RESOLUTION ACCEPTING COMPLETION OF
2017/18 RIGHT-OF-WAY RESTORATION
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2017/18 Right-of-Way Restoration for the City of Ames,Iowa,in accordance with a contract dated
August 28,2018,by and between the City of Ames,Iowa,and GreenTech of Iowa,of Grimes,Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2017/18 Right-of-Way Restoration has been fully
completed by the Contractor in accordance with the terms of the contract and is hereby
accepted and approved.
Section 2. The total cost of the contract is $130,966.20.
Section 3. The amount due GreenTech of Iowa of Grimes,Iowa,is hereby ordered paid
as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8'day of December, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None