Loading...
HomeMy WebLinkAbout~Master - Approving Change Order No. 3 for Flood Mitigation - River Flooding (Ioway Creek) RESOLUTION NO. 22-389 RESOLUTION APPROVING CHANGE ORDER NO. 3 ON CONTRACT WITH KELLER EXCAVATING, INC., FOR FLOOD MITIGATION -RIVER FLOODING(IOWAY CREEK) FOR THE CITY OF AMES,IOWA WHEREAS, it has been determined that a Change Order is necessary and proper on the above Contract. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa, that Change Order No. 3 in the amount of$223,713.72 on contract with Keller Excavating,Inc.,of Boone,Iowa,for the Flood Mitigation-River Flooding(Ioway Creek)be approved and adopted as attached hereto and made a part hereof by this reference. ADOPTED THIS 12t' day of July, 2022. Diane R. Voss, City Clerk John A. Haila, Mayor Introduced by: Junck Seconded by: Beatty-Hansen Voting aye: Beatty-Hansen, Corrieri, Gartin, Junck, Rollins Voting nay: None Absent: Betcher Resolution declared adopted and signed by the Mayor this 12'day of July, 2022. CITY OF AMES PVHLIC WORKS - ENGINEERING DIVISION Date 6Jul-22 "TV- CONTRACT CHANGE ORDER#�3 P.O.#59961 >_; A me S ACCT#VARIOUS PROJECT: loway Creek Restoration & Flood Mitigation Protect CONTRACTOR CHANGE ORDERS APPROVED TO DATE: 1 $107,340.00 11 PREVIOUS APPROVED Keller Excavating - - 2 $19,572.20 12 CHANGE ORDERS (Name) 3 13 $126,912.20 1133 155th Street 4 14 ORIGINAL CONTRACT ----------------------------------------- (Address) 5 15 $3,327,523.50 Boone, IA 50036 6 16 CURRENT ADJUSTMENT ---- ---------------------------------------- (City,State.Zip) 7 17 $223,713.72 8 18 CUMULATIVE CHANGE 9 19 ORDER AMOUN' 10 20 $243.285.92 Requires City Council Approval 40.NSTE0 coroTRAC7 $3,678,149.42 The contract is hereby modified and amended as follows: ITEM DESCRIPTION UNIT PRICE QUANTITY TOTAL 4.7 Jet existing storm sewer(approx 160 LF -lour $260.00 32.00 S8,320.00 4.8 Clean out silt from jelling Hour $250.00 3.00 S750.00 4.9 48"Storrs Sewer Apron EA $2,900.00 1.00 $2,900.00 4.10 Relay 12"RCP Storm Sewer in NW Quadrant LS $6,320.00 1.00 S6,320.00 4.11 12"Storm Sewer Apron LS $3,160.00 1.00 $3 100.00 4.12 30"Storm Sewer Headwall and Fla ate EA $13,833.00 1.00 $13,833.00 4.13 30-RCP Storm Sewer LF 1 $190.00 50.00 $9,500.00 9.10 Additional Rip-Rap,Class E Revetment Ton $53.00 481.22 $25,504.66 2.8 Removal Concrete Pad/Foundation LS $10,978.D0 1 $10.978.00 2.9 Removal/Cut Existing Steel Sheet Pile LS $26,525.00 1.00 $26.625.00 7.5 Pedestrian Ramps at 1100 Buckeye Ave LS $5,145.30 1.00 $5.145.30 2.10 Sift Tires and Garbage NE/NW quadrants LS $10,170.00 1.00 $10.170.00 Balancing CO Items To Date: 2.4 Modified Subbase TON $39.00 247,08 $9,636.12 2.5 Modified Granular Subbase TON $41.00 80.00 $3,280.00) 2.6 Special Backfill TON $34.00 329.72 $11,210.48 4.1 Removal of Storm Sewer LF $30.00 333.00 $9.990.00 4.4 Storm Sewer,Trenched.36"RCP LF $200.00 2.00 (S400.00 5.3 8"Gate Valve&Box EA $2,300.00 1.00 (S2.300.00) 6.7 Connect to Existing Manhole EA 1 $3,000.00 1.00 S3,000.00 6.9 Remove Manhole 96'� EA $2,000.00 1 00 ($2.000.00) 6.10 Remove Intake EA $600.00 1.00) (S500.00) 6.11 Connect to Existing Storm Sewer EA $3,000.00 1.00 $3,000.00 7.1 PCC Pavement,6" SY $58.00 98.49 $5,712.42 7.2 PCC Curb and Gutter,6"Standard LF $24.00 79.50 $1,908.00 7.3 1HMA Pavement.6" SY $107 00 63.53 $6,79771 9.1 Tem ora Seeding And Mulching AC 1 $880.00 (15.00) ($13.200.00) 9.8 Temporary Rolled Erosion Control Product,Type 2D SY $1.65 7.500.00 $12.375.00) 9.9 Wattles LF $2.75 12,801.00 $35,202.75 9.12 Stabilized Construction Entrance SY $30.00 1,260.77 $37,823.10 9.19 Root Wads EA $550.00 5.00 $2,750.00 10.3 Regulated Waste Disposal Ton $110.00 150.00 $16.500.00) 10.4 Non-Re ulated Waste Disposal Ton $77.00 931.28 $71,708.56 Extend Cam letion Date to:November 11 2022 It is mutually agreed that the contract price is increasedydecreased by Total:1 $223,713.72 payable/deductible immediately upon completion of the work called for in this order As a result of this change order. t)-,e time for completion of the above-mentioned contract is hereby extended by an additional 0 days. This change order is incorporated into and governed by the above mentioned contract. A ed to g Recommended fp[4p2mtaFbytti9 City of Ames: 7 7 c"n, Dery Muria aI En o er For the Cry of Ames 7-7- _7 h► Zti Works D+reclar Dear 51,We."gal aY e^ Date Page 1 f `- CC:Project Engineer,PW Mgmt.Asst.,Finance.Contractor 7/6i2022 6:08 PM