HomeMy WebLinkAboutA002 - Motion approving Report of Change OrdersTo:Mayor & City Council
From:City of Ames Purchasing Division
Date:January 9, 2024
Subject:Report of Contract Change Orders
Item No. 4
MEMO
The Report of Change Orders for periods December 1-15, 2024, and December 16-31,
2024, are attached for your review and consideration.
ATTACHMENT(S):
Change Order Report - December 1-15, 2024.docx
Change Order Report - December 16-31, 2024.docx
City Clerk's Office 515.239.5105 main
515.239.5142 fax
515 Clark Ave. P.O. Box 811
Ames, IA 50010
www.CityofAmes.org
1
REPORT OF
CONTRACT CHANGE ORDERS
Department
General Description
of Contract
Contract
Change
No.
Original Contract
Amount Contractor/ Vendor
Total of Prior
Change Orders
Amount this
Change Order
Change
Approved By
Purchasing
Contact
(Buyer)
Electric
Services
Engineering Services for
Standby Generation for the
Power Plant
1 $100,118.00 Farris Engineering $0.00 $5,600.00 D. Kom AM
Public Works 2022/23 North Sunset
Ridge Sanitary Sewer
2 $941,044.50 Rognes Corporation $0.00 $-(1,094.66)J. Joiner KS
Parks &
Recreation
Construction Materials
Testing Services for Fitch
Family Indoor Aquatic
Center
2 $89,338.00 Terracon Consultant Inc.$92,965.00 $4,110.00 K. Abraham KS
Facilities /
Parks &
Recreation
Ames Downtown Plaza 16 $4,633,000.00 Henkel Construction
Company
$-(2,039.69)$0.00 C. Mellies KS
Transit CyRide 2023 Shop
Rehabilitation
8 $390,165.00 R.H. Grabau Construction
Inc.
$75,880.54 $-(5,165.00)J. Rendall AM
Water &
Pollution
Control
Lagoon Biosolids Disposal 1 $105,625.00 Wulfekuhle Injection and
Pumping
$0.00 $1.61 T. Ver Meer QE
Period:1st – 15th
16th – End of Month
Month & Year:December 2024
For City Council Date:January 14, 2025
2
REPORT OF
CONTRACT CHANGE ORDERS
Department
General Description
of Contract
Contract
Change
No.
Original Contract
Amount Contractor/ Vendor
Total of Prior
Change Orders
Amount this
Change Order
Change Approved
By
Purchasing
Contact
(Buyer)
Public Works Ames Plan 2040 Sanitary
Sewer Infrastructure (256th
St Extension) Design
1 $273,330.00 WHKS & Co.$0.00 $0.00
Change in
Scope
M. Bryngelson KS
$$$
$$$
$$$
$$$
$$$
Period:1st – 15th
16th – End of Month
Month & Year:December 2024
For City Council Date:January 14, 2025
3