HomeMy WebLinkAboutA015 - Fitch Family Indoor Aquatic Center Monthly UpdateTo:Mayor and City Council
From:Keith Abraham, Parks and Recreation Director
Date:January 24, 2025
Subject:Fitch Family Indoor Aquatic Center Monthly Update
Item No. 17
MEMO
PROJECT UPDATE: To keep City Council informed of the construction status of the
Fitch Family Indoor Aquatic Center (FFIAC), staff will provide a written update at
Council's second meeting of each month. Additionally, staff, along with representatives
from Story Construction and RDG Planning and Design, will provide an in-person update
once per quarter (January, April, July, & October). If anything occurs during the project
that requires Council action, staff will present this in a timely manner. The City's
Construction Manager for the project, Story Construction, has provided a Project Status
Report (Attachment A).
Story Construction and RDG Planning and Design are 89% complete with reviewing
shop drawings and submittals. This activity will continue until 100% complete.
CHANGE ORDER SUMMARY: There were three change orders recently approved.
An updated change order log is shown as Attachment B. To date, change orders for the
project total $245,524, or 1.4% of the construction budget. The contingency for this
project is $2.1 million with a current balance of $1,854,476. There is also $1 million set
aside for mitigation of contamination issues, which has not been used at this time.
ATTACHMENT(S):
Attachment A - Story Construction Monthly Project Status Report 2025-1.pdf
Attachment B - Change Order Log - 1-28-25.pdf
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
Page 1 of 3
Fitch Family Indoor Aquatic Center
Monthly Project Status Report
January 2025
PROGRESS THIS PAST MONTH:
1. The Natatorium precast concrete columns and wall panels have all been set. This included a
successful multi-day closure of one west-bound lane of Lincoln Way to set the south side
materials.
2. All the Natatorium structural steel has been set.
3. The Natatorium steel roof decking is nearing completion.
4. Precast concrete and structural steel erection began in the areas of the building outside of the
Natatorium.
5. The grouting process at the base of the precast concrete wall panels and columns began.
6. Sealant installation began at the joints between the precast concrete wall panels. The Building
Envelope Consult mock up is complete and periodic inspections are ongoing.
7. Installation of temporary enclosures began in preparation for temporarily heating the
Natatorium once the roofing is installed.
8. A temporary stair-tower was installed to access the Natatorium roof.
9. The Building Envelope Consult pre-installation meeting was held for the roofing system.
10. Special Inspections and Testing of structural steel welds, masonry, and base-of-precast grout
continued and are ongoing.
11. Submittals and Requests for Information continued to be processed between the Bid Package
Contractors, Story Construction, and RDG Planning & Design.
WORK PLANNED FOR NEXT MONTH:
1. Finish the installation of the Natatorium steel roof decking.
2. The installation of the Natatorium roofing is planned to begin.
3. Temporary enclosures will be completed in the Natatorium.
4. Fire sprinkler piping and electrical conduit work is planned to begin in the Natatorium ceiling.
5. Precast concrete and structural steel erection for the areas of the building outside of the
Natatorium will continue.
6. Masonry will continue to follow along with the sequence of the structural steel erection.
7. Joint sealant work will continue at the joints between the precast concrete wall panels.
SCHEDULE SUMMARY:
Construction Substantial Completion Date: November 15, 2025
Page 1 of 5
2
Aerial Photos
Description
Taken Date
01/17/2025 at 02:31 pm
Upload Date
01/17/2025 at 02:55 pm
Uploaded By
Mitch Anderson
Name
DJI_0392.jpg
Aerial Photos
Description
Taken Date
01/17/2025 at 02:30 pm
Upload Date
01/17/2025 at 02:55 pm
Uploaded By
Mitch Anderson
Name
DJI_0389.jpg
Story Construction Co.
Printed on Mon Jan 20, 2025 at 02:56 pm CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 1 of 2
Building Site - View to SW
Building Site - View to SE
Page 2 of 5 3
Aerial Photos
Description
Taken Date
01/17/2025 at 02:30 pm
Upload Date
01/17/2025 at 02:55 pm
Uploaded By
Mitch Anderson
Name
DJI_0385.jpg
Story Construction Co.
Printed on Mon Jan 20, 2025 at 02:56 pm CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 2 of 2
Description
Taken Date Uploaded By
01/10/2025 at 03:26 pm Eli Rochleau
Upload Date File Name
01/13/2025 at 02:43 pm
Album
Progress
Description
Taken Date Uploaded By
01/10/2025 at 03:27 pm Eli Rochleau
Upload Date File Name
01/13/2025 at 02:43 pm
Album
Progress
Building Site - View to NW
Mech/Elec Equipment Rm Natatorium - Staging Roof Decking on Roof Joists
Page 3 of 5 4
Description
Taken Date Uploaded By
01/16/2025 at 03:42 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:04 pm
Album
Progress
Description
Taken Date Uploaded By
01/16/2025 at 03:42 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:04 pm
Album
Progress
Description
Taken Date Uploaded By
01/16/2025 at 03:42 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:05 pm
Album
Progress
Description
Taken Date Uploaded By
01/16/2025 at 03:41 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:05 pm
Album
Progress
Story Construction Co.
Printed on Mon Jan 20, 2025 at 03:17 pm CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 1 of 3
Natatorium Interior - View to SW past Wellness Pool Natatorium Interior - View to SE
Natatorium Interior - View to East North Precast Wall of Locker Room Corridor
Page 4 of 5 5
Description
Taken Date Uploaded By
01/16/2025 at 03:40 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:05 pm
Album
Progress
Description
Taken Date Uploaded By
01/16/2025 at 03:37 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:05 pm
Album
Progress
Description
Taken Date Uploaded By
01/16/2025 at 03:36 pm Deb Thurmond
Upload Date File Name
01/20/2025 at 03:05 pm
Album
Progress
Story Construction Co.
Printed on Mon Jan 20, 2025 at 03:17 pm CST
Job #: 23401-01 Fitch Family Indoor Aquatic Center
115 N Elm Avenue
Ames, Iowa 50010
Page 2 of 3
South Precast Wall of Locker Rooms Precast Elevation at Locker Rooms
Precast North Elevation
Page 5 of 5 6
Contractor Change
Order #Description Amount Balance
Beginning Contingency
Balance $ 2,100,000
All Star Concrete 1 Precast Enbeds Install Change Contracts $ 10,010 $ 2,089,990
Core Construction 1 IDPH Permit Review, Precast Panel Joint Mods, Mechanical Louver Mods, Steel
Lintel, Precast Enbeds Install Change Contracts $ 22,065 $ 2,067,925
Core Construction 2 Misc. Structural Revisions & South Elevation Glazing Revised $ 3,979 $ 2,063,946
Lansink Construction 1 Wet Room Door Change, Multipurpose Room Cubbies $ 42,129 $ 2,021,817
Lansink Construction 2 Door 115A Change to FRP $ 2,858 $ 2,018,959
Lansink Construction 3 Interior Finishes $ 3,021 $ 2,015,938
Central States Roofing 1 IDPH Permit Review, Mechanical Louver Mods $ 1,647 $ 2,014,291
Orning Glass Company 1 Wet Room Door Changes $ (3,823) $ 2,018,114
Orning Glass Company 2 Window Frit Revisions $ 1,743 $ 2,016,371
Hilsabek Schacht 1 Wet Room Door Change $ - $ 2,016,371
Hilsabek Schacht 2 Door 115A Change to FRP $ - $ 2,016,371
Hilsabek Schacht 3 Donor Wall Drywall $ 3,557 $ 2,012,814
Sande Construction 1 IDPH Permit Review Updates $ 1,370 $ 2,011,444
Brockway Mechanical 1 Hydronic Pumps Flow Update $ (2,320) $ 2,013,764
Brockway Mechanical 2 IDPH Permit Review Updates, 6" Storm Drain Relocation, Mechanical Louver Mods,
Glycol Feed Dual Pump $ 38,702 $ 1,975,062
Brockway Mechanical 3 State Requirements $ 12,033 $ 1,963,029
Van Maanen Electric 1 IDPH Permit Review Updates $ 21,953 $ 1,941,076
Van Maanen Electric 2 Transformer Relocate $ 14,237 $ 1,926,839
Van Maanen Electric 3 Light Fixture SWA Dimming $ 4,679 $ 1,922,160
Con-Struct 1 Water Service Disconnect $ 7,747 $ 1,914,413
Con-Struct 2 Building Rubble Removal $ 45,419 $ 1,868,994
Iowa Pipe & Grading 1 Storm & Existing Water Utility Conflict & Sanitary Tie in at N. 2nd Ave $ 14,518 $ 1,854,476
Totals / Current Balance $ 245,524 $ 1,854,476
FITCH FAMILY INDOOR AQUATIC CENTER
CHANGE ORDER LOG
(As of 1/28/25)
Highlighted Rows Indicate New Change Orders Since the Last Update
7