RESOLUTION ACCEPTING COMPLETION OF
2020/21 CONCRETE PAVEMENT IMPROVEMENTS PROGRAM
(FORD ST., BELL AVE., S. 17TH ST., S. KELLOGG AVE.)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2020/21 Concrete Pavement Improvements Program (Ford St., Bell Ave., S. 17th St., S. Kellogg
Ave.) for the City of Ames, Iowa, in accordance with a contract dated the I Oth day of May, 2022,
by and between the City of Ames, Iowa, and Con-Struct Inc. of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2020/21 Concrete Pavement Improvements
Program(Ford St.,Bell Ave., S. 17th St., S. Kellogg Ave.)has been fully completed by
the Contractor in accordance with the terms of the contract and is hereby accepted and
approved.
Section 2. The total cost of the contract is $664,014.
Section 3. The amount due Con-Struct Inc. of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 13th day of August, 2024.
�5w-
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Junck
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 13th day of August, 2024.