RESOLUTION APPROVING CHANGE ORDER NO. 5
ON CONTRACT WITH
HENKEL CONSTRUCTION COMPANY
FOR AMES DOWNTOWN PLAZA PROJECT
(STEVEN L. SCHAINKER PLAZA)
FOR THE CITY OF AMES,IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above Contract; and,
WHEREAS, the City should not be responsible for the costs associated with the Change
Order due to site conditions being known during the site design. Thus, staff is directed to seek
reimbursement from the design consultant.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No. 5 in the amount of $37,285.03 on contract with Henkel Construction
Company of Ames, Iowa, for the Ames Downtown Plaza Project (Steven L. Schainker Plaza) be
approved and adopted as attached hereto and made a part hereof by this reference.
ADOPTED THIS 1 Ith day of April, 2023.
e4 W- 4�z e
Renee hall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 1 Ith day of April, 2023.