RESOLUTION ACCEPTING COMPLETION OF
WATER TREATMENT PLANT REMOTE SITE RADIO AND POWER LINE
COMMUNICATIONS UPGRADES PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Water Department has filed a certificate of completion for the Water
Treatment Plant Remote Site Radio and Power Line Communications (PLC)Upgrades Project for
the City of Ames,Iowa,in accordance with a contract dated the 14th of May,2021,by and between
the City of Ames, Iowa, and Jetco, Inc., of Altoona, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Water Treatment Plant Remote Site Radio and
Powerline Communications Upgrades Project has been fully completed by the
Contractor in accordance with the terms of the contract and is hereby accepted and
approved.
Section 2. The total cost of the contract is $82,434.
Section 3. The amount due Jetco, Inc., of Altoona, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 1 lth day of October, 2022.
Renee Nall, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Gartin
Voting aye: Beatty-Hansen, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: Betcher
Resolution declared adopted and signed by the Mayor this 1 lth day of October, 2022.