HomeMy WebLinkAbout~Master - Completion of Fire Station No. 1 HVAC Replacement Project RESOLUTION NO. 22-081
RESOLUTION ACCEPTING COMPLETION OF
FIRE STATION NO. 1 HVAC REPLACEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS,the Fire Department has filed a certificate of completion for the Fire Station No.
1 HVAC Replacement Project for the City of Ames,Iowa,in accordance with a contract dated April
13, 2021,by and between the City of Ames, Iowa, and Mechanical Comfort Inc., of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Fire Station No. 1 HVAC Replacement Project has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $114,434.
Section 3. The amount due Mechanical Comfort Inc.,of Ames,Iowa,is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 22nd day of February, 2022.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Junck
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Rollins
Voting nay: None Absent: None