RESOLUTION APPROVING A PROFESSIONAL SERVICES AGREEMENT WITH
BOLTON&MENK,INC., FOR WORK-ORDER NO.2 FOR THE FY 2020/21 AIRPORT
IMPROVEMENTS (RUNWAY 01/19 AIRFIELD LIGHTING)
FOR THE CITY OF AMES, IOWA
WHEREAS,in September 2019,staff initiated a professional service procurement process for
projects shown in the Ames Airport Improvement Program (AIP) in accordance with the City's
purchasing policies; and,
WHEREAS,following Federal Aviation Administration(FAA)procedures,this procurement
established consulting services for all projects shown in the AIP; and,
WHEREAS, Bolton and Menk, Inc., was selected and the City Council approved a contract
on February 11, 2020, for the first project(Electrical Vault)under Work Order No. 1; and,
WHEREAS,the runway lighting project is the second in the series,referred to by the FAA as
Work Order No. 2; and,
WHEREAS,the Professional Services contract will be for all design,survey,and construction
inspection required for the next phase of airfield lighting replacements, which includes the main
Runway 0l/19 and minor connecting taxiway lighting; and,
WHEREAS, the project was originally shown in the FY 2021/22 Airport Improvements
Program of the Capital Improvements Plan(CIP)with a total budget of$637,575;however,because
the Federal Government issued additional funding under the CARES Act(100%with no local match)
it allowed airports nationwide to finance their FY 2020/21 projects with CARES funds and"move up"
the other project in their plan; and,
WHEREAS,the normal FAA entitlement money the Ames Airport received for FY 2020/21
can now be planned to be used on this Runway 0 1/19 lighting project, and it should be noted that the
project order in the draft 2021-2026 CIP will be adjusted to account for the effect of the CARES Act
funding bill; and,
WHEREAS,FAA funding covers 90%of the project(up to$573,817),with a local match of
$63,758 coming from the Airport Construction Fund; and,
WHEREAS,the current balance of the Airport Construction Fund is$369,051 and the design
and construction observation services in this contract(WO No. 2)are not to exceed$99,900(Federal
Share=$89,910 and Local Share= $9,990).
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Ames,Iowa,that
the Professional Services Agreement with Bolton&Menk,Inc.,of Ames,Iowa, for Work-Order No.
2 for the FY 2020/21 Airport Improvements (Runway 0l/19 Airfield Lighting) project at a not-to-
exceed amount of$99,900 is hereby approved.
ADOPTED THIS 10`'' day of November, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 10'day of November, 2020.