HomeMy WebLinkAbout~Master - Awarding a Contract to Confluence for Design and Construction Management of the Downtown Plaza RESOLUTION NO. 21-428
RESOLUTION AWARDING A CONTRACT TO CONFLUENCE FOR DESIGN AND
CONSTRUCTION MANAGEMENT OF THE DOWNTOWN PLAZA
FOR THE CITY OF AMES,IOWA
WHEREAS,the City Council initially discussed features and amenities for a new Downtown
Plaza at its November 24,2020,meeting as it relates to the City Council Goal to"begin construction
of downtown community space in 2021"; and,
WHEREAS,on December 8,2020,the City Council directed staff to proceed with preparing
a conceptual design for a plaza at the site located east of City Hall known as Parking Lot N; and,
WHEREAS, the City hired Confluence,Inc., to help create concepts for the Lot N site that
addresses the goals for the project as a new amenity and attraction to Downtown; and,
WHEREAS, the scope of work included an outline of the City Council's ideas for features
to include in the concept and Confluence worked with the City's team to address these City Council
interests and refine a concept for public comment; and,
WHEREAS, Confluence developed multiple designs that integrated art,water features,and
ice skating into a Plaza concept; and,
WHEREAS, Confluence,along with City staff,hosted an online public meeting in January
2021 to review the preferred concept and to gauge interest in preferred features; and,
WHEREAS,the City also had two weeks of public input through an online survey and online
comment options; and,
WHEREAS,the City Council has included funding for$3.7 million for the Downtown Plaza
project as part of the budget approval for FY 2021/22, and in July 2021,the City Council requested
Confluence's opinion regarding its confidence in the February 2021 cost estimate, given the
increasing volatility in the market for construction materials; and,
WHEREAS, the final concept accepted by the City includes a water feature known as a
runnel that flows through the site and ends in a spray feature for summer activity as well as a ribbon
ice skating loop for winter activities; and,
WHEREAS, the Plan also includes hardscape and green landscaped areas, benches, small
stage for performances, year-round public restrooms, support for food trucks, and public art; and,
WHEREAS, the next step in realizing a Downtown Plaza is to move forward with final
design and construction documents for bidding; and,
WHEREAS, the project scope also includes the addition of angled parking in front of City
Hall along Clark Avenue; and,
WHEREAS, a multi-disciplinary team is needed for the integrated features of the Plaza,
which will consist of a landscape architect, civil engineer, water feature designer, ice skating
designer,and an architect are all needed,at a minimum,to complete the design work for the project;
and,
WHEREAS,City staff have also determined that construction management of the project is
a necessary service for the project once the award of a contract for construction occurs; and,
WHEREAS, due to support for the Conceptual Plan prepared by Confluence and the
necessary integrated nature of the design team, staff approached Confluence for a proposed scope
of service as the lead consultant for the Project; and,
WHEREAS, Confluence provided a scope of services that matches the expectations of the
City for design needs as well as the overall timeline for the project; and,
WHEREAS,current City of Ames Purchasing Policies require competitive written proposals
for Professional Services over $50,000 and due to the need to meet the desired timeline and
Confluence's work on the conceptual design of the plaza, staff is recommending waiving the City's
Purchasing Policies and Procedures for competitive bidding of professional services and hire
Confluence for the design of the Plaza; and,
WHEREAS, the scope of services provided by Confluence for the design and construction
management and to meet the timeline to construct next summer has a fee of$325,250; and,
WHEREAS, staff has reviewed the costs proposed by Confluence and found them to be
reasonable for the scope of the project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Contract for the design and construction management for the Downtown Plaza is awarded
to Confluence of Des Moines, Iowa in the amount of$325,250.
ADOPTED THIS 27`h day of July, 2021.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Martin
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27'day of July, 2021.