HomeMy WebLinkAboutA002 - Resolution exercising the option to purchase real property addressed as 2715 Dayton AvenueITEM #:2
DATE:02-18-25
DEPT:POLICE
SUBJECT:PURCHASE OF PROPERTY AT 2715 DAYTON AVENUE FOR FUTURE
ANIMAL SHELTER AND CONTROL FACILITY
COUNCIL ACTION FORM
BACKGROUND:
The City's Animal Shelter, located at 325 Billy Sunday Road, is in need of replacement. The existing
facility is undersized and experiences challenges related to weatherization, mechanical equipment, and
other aging systems. City staff has been working through the planning stages to develop a new animal
shelter facility for the past several years.
In November 2024, staff became aware that the property that until recently housed Eagle’s Loft
day care (2715 Dayton Avenue) was for sale. Staff's impression was that this property presented a
viable opportunity to purchase an existing building and remodel it for an animal shelter facility at
a lower cost compared to constructing an entirely new building. Additionally, this approach
would allow a new space to be occupied sooner compared to constructing a new purpose-built
facility.
The asking price for the 2715 Dayton property is $1.1 million. It is assessed at $1,159,200. The property
consists of a single-story building containing 10,880 square feet, plus a 1,851 square foot basement, and
a 26-stall parking lot on a 5.59 acre site. The building appears to be in good condition and well-kept.
On November 12, 2024, the City Council authorized staff to pursue an option to purchase the property.
Staff secured a $5,000 option to purchase the property on or before February 24 for the asking price of
$1,100,000.
On December 26, 2024, the City Council approved an agreement with INVISION Architecture LTD,
Des Moines, Iowa, to analyze the existing conditions and needs and identify future requirements for a
modern animal shelter facility. Following that evaluation, the INVISION was to provide the City a
conceptual design and a preliminary cost estimate.
Following the selection of the design firm, and following feedback from the Council at its December 10
Budget Guidelines Session, staff presented the City Council with a proposed project budget totaling
$4,455,000 on January 14, 2025, as shown below:
EXPENSES FUNDING SOURCES
Previous Site Investigation $ 4,075
2715 Dayton Purchase Option 5,000
Land Acquisition 1,100,000
Conceptual Design 66,360
Detailed Design/Construction Specs 250,000
Design Contingency 30,000
Construction/Renovation 2,500,000
1
Contingency (10%)250,000
Fixtures/Furnishings/Equipment 250,000
FY 2024/25 Adjusted Budget $ 100,000
Council Priorities Capital Fund 2,855,435
Donations 1,500,000
TOTAL $ 4,455,435 TOTAL $ 4,455,435
note: italicized expenses are estimated
Since the Council discussion on January 14, staff has learned that the fundraising effort has
verbally secured a lead commitment for $3,000,000, exceeding the initial expectations. A signed
pledge is anticipated to be secured this week. It is planned that after this lead gift commitment is
secured, the fundraising effort would continue, in an effort to secure sufficient funding to
complete all the desired components of the project. The goal now is to raise an additional
$1,500,000, which would support a total project cost up to approximately $7,500,000.
The additional fundraising would allow for two significant enhancements to the project. The first
would be a separate addition to the existing structure, dedicated to housing dogs. The consultants
expressed concerns about attempting the modifications to house the dog population within in the
existing structure, since this would require cutting out the floor for drains and significant work
and expense for soundproofing. A dog addition would alleviate those concerns while also
providing more adequate space inside the facility for cats housing and volunteer space.
Volunteers provide over 7,000 hours per year towards the shelter operation and some space for
them was a concern.
The second addition to the project would be the creation of a space for advanced animal care and
procedures. Currently, significant operating budget and donation funds are utilized for spays,
neuters, and other medical needs. An animal care/procedure space area would allow these
procedures to be performed in the shelter by qualified veterinarians. Several local veterinarians
have committed to provide such services at no cost if the space exists for it. It becomes feasible to
dedicate a portion of the existing Dayton building to this use if the dogs are located in a new
addition.
CONSULTANT EVALUATION:
INVISION has toured the Dayton site and reviewed the facility's original construction drawings to
determine whether and how various components might fit into a renovated facility. It is important to
note that this effort was focused on developing rough cost estimates to determine if advancing the
project in this facility is feasible, as opposed to preparing detailed designs of specific spaces. If the
site is pursued, more work will occur to collect feedback from various stakeholders, review
different configurations, and make decisions regarding features such as finishes and amenities.
INVISION has stated the following:
"On behalf of the City of Ames, INVISION / DLI has completed an evaluation of the proposed site and
building at 2715 Dayton Avenue. Constructed in 1995, both the site and building appear to be in good
working condition. Site paving including drive lanes, parking stalls, and sidewalks appears to be in
good conditions along with site grading. Building utility information was provided through utility
drawings. Water service (domestic and fire protection), sewer, and electrical service appear to be in
good condition. Sprinkler service size will need to be confirmed if the final building design includes
2
additions that need to be sprinklered. The building exterior and roof appears to be watertight with no
initial signs of water infiltration within the building. Based on the 1995 construction date of the
building it is anticipated that the exterior building wall insulation may not meet current energy code
requirements and will need to be addressed as part of this project. It is anticipated that most interior
walls within the building will be removed as the current interior configuration is not conducive for the
proposed program and will be revised as part of the project.
Overall, the building and site appear to be in good condition and will work well for the city’s Animal
Shelter Facility."
The consultant's initial evaluation suggests a total project cost (including design and construction,
but excluding property acquisition), ranging between $6,290,000 and $7,812,000, with an average
of $7,051,000. These figures represent renovation of the existing interior space at an average cost of
$327/sq. ft., new construction of a 5,000 sq. ft. dog addition at an average cost of $475/sq. ft.,
equipment costs of approximately $848,500, outside yard work of approximately $120,000, and design
and engineering work of approximately $502,200. The attachment provides further detail regarding this
cost opinion.
It is important for the Council to note that the consultant has been asked to produce these
estimates quickly, in order to allow for this information to be presented before the property
purchase option must be exercised. Therefore, these figures represent conservative estimates. If
the Council approves proceeding with the project, the project features will be refined during
design development to fit within the project budget. Adjustments will need to be made to reflect
equipment and supplies that will be reused from the existing facility rather than being purchased
new, plus design choices that may be made to reduce project costs or divide components into add-
alternates that can be bid and awarded only if available funding is adequate.
FEBRUARY 18 ACTION:
INVISION will provide the Council with a presentation at the Council workshop on February 18. At
that time, the Council will be asked whether to exercise the option to purchase the property. If the
Council chooses to do so, the $1,100,000 purchase price will be financed from the Council Priorities
Capital Improvements Fund, in which the Council has allocated $2,855,435.
ALTERNATIVES:
1. Accept the report and approve the purchase of the property located at 2715 Dayton Avenue in the
amount of $1,100,000.
2. Accept the report, but decline to purchase the property and instead direct staff to prepare a
conceptual design for a new Animal Control facility adjacent the Water Treatment Plant.
3. Refer this item back to staff for further information. The Council should note that the purchase
option expires on February 24 and Council action would be necessary before that date to
continue pursuing the Dayton property.
CITY MANAGER'S RECOMMENDED ACTION:
The site at 2715 Dayton presents an opportunity to redevelop an existing building into a larger and
better quality animal shelter and control facility, in a manner that has a variety of advantages for the
3
City.
First, as indicated to staff by the consultant, the redevelopment is anticipated to be less costly than new
construction of the same square footage at a purpose-built facility.
Second, this Alternative #1 allows the City to proceed without having to rely on a bond referendum to
finance.
Third, since a bond referendum would not be required, this approach would allow the operations to be
moved into the new facility much sooner than a project that requires a referendum.
Fourth and finally, the proposed site contains a substantial amount of area for building expansion or
other City activities. The topography of this area would make it difficult to develop in the future if the
site remained a private development.
The Council should note that once the existing Animal Shelter at Billy Sunday Road is vacated, the
property along Billy Sunday will be able to be sold for commercial development, with the proceeds
replenishing the Council Priorities Capital Improvement Fund or being dedicated to any other purpose
the Council may desire.
The evaluation of the Dayton site by the consultant indicates that both the building and the site
appear to be in good working condition. The parking area, drive lanes and sidewalks are all in
good condition. Water, sewer, and electric are all in good condition and there is already a fire
suppression system (sprinklers) on site. The roof and structure are in good condition with no
leaks or water issues. The consultants believe that overall, the building and site appear to work
well for a new Animal Shelter facility. The anticipated fundraising will allow for additions to the
structure that will provide much needed space to meet the needs of the community for years to
come. If directed to proceed, staff would work to finalize contract details for design development.
Thereafter, the design team would work to refine the design based on feedback from stakeholders
and the available project budget. Therefore, it is the recommendation of the City Manager that the
City Council adopt Alternative No. 1, as described above.
ATTACHMENT(S):
2025.02.13 AMES.IA Costing.pdf
4
Thursday, February 13, 2025
77$ 5,000 sq ft 390,000$ +/- 58,500$ site work
142$ 5,000 sq ft 710,000$ +/- 71,000$ building shell construction
116$ 5,000 sq ft 580,000$ +/- 58,000$ interior construction
10$ 5,000 sq ft 50,000$ +/- 5,000$ fire suppression system
45$ 5,000 sq ft 230,000$ +/- 23,000$ plumbing and cleaning system installation
50$ 5,000 sq ft 250,000$ +/- 25,000$ mechanical HVAC system installation
35$ 5,000 sq ft 180,000$ +/- 18,000$ electrical system installation
475$ 2,000,000$ +/-200,000$
71$ 10,960 sq ft 780,000$ +/- 78,000$ budget for shell insulation, repairs
116$ 10,960 sq ft 1,270,000$ +/- 127,000$ interior construction
10$ 10,960 sq ft 110,000$ +/- 11,000$ fire suppression system
45$ 10,960 sq ft 490,000$ +/- 49,000$ plumbing and cleaning system installation
50$ 10,960 sq ft 550,000$ +/- 55,000$ mechanical HVAC system installation
35$ 10,960 sq ft 380,000$ +/- 38,000$ electrical system installation
327$ 3,580,000$ +/-358,000$
10% 502,200$ +/- 50,000$ architectural & engineering fees
502,200$ +/-50,000$
2,000$ 98 196,000$ +/- 20,000$ cat enclosures
5,000$ 45 225,000$ +/- 23,000$ dog enclosures
400,000$ +/- 80,000$ shelter medicine equipment budget
2,500$ 11 27,500$ +/- 5,500$ workstations
848,500$ +/-128,500$
15$ 2,000 sq ft 30,000$ +/- 6,000$ turf
15$ 2,000 sq ft 30,000$ +/- 6,000$ drainage
30$ 2,000 sq ft 60,000$ +/- 12,000$ portable tent or sunshade
120,000$ +/-24,000$
7,051,000$ +/- 761,000$ expected to be $6.3M to $7.8M
AAMES.IA
Professional Fees
Outside Yards
New Construction
Renovation
Equipment
5