RESOLUTION ACCEPTING COMPLETION OF
2018/19 ASPHALT STREET PAVEMENT IMPROVEMENTS
(FLORIDA AVE., RELIABLE ST., HUTCHISON ST.,DELAWARE AVE.)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2018/19 Asphalt Street Pavement Improvements(Florida Avenue,Reliable Street,Hutchison Street,
and Delaware Avenue) for the City of Ames, Iowa, in accordance with a contract dated July 23,
2019,by and between the City of Ames, Iowa, and Con-Struct, Inc., of Ames, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2018/19 Asphalt Street Pavement Improvements
(Florida Avenue,Reliable Street,Hutchison Street,and Delaware Avenue)has been fully
completed by the Contractor in accordance with the terms of the contract and is hereby
accepted and approved.
Section 2. The total cost of the contract is $1,003,171.74.
Section 3. The amount due Con-Struct, Inc., of Ames, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 28`h day of July, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 28'day of July, 2020.