RESOLUTION ACCEPTING COMPLETION OF
FURNISHING 69kV SF6 CIRCUIT BREAKERS AND CAPACITOR BANK
FOR TOP-0-HOLLOW SUBSTATION
ON CONTRACT WITH SIEMENS INDUSTRY,INC., OF RICHLAND, MISSISSIPPI
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Furnishing 69kV SF6 Circuit Breakers and Capacitor Bank for the Top-O-Hollow Substation for
the City of Ames, Iowa, in accordance with a contract dated the 10th day of April, 2018, by and
between the City of Ames, Iowa, and Siemens Industry, Inc, of Richland, Mississippi.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for Furnishing four 69kV SF6 Circuit Breakers for the
Top-O-Hollow Substation has been fully completed by the Contractor in accordance
with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $150,442 (inclusive of Iowa sales tax).
Section 3. The amount due Siemens Industry, Inc., of Richland,Mississippi, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26th day of September, 2023.
�5w-
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 26th day of September, 2023.