HomeMy WebLinkAboutA6 ITEM # 2
DATE: 07-24-13
CITY OF AMES
DEPARTMENT OF PLANNING AND HOUSING
REPORT TO THE ZONING BOARD OF ADJUSTMENT
DATE PREPARED: July 19, 2013
CASE FILE NO.: ZBA 13-08
REQUEST : To allow a portable cellular tower at 1325 South 4th Street during ISU
football season
PROPERTY OWNER: Randall Corporation
CONTACT: Shelley Trampetti, St. Paul, MN
LOCATION: 1325 South 4th Street
ZONING: "A" Agriculture
BACKGROUND AND PROJECT DESCRIPTION:
Shelley Trampetti, representing Verizon Wireless, is seeking to place a portable cellular
tower on land near Jack Trice Stadium in order to provide acceptable coverage during
peak call times on home football Saturdays. The site is shown on Attachment A. This
temporary service had been provided in the past by placing the portable cellular tower
on land owned by the University which did not subject it to City of Ames zoning
regulations. However, the University has decided not to allow this use so Verizon found
an alternative site on private land near the stadium. A Special Use Permit was issued
last year for this purpose on this same property.
The project is described as a cell-on-wheels, sometimes referred to as a "COW." It is a
trailer with a pneumatically operated tower that will rise to a height of 28 feet, which is a
reduction from the 69 foot tower from last year. The trailer will also contain the
necessary electronic equipment. The trailer will be surrounded by a six-foot tall wood
fence. Electricity will be available from the City and will be provided from an adjacent
power pole.
The applicant has stated that the COW will be in service from approximately one week
before the first home ISU football game to one week following the last home game. It
will be in service the entire time. By leaving the tower in operation during this time, it
would reduce the need for cellular technicians to visit the site to turn the equipment on
and off.
1
40,
APPLICABLE LAW:
Specific criteria and design standards for wireless communication facilities are found in
Section 29.1307.
(7) Standards for Special Use Permit. The following standards and procedures, in addition
to those contained in Section 29.1503, shall apply to the issuance of a Special Use Permit
for a cell site with antenna:
(a) Necessity. The wireless communications company shall demonstrate, using
technological evidence, that the antenna must be located where it is proposed in
order to satisfy the antenna's function in the company's grid system.
(b) Co-location Effort. If the wireless communications company proposes to build a
tower(as opposed to mounting the antenna on an existing tall structure), it shall
demonstrate that it contacted the owners of tall structures within a one-quarter-
mile radius of the site proposed, asked for permission to install the antenna on
those tall structures, and was denied for reasons other than failure to agree on
compensation. The Zoning Board of Adjustment may deny the permit if it
concludes that the applicant has not made a good faith effort to mount the antenna
on an existing tall structure.
(c) Antenna Height. The applicant shall demonstrate, to the reasonable satisfaction of
the Zoning Board of Adjustment, that the antenna is the minimum height required
to function satisfactorily. No antenna that is taller than this minimum height shall
be approved.
(d) Setbacks from Base of Antenna Support Structure. The minimum distance
between the base of the support or any guy anchors and any property line shall be
the largest of the following:
(i) 50% of antenna height;
(ii) The minimum setback in the underlying Zone; or
(iii) 60 feet.
(e) Antenna Support Structure Safety. The applicant shall demonstrate, to the
reasonable satisfaction of the Zoning Board of Adjustment, that the proposed
antenna and support structure are safe and the surrounding areas will not be
negatively affected by support structure failure, falling ice or other debris, or radio
frequency interference. All support structures shall be fitted with anti-climbing
devices, as approved by the manufacturers.
(f) Fencing. An opaque fence constructed of wood or masonry material, or other
substantial material, that is consistent with the existing structures on the proposed
site and approved by the Zoning Board of Adjustment, shall be installed around
the antenna support structure and other equipment unless the antenna is mounted
on an existing structure.
(g) Co-location. In order to reduce the number of antenna support structures needed
in the community in the future, the proposed support structure shall be required to
accommodate other users, including other wireless communications companies
and local police, fire and ambulance companies.
(h) FCC License. The wireless communication company shall provide proof that it is
licensed by the Federal Communications Commission.
2
(i) Required Parking. If the cell site is fully automated, adequate parking shall be
required for maintenance workers. If the site is not automated, the number of
required parking spaces shall equal the number of people on the largest shift. .
(j) Painting. Antenna support structures should be painted in such a manner as to
reduce the visual impact and create a harmonious appearance with its
surroundings.
(k) Site Plan. A full site plan shall be required for all cell sites, showing the antenna,
antenna support structure,building, fencing, buffering, and access.
(1) Air Safety. Support structures 200 feet in height or taller, or those near airports,
shall meet all Federal Aviation Administration regulations.
In addition, Chapter 29, Section 29.1503(4)(a) and (e) of the Municipal Code states the
following:
(4) Review Criteria. Before a Special Use Permit application can be approved, the Zoning
Board of Adjustment shall establish that the following general standards, as well as the
specific standards outlined in subsection (b) below, where applicable, have been or shall
be satisfied. The Board's action shall be based on stated findings of fact. The conditions
imposed shall be construed as limitations on the power of the Board to act. A mere
finding that a use conforms to those conditions or a recitation of those conditions,
unaccompanied by specific findings of fact, shall not be considered findings of fact for
the purpose of complying with this Ordinance.
(a) General Standards. The Zoning Board of Adjustment shall review each
application for the purpose of determining that each proposed use meets the
following standards, and in addition, shall find adequate evidence that each use in
its proposed location will:
(1) Be harmonious with and in accordance with the general principles and
proposals of the Land Use Policy Plan of the City;
(ii) Be designed, constructed, operated, and maintained so as to be
harmonious in appearance with the existing or intended character of the
general vicinity and that such a use will not change the essential character
of the area in which it is proposed;
(iii) Not be hazardous or disturbing to existing or future uses in the same
general vicinity;
(iv) Be served adequately by essential public facilities and services such as
highways, streets, police, fire protection, drainage structure, refuse
disposal, water and sewage facilities, and/or schools;
(v) Not create excessive additional requirements at public cost for public
facilities and services;
(vi) Not involve uses, activities, processes, materials, equipment or conditions
of operation that will be detrimental to any person, property or general
welfare by reason of excessive production of traffic, noise, smoke, fumes,
glare, or odors; and
(vii) Be consistent with the intent and purpose of the Zone in which it is
proposed to locate such use.
3
(e) Conditions. The Board may impose such additional conditions it deems
necessary for the general welfare, for the protection of individual property rights,
and for ensuring that the intent and objectives of this Ordinance will be observed.
Any development in the City is also subject to the Development Standards of Article 4.
PUBLIC COMMENTS:
Notification was made to all owners of property within 200 feet. In addition, a notice of
public hearing was placed on the property at 1325 S. 4th Street. As of this writing, no
comments have been received.
FINDINGS OF FACT & CONCLUSIONS:
Based upon the project description and the submitted site plan and additional material,
the following findings of fact and conclusions may be made.
Findings:
1. The proposed use is allowed in the Agricultural Zoning District.
2. Section 29.1307 provides criteria for wireless communication facilities. No
distinction is noted between temporary and permanent facilities.
a. The applicant has provided information that there is a need for the tower
to serve the increased traffic during home football games. A similar tower
was approved and used last season on this site. The tower has been
reduced in height from the 69 feet approved last year to 28 feet proposed
this year.
b. The applicant and City staff has reviewed the area and there are no
suitable existing structures for collocation.
c. The applicant has stated that this height allows for the minimal coverage
needed. A greater height is limited by the type of tower and the need for
guy wires which are not permitted.
d. The tower is set back 125 feet from the nearest property line. The required
minimum is 60 feet.
e. The City's Inspection Division has reviewed the submitted exhibits and
finds that they meet City standards for safety.
f. Opaque wood fencing with gates is proposed.
g. This temporary cell tower is not designed to accommodate additional
users.
h. The FCC license has been issued for Verizon.
i. A parking area is adjacent to the tower.
j. The tower will be bare aluminum.
k. A site plan has been submitted.
I. This item is not applicable for the height of the proposed tower.
3. Section 29.1503 provides criteria for all uses in any zone.
a. This use is a direct result of University activities (although it is outside the
designated "University Impacted" areas of the Land Use Policy Plan.
4
l
b. The site is in an area that is heavily impacted during home football games.
However, there are residential uses to the west and north of this site.
There will only be noise from the air-conditioner unit to cool the
equipment. No generator will be used.
c. The tower rises 28 feet above grade. There are trees in the area to
provide screening. The site will generate a minimum amount of noise as
the equipment will be connected to power and fiber optic utilities thus
minimizing the noise. No generator will be used.
d. Except for electricity and fiber optic, the site will need no other public
infrastructure.
e. The City is responsible for police and fire coverage of the site. It is
unknown what the demand for these services might be.
f. The only noise anticipated is the air conditioner.
g. The purpose of the Agricultural zone is for uses that are agriculture or
"undeveloped for urban uses."
4. Article 4 describes certain other development standards that must be met.
a. Any parking area must be paved with asphalt or concrete. The applicant
proposes to use the existing rock that has been laid down within the past
two years.
b. Landscape screening between all parking areas and adjacent residential
zones and rights-of-way is required.
5. The site is within the Floodway Fringe Overlay District. A Flood Plain
Development Permit has been submitted. It will need to be approved prior to
establishing the use on the site.
Conclusion:
City staff has reviewed the information submitted by the applicant. In most respects,
staff concludes that the criteria of Section 29.1307 and Section 29.14003 have been
met, except as noted below. In addition, the development standards of Article 4 have
been met except as noted below.
The Board does not have the right to waive any of the standards of the zoning
regulations. In this instance, though, the Board may defer installation of certain
improvements provided an acceptable financial security is held by the City. The
installation of permanent paving and landscaping for a temporary use may not be
necessary if a bond is held by the City. The terms of the bond would be such that if the
cell tower were not removed within a reasonable time limit, the City would draw upon
the bond and install the required improvements. Staff will recommend this option
deferring the installation of the required improvements.
ALTERNATIVES:
1. The Zoning Board of Adjustment may approve the Special Use Permit for Cell Site
with Antenna at 1325 S. 4th Street as detailed on the Site Plan (prepared by SSC,
INC. and dated July 11, 2013) with the adoption of the findings of fact and
5
conclusions stated herein, and subject to the following condition:
The required landscaping and paving may be deferred until May 1, 2014 provided
the applicant submit financial security in a form acceptable to the City for that
amount noted in the engineer's estimate of probable cost of improvements ($15,000)
that satisfy the City's development standards. Said security would be valid until
drawn upon by the City or returned to the applicant.
2. The Zoning Board of Adjustment may approve the Special Use Permit for Cell Site
with Antenna at 1325 S. 4th Street as detailed on the Site Plan (prepared by SSC,
INC. and dated July 11, 2013) by adopting its own findings of fact and conclusion.
3. The Zoning Board of Adjustment may deny the Special Use Permit for Cell Site with
Antenna at 1325 S. 4th Street if the Board finds and concludes that the proposed
Special Use Permit is not consistent with adopted policies and regulations, or that
the Special Use Permit will impose impacts that cannot be reasonably mitigated.
4. The Zoning Board of Adjustment may table this request for a Special Use Permit for
Cell Site with Antenna and request additional information from City staff or the
applicant.
RECOMMENDED ACTION:
The City has a mechanism for the review and approval of wireless communications
facilities. However, the City's experience has been with traditional permanent facilities,
either a freestanding pole or mounted on existing tall structures. This is the second time
this type of temporary request as been made. The site and proposal for the COW are
very similar to the previous application; therefore, staff is proposing the same conditions
as in the previous application.
Staff's analysis of the submitted information finds that, for the most part, the criteria
have been met and the development standards are satisfied. The issue of parking and
landscaping remain. The site has only gravel installed. For this use to install
approximately 140 feet of asphalt and plant shrubs and trees along its entire length for a
use that will go away by Thanksgiving is an investment that Verizon is not willing to
make. Staff agrees that this requirement appears to be directed at more permanent
installations. Staff believes that a deferral of this requirement, provided that appropriate
financial security is in place, is appropriate.
Therefore, based upon the Findings of Fact and Conclusions above, it is the
recommendation of the Department of Planning and Housing that the Zoning Board of
Adjustment act in accordance with Alternative #1. This is a recommendation to approve
the Special Use Permit for Cell Site with Antenna at 1325 S. 4th Street as detailed on
the Site Plan (prepared by SSC, INC. and dated July 11, 2013) with the adoption of the
findings of fact and conclusions stated herein, and subject to the following condition:
The required landscaping and paving may be deferred until May 1, 2014 provided the
applicant submit financial security in a form acceptable to the City for that amount noted
6
s
in the engineer's estimate of probable cost of improvements ($15,000) that satisfy the
City's development standards. Said security would be valid until drawn upon by the City
or returned to the applicant.
SAPLAN_SHR\Council Boards Commissions\ZBA\Special Use Perm its\1325_S_4th_Cell_Tower-07-24-13.docx
7
Attachment A
Location Map
UJ S
N
LU
� �w � S•3RD ST a'
� f
x0
J
TER" R uNi a
� p
Subject Property N
'��� �• w ., �"� S 4TH ST -g4TH ST
� y i
� U• > . � � � p�� �'� ill IN��Vi �
" ym 0 Sy l'��ti III
<µ
_ � m
S 4TH ST��" S 4TH ST ' S:4TH§ST" m
l vy,.
N"
LU
>
°
3
Location Map
1325 S. 4th Street
N
0 50100 200 300 400 500
Feet
8