HomeMy WebLinkAbout~Master - Accepting Completion of 2022/23 Downtown Street Pavement Improvements - Alley (5th St to 6th St from Duff to Douglas) RESOLUTION NO. 23-450
RESOLUTION ACCEPTING COMPLETION OF
2022/23 DOWNTOWN STREET PAVEMENT IMPROVEMENTS —ALLEY
(5TH ST—6TH ST BETWEEN DUFF AVE TO DOUGLAS AVE)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2022/23 Downtown Street Pavement Improvements —Alley (5th St— 6th St between Duff Ave to
Douglas Ave)for the City of Ames,Iowa,in accordance with a contract dated 141h day of February,
2023,by and between the City of Ames, Iowa, and Brothers Concrete, of Des Moines, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2022/23 Downtown Street Pavement
Improvements—Alley(5th St—6th St between Duff Ave to Douglas Ave)has been fully
completed by the Contractor in accordance with the terms of the contract and is hereby
accepted and approved.
Section 2. The total cost of the contract is $103,933.30.
Section 3. The amount due Brothers Concrete, of Des Moines, Iowa,is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8th day of August, 2023.
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Gartin, Junck, Rollins
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 81h day of August, 2023.