HomeMy WebLinkAbout~Master - Completion of Inis Grove Restroom Renovation Project RESOLUTION NO. 24-006
RESOLUTION ACCEPTING COMPLETION OF
INIS GROVE RESTROOM RENOVATION PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Parks and Recreation Department has filed a certificate of completion for
the Inis Grove Restroom Renovation Project for the City of Ames, Iowa, in accordance with a
contract dated the 141h day of March, 2023, by and between the City of Ames, Iowa, and HPC,
LLC., of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Inis Grove Restroom Renovation Project has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $135,000.
Section 3. The amount due HPC, LLC., of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 9th day of January, 2024.
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Junck
Voting aye: Beatty-Hansen, Betcher, Gartin, Junck, Rollins
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 9th day of January, 2024.