HomeMy WebLinkAbout~Master - Accepting the 2019/20 Sanitary Sewer Rehabilitation (Basin 10) project as Complete RESOLUTION NO. 22-579
RESOLUTION ACCEPTING COMPLETION OF
2019/20 SANITARY SEWER REHABILITATION (BASIN 10)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2019/20 Sanitary Sewer Rehabilitation (Basin 10) for the City of Ames, Iowa, in accordance with
a contract dated 9th day of February, 2021,by and between the City of Ames, Iowa, and Municipal
Pipe Tool Co., LLC, of Hudson, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2019/20 Sanitary Sewer Rehabilitation(Basin 10)
has been fully completed by the Contractor in accordance with the terms of the contract
and is hereby accepted and approved.
Section 2. The total cost of the contract is $814,323.71.
Section 3. The amount due Municipal Pipe Tool Co.,LLC, of Hudson, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8th day of November, 2022.
Renee kall, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 8th day of November, 2022.