HomeMy WebLinkAbout~Master - Completion of 2014/15 Storm Water Facility Rehabiliation Program (Somerset Subdivision) RESOLUTION NO. 20-569
RESOLUTION ACCEPTING COMPLETION OF
2044/15 STORM WATER FACILITY REHABILITATION PROGRAM
(SOMERSET SUBDIVISION)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2014/15 Storm Water Facility Rehabilitation Program for the City of Ames, Iowa, in accordance
with a contract dated August 13,2019,by and between the City of Ames,Iowa,and Con-Struct,Inc.,
of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2014/15 Storm Water Facility Rehabilitation
Program has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $322,763.70.
Section 3. The amount due Con-Struct, Inc., of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 27`h day of October, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Gartin
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27' day of October, 2020.