and preparation of recommendation of acceptance to the sponsor. • CONSTRUCTION OBSERVATION. Perform any construction observation related to the project. Services typically associated with construction observation include but are not limited to monitoring construction progress, monitoring construction schedule, monitoring general conformance with the plans and specifications, maintaining records of construction progress, evaluating change orders or substitute materials, calculating as-built quantities, preparing as-built plan, attending construction progress meetings and/or performing other services reasonably required by the client and as outlined in the contract documents. • All other services not specifically identified in this work order. I.C. ITEMS PROVIDED BY CLIENT The following items are to be provided by CLIENT: 1. Existing mapping, reports, and other pertinent information 2. Relevant as-built information. I.D. CONSIDERATION The services described above in I.A BASIC SERVICES shall be provided as follows: TASK 1 – DESIGN AND BIDDING SERVICES $ 67,300.00 (lump sum) TASK 2 – CONCEPTUAL PARKING LOT LAYOUT $ 5,400.00 (lump sum) TASK 3 – CONSTRUCTION PHASE SERVICES Not Provided* TOTAL AUTHORIZED FEE $ 72,700.00 * Services available upon completion of a future addendum to work order. Any changes to the scope of work that are not specifically included in this proposal will be considered additional work and a negotiated addendum to the agreement will be completed. Progress payments shall be made in accordance with Section 3 of the MASTER AGREEMENT. 8 Ames Municipal Airport Work Order #6 BMI Project No. 24X.136286.000 \\ames4\h\AMES\24X136286000\0_Airport Entrance Road\A_Project Management\2_Contracts\Contract\Ames-Entrance Road-Iowa-WO 6 - Updated after Client Comments 10-16-2024.docx Page 8 I.E. AUTHORIZATION City of Ames Bolton & Menk, Inc. By: By: Date Ronald A. Roetzel, P.E. Date Aviation Services Manager Attest: Attachments: Exhibit I – Ames Airport Utilities 10/16/2024 9