RESOLUTION ACCEPTING COMPLETION OF
2024/25 CLEAR WATER DIVERSION PROGRAM
FOR THE CITY OF AMES, IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2024/25 Clear Water Diversion Program for the City of Ames, Iowa, in accordance with a contract
dated the 11th day of June, 2024, by and between the City of Ames, Iowa, and Iowa Water & Waste
Systems of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2024/25 Clear Water Diversion Program has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $72,848.
Section 3. The amount due Iowa Water & Waste Systems of Ames, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 25th day of February, 2025.
_________________________________ ___________________________________
Renee Hall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Gartin, Junck, Rollins
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 25th day of February, 2025.