HomeMy WebLinkAbout~Master - Completion of 2022/23 Asphalt Street Pavement Improvements (28th Street) RESOLUTION NO. 23-563
RESOLUTION ACCEPTING COMPLETION OF
2022/23 ASPHALT STREET PAVEMENT IMPROVEMENTS (28TH STREET)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2022/23 Asphalt Street Pavement Improvements (28th Street) for the City of Ames, Iowa, in
accordance with a contract dated the 13th day of December, 2022, by and between the City of
Ames, Iowa, and Manatt's Inc, of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2022/23 Asphalt Street Pavement Improvements
(28th Street) has been fully completed by the Contractor in accordance with the terms
of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $867,082.40.
Section 3. The amount due Manatt's Inc, of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 24th day of October, 2023.
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 24th day of October, 2023.